BHEL Wins Rs 6,500 Crore Adani Order for Six 800 MW Units
Key highlights
- BHEL received an Adani Power Letter of Award worth more than Rs 6,500 crore, excluding GST.
- The order covers steam turbine generators and auxiliaries for six 800 MW thermal units, representing 4,800 MW.
- BHEL will supervise erection, testing and commissioning, with execution tied to Adani Power's project timelines.
- BHEL shares closed at Rs 264.05 on the BSE on the reported Friday, down Rs 0.55 or 0.21%.
powered by IRIS

Bharat Heavy Electricals Ltd (BHEL) has received a Rs 6,500 crore order, excluding GST, from Adani Power Ltd to supply equipment and supervisory services for six thermal power units of 800 MW each. The contract adds 4,800 MW of unit-level equipment scope to BHEL's order pipeline and reinforces its role in coal-based power project execution.
Know Bharat Heavy Electricals inside out
Results, valuation, peers and who's buying, in one view.
What has BHEL won from Adani Power?
BHEL has received a Letter of Award from Adani Power for the supply of steam turbine generators and associated auxiliaries for six thermal units, each rated at 800 MW. The order is valued at more than Rs 6,500 crore, excluding GST, according to BHEL's regulatory disclosure.
The scope also includes supervision of erection, testing and commissioning. BHEL will therefore provide both the main turbine-generator equipment and technical oversight during the installation and start-up stages of the units. The total capacity represented by the six units is 4,800 MW.
Adani Power is the customer for the order, while BHEL is the equipment supplier and supervisory services provider. BHEL said the transaction is domestic and does not fall under the related-party transaction category. The disclosure did not identify the specific power projects or locations where the six units will be installed.
How will the six-unit order be executed?
BHEL said equipment deliveries and services will be aligned with Adani Power's internal project timelines. No fixed completion date, plant-wise allocation or delivery schedule was disclosed in the announcement. This means the execution timetable will depend on the customer's project requirements.
The contract covers supervision rather than a stated full turnkey construction role. BHEL's responsibilities include supplying steam turbine-generator sets with auxiliaries and overseeing erection, testing and commissioning. These activities are central to preparing thermal generating units for operation, but the disclosure does not provide details on civil works, fuel arrangements or other project packages.
The Letter of Award establishes the commercial award for the equipment and services. BHEL's filing described the order value as exceeding Rs 6,500 crore excluding GST. It did not provide a break-up between equipment supply, auxiliary systems and supervisory work.
How does this compare with BHEL's earlier Adani Power contracts?
The latest order follows three supercritical thermal power contracts worth more than Rs 11,000 crore, excluding GST, that BHEL received from Adani Power and its subsidiary Mahan Energen Ltd in August 2024. Those agreements covered boiler, turbine and generator equipment, along with erection and commissioning supervision, for three projects of 2x800 MW each.
The 2024 contracts involved Kawai Phase-II and Kawai Phase-III in Rajasthan, and Mahan Phase-III in Madhya Pradesh. Each project had a planned capacity of 1,600 MW, taking the combined capacity of the three projects to 4,800 MW. BHEL stated that the Kawai Phase-II, Kawai Phase-III and Mahan Phase-III projects had scheduled completion periods of 49 months, 52 months and 55 months respectively.
The new Rs 6,500 crore award is separate from the previously reported Rs 11,000 crore contracts. While both sets of orders relate to 800 MW thermal units and include BHEL's turbine-generator capabilities, the latest filing does not disclose whether its six units are linked to any of the projects previously named.
Got a follow-up? Ask IRIS
Why does the order matter for BHEL and the power equipment sector?
The order provides BHEL with a sizable domestic equipment supply and services mandate in the thermal power segment. Its value exceeds Rs 6,500 crore before GST, and the order involves six large 800 MW units. Such units require high-capacity turbine-generator systems and coordinated commissioning support.
For BHEL, the award adds to its work with Adani Power on supercritical coal-based generation projects. The earlier August 2024 contracts were for complete boiler, turbine and generator packages, while the new award is specifically described as covering steam turbine generators, auxiliaries and supervision. The distinction matters because the contract scope determines the equipment BHEL will supply and the work it will undertake.
The order also highlights continued project activity involving 800 MW coal-fired units. The source material notes that Adani Power has upcoming 800 MW supercritical unit plans across states including Madhya Pradesh, Chhattisgarh, Rajasthan and Uttar Pradesh. However, BHEL has not disclosed the project locations covered by this latest award, so no specific site allocation can be confirmed.
What was the immediate market and investor context?
BHEL shares ended at Rs 264.05 on the BSE on the reported Friday, down Rs 0.55, or 0.21%. The reported closing movement provides the immediate trading context available alongside the order announcement, but it does not establish that the contract caused the day's share-price change.
For investors, the disclosed facts are the order value, the 4,800 MW aggregate equipment scope, and the absence of a published execution deadline. The timeline will be governed by Adani Power's project requirements, which limits visibility on the precise schedule of deliveries and supervisory activity from the information released.
The company also clarified that the award was made by a domestic entity and was not a related-party transaction. This disclosure addresses the nature of the transaction, while the execution and financial recognition of the order will depend on progress under the customer's project schedule.
Conclusion
BHEL's new Adani Power award is valued at more than Rs 6,500 crore excluding GST and covers steam turbine generators, auxiliaries, and supervisory services for six 800 MW units. The order represents 4,800 MW of equipment-linked capacity and follows BHEL's earlier Adani-linked contracts for three 2x800 MW supercritical projects.
The key issue to watch is the project execution schedule, as BHEL has said deliveries and services will follow Adani Power's internal timelines. Investors will also look for any future disclosure identifying the six project locations, detailing the delivery programme, or clarifying the order's progress through equipment supply and commissioning stages.