Swastik Infra Frame Limited gets 97% revenue from EPC
Ask Iris
Swastik Infra Frame Limited is principally a turnkey power engineering, procurement and construction contractor rather than an equipment manufacturer: EPC Power Projects generated Rs 487.823 crore, or 97%, of Fiscal 2026 revenue from operations. Its asset-light model assigns part of erection work to third-party contractors while Swastik retains centralized procurement, engineering oversight and project management.
How dependent is Swastik on power EPC revenue?
Swastik is dependent on power EPC contracts because this vertical generated Rs 487.823 crore of its Rs 503.573 crore Fiscal 2026 revenue from operations. Engineering, procurement and construction, or EPC, means responsibility spanning engineering and material procurement through construction, testing and commissioning. The sale-of-products vertical, involving power cables and other electrical items, generated the remaining Rs 15.7502 crore, or 3%, in Fiscal 2026.
The revenue mix became more concentrated in EPC over the three reported fiscal years. EPC revenue was 90% of Fiscal 2024 revenue from operations at Rs 188.2789 crore, then rose to 97%, or Rs 339.0432 crore, in Fiscal 2025 and remained at 97% in Fiscal 2026. Product sales moved in the opposite direction, declining from 10% of operating revenue, or Rs 21.2964 crore, in Fiscal 2024 to 3% in each of Fiscal 2025 and Fiscal 2026.
What does Swastik’s turnkey EPC work include?
Swastik’s turnkey EPC scope runs from survey and design to supply, erection, installation, testing and commissioning of power infrastructure. Its stated activities include underground cabling, gas-insulated substations, air-insulated substations, rural and urban electrification, street lighting, and renewable-energy works. As of July 31, 2026, Swastik reported laying 18,579.47 kilometres of distribution lines and completing 36 power-distribution infrastructure projects across six Indian states.
A turnkey contract leaves Swastik responsible for delivering a completed project to the client under agreed specifications. In item-rate contracts, payment is based on agreed rates multiplied by quantities actually executed; in percentage-rate contracts, compensation is determined as an agreed percentage above or below the total project cost. Swastik reported an aggregate completed-project contract value of Rs 764.67 crore since 2012, compared with its first power EPC project in 2012, which had a contract value of Rs 60 lakh.
How does Swastik use subcontractors without giving up control?
Swastik subcontracts a portion of a project, specifically erection work, to third-party contractors that deploy their own on-site manpower and equipment. The company does not state that it self-performs every construction activity. It retains the material side of execution through a centralized procurement team that supplies construction materials and electrical equipment to support standardized quality and cost efficiency.
Swastik says its on-site engineers and project managers monitor work in progress against design specifications, quality standards and project timelines. As of July 31, 2026, it had 65 engineers and technicians in project execution within a workforce of 182 full-time employees. It also hires contract labour based on factors including project location, size and duration through contractors supplying skilled and unskilled labour.
The allocation of erection work to subcontractors is distinct from Swastik’s contractual responsibility to clients. Under EPC agreements, Swastik remains responsible for survey, investigation, design, engineering, procurement, construction, permits, testing and superintendence. Completion includes third-party physical verification of installed stock and site work before the final bill, followed by a defect-liability period that typically lasts 12 months.
Why is Swastik’s model described as asset-light?
Swastik’s asset-light model relies on leasing project-specific equipment from third-party lessors rather than owning heavy machinery and equipment. The company says this approach reduces fixed-asset investment and equipment-maintenance requirements while allowing equipment use to be adjusted to projects in multiple states. The arrangement operates alongside the use of third-party contractors for erection activities.
Fixed-asset turnover, a ratio comparing revenue with fixed assets, was 78.90 times in Fiscal 2024, 153.67 times in Fiscal 2025 and 70.72 times in Fiscal 2026. The Fiscal 2026 ratio was lower than the Fiscal 2025 level but was below neither the company’s stated model nor an asset-base benchmark disclosed in the source. The reported movement shows that the ratio changed as operations expanded from Rs 209.5753 crore of revenue in Fiscal 2024 to Rs 503.5732 crore in Fiscal 2026.
The model still requires working capital because Swastik purchases and supplies project materials and bills for both material supply and execution milestones. Net working capital rose from Rs 51.989 crore in Fiscal 2024 to Rs 162.033 crore in Fiscal 2025 and Rs 249.636 crore in Fiscal 2026. Continued asset-light execution therefore depends on procurement coordination, milestone billing, client payments, leased equipment and subcontractor availability.
What scale and concentration shape Swastik’s EPC operations?
Swastik had 18 ongoing EPC projects across six states with aggregate contract value of Rs 2,036.65 crore as of July 31, 2026, of which Rs 916.5546 crore was balance work value. Its order book is the anticipated revenue from the unexecuted part of ongoing contracts for which relevant preconditions, including letters of intent or allotment, have been met. Rajasthan represented Rs 553.9694 crore, or 60.44%, of that balance-work order book.
Revenue was also concentrated among clients, although the largest-client share declined over the three fiscal years. The top client generated Rs 158.3165 crore, or 31.44%, of Fiscal 2026 revenue, compared with 39.18% in Fiscal 2025 and 60.97% in Fiscal 2024. The top five clients accounted for Rs 487.823 crore, or 96.87%, of Fiscal 2026 revenue, making contract awards, execution and payment performance from a limited client group material to the business model.
Swastik’s Fiscal 2026 order book, measured at the end of that fiscal year, was Rs 687.4352 crore and represented 1.41 times revenue from operations, compared with 1.92 times in Fiscal 2025 and 2.08 times in Fiscal 2024. The subsequent Rs 916.5546 crore balance-work figure as of July 31, 2026 reflects ongoing projects at that later date. The two measures use different dates and should not be treated as the same period-end figure.
Conclusion
Swastik’s reported model is a procurement-led turnkey EPC structure: power projects accounted for 97% of Fiscal 2026 operating revenue, while subcontractors performed part of on-site erection. Swastik retains responsibility for engineering, material supply, supervision, testing and commissioning, so the model depends on controlling the project lifecycle rather than owning the equipment used at every site.
The next operational test is execution of the Rs 916.5546 crore balance work as of July 31, 2026, including distribution, transmission and renewable-energy projects. Swastik has disclosed plans to expand into power transmission, railway electrification and solar electrification and to implement an enterprise resource planning system, while delivery will depend on project awards, working-capital availability, subcontractor execution and milestone compliance.
Frequently Asked Questions
Did your stocks survive the war?
See what broke. See what stood.
Live Q1 Earnings Tracker
