Capex/Expansion
Borana Weaves: Delay in 9.9 MW Hybrid Project
Borana Weaves Ltd reports further delay in commissioning its 9.9 MW hybrid power project at Kalikanagar. Revised schedule: WTG+7.65 MW solar by end-Oct 2026; second WTG by end-Nov 2026; third by end-Dec 2026. Delays due to weather and transmission shutdown issues.