Ashoka Buildcon L1 bids total Rs 2,791 crore for NHAI projects
Key highlights
- Ashoka Buildcon was declared L1 bidder for two NHAI projects worth Rs 2,791 crore excluding GST on November 18, 2024.
- The two NH 116A projects in West Bengal cover about 84.186 km in total.
- The Kharagpur to Chandrakona-Ghatal package carries a Rs 1,400 crore quoted bid.
- Each HAM project has a stated execution period of 910 days, including monsoon.
powered by IRIS

Ashoka Buildcon Limited was declared the lowest bidder for two National Highways Authority of India projects in West Bengal, with aggregate quoted bids of Rs 2,791 crore excluding GST on November 18, 2024. The two NH 116A economic-corridor projects are to be delivered under the Hybrid Annuity Mode and carry an execution period of 910 days each.
Know Ashoka Buildcon inside out
Results, valuation, peers and who's buying, in one view.
What did Ashoka Buildcon bid for in the NHAI projects?
Ashoka Buildcon submitted the lowest bids for two four-lane economic-corridor packages on NH 116A in West Bengal. The company disclosed the L1 status to stock exchanges under Regulation 30 of the SEBI Listing Obligations and Disclosure Requirements Regulations, 2015.
The larger of the two bids, at Rs 1,400 crore excluding GST, is for Package-1 of the Kharagpur to Chandrakona-Ghatal Road Crossing section. The work covers the stretch from km 0.000 to km 41.000 of NH 116A and is part of the Kharagpur-Siliguri Economic Corridor under Bharatmala Pariyojana.
The second bid, at Rs 1,391 crore excluding GST, covers Package-3 between Bowaichandi and the Guskara-Katwa Road section. This package spans km 89.814 to km 133.000 of NH 116A. Together, the two packages cover about 84.186 km based on the disclosed project lengths.
What are the key details of Ashoka Buildcon's two bids?
The two projects have a combined quoted bid price of Rs 2,791 crore excluding GST, and each has a stipulated execution period of 910 days, including monsoon. Both are four-lane economic-corridor works under the Hybrid Annuity Mode, or HAM.
For Package-1, Ashoka Buildcon's quoted amount of Rs 1,400 crore was above the stated NHAI estimated cost of Rs 984.86 crore. For Package-3, the Rs 1,391 crore bid was above the stated estimate of Rs 1,231.32 crore. These figures indicate that the project estimates and final L1 bid values differed across both packages.
L1 status identifies the lowest bidder in the tender process. The November 18 disclosure said Ashoka Buildcon had been declared the lowest bidder; it did not itself state that the contracts had been awarded. A later report said the company received a Letter of Award for the Rs 1,391 crore Package-3 project.
Got a follow-up? Ask IRIS
How does the Hybrid Annuity Mode work for these road projects?
The projects are structured under HAM, a road-project model used by NHAI for developing highway infrastructure. The source identifies both NH 116A packages as HAM projects, rather than conventional standalone EPC works.
The Kharagpur-Siliguri Economic Corridor is being developed within Bharatmala Pariyojana, the Government of India's road connectivity programme. The two disclosed packages form parts of that corridor and focus on expanding specified stretches of NH 116A to four lanes.
The stated 910-day execution timetable includes the monsoon period. This is relevant for project planning because civil construction schedules need to account for seasonal conditions as well as the scale of highway and corridor works. The available disclosures provide the bid values, route sections, lengths and schedule, but do not provide a detailed construction milestone plan.
Why do these NHAI bids matter for Ashoka Buildcon investors?
The Rs 2,791 crore aggregate value represents a material disclosed pipeline opportunity for Ashoka Buildcon, subject to the tender process and project-specific award steps. It adds two identified West Bengal highway packages to the company's record of participating in NHAI road tenders.
The market relevance lies in the size and visibility of the quoted bids, as well as the 910-day execution period. For investors, the L1 announcement establishes Ashoka Buildcon's position in the bidding process but should be distinguished from project revenue recognition, which depends on the subsequent award and execution of the work.
The two bids also illustrate the competitive tender environment in national highway construction, where companies compete against NHAI project estimates. Package-1's Rs 1,400 crore quoted bid was higher than the stated Rs 984.86 crore estimate, while Package-3's Rs 1,391 crore bid was above its Rs 1,231.32 crore estimate.
For road users and the affected region, the projects concern planned four-laning on two sections of NH 116A. The disclosed work scope is focused on economic-corridor development in West Bengal, connecting the named Kharagpur, Chandrakona-Ghatal, Bowaichandi and Guskara-Katwa sections.
Conclusion
Ashoka Buildcon's L1 status for the two NHAI packages placed Rs 2,791 crore of quoted highway work in its disclosed tender pipeline. The projects cover about 84.186 km of NH 116A in West Bengal, are linked to the Kharagpur-Siliguri Economic Corridor, and are scheduled for completion within 910 days each under HAM.
The next point to watch is the completion of tender-related award processes for both packages and progress on execution after award. The available information confirms a later Letter of Award for the Rs 1,391 crore Bowaichandi to Guskara-Katwa project, while the November 18 filing recorded L1 status for both projects.