Key highlights
- CG Power received the Maharashtra Pollution Control Board direction on 4 November 2026.
- The 3 November 2026 order requires closure of all manufacturing activities at the Waluj plant.
- The direction cites alleged breaches of the Water Act, 1974 and Air Act, 1981.
- CG Power said on 5 November 2026 that the financial impact was not ascertainable.
powered by IRIS

CG Power and Industrial Solutions Limited received a Maharashtra Pollution Control Board direction on 4 November 2026 to close all manufacturing activities at its Waluj plant, citing alleged breaches of the Water Act, 1974 and Air Act, 1981. CG Power said in its 5 November 2026 filing that the financial impact was not ascertainable.
Know CG Power & Industrial Solutions inside out
Results, valuation, peers and who's buying, in one view.
What has the Maharashtra Pollution Control Board ordered CG Power to do?
The Maharashtra Pollution Control Board has directed CG Power to close all manufacturing activities at its Waluj plant through a letter dated 3 November 2026. The order applies to the unit at Plot No. D-2, D1/2, MIDC, Waluj, Chhatrapati Sambhajinagar, according to CG Power’s stock-exchange disclosure dated 5 November 2026.
The disclosed instruction covers all manufacturing activities at the identified plant, rather than a specified production line or process. CG Power said it received the direction on 4 November 2026, one day after the board issued its 3 November 2026 letter.
CG Power reported the matter under Regulation 30 of the Securities and Exchange Board of India Listing Obligations and Disclosure Requirements Regulations, 2015. Its 5 November 2026 filing was addressed to BSE Limited, where its scrip code is 500093, and the National Stock Exchange of India, where its scrip ID is CGPOWER.
Which Waluj facility and laws does the closure direction cover?
The closure direction covers CG Power’s plant at Plot No. D-2, D1/2, MIDC, Waluj, Chhatrapati Sambhajinagar. The 3 November 2026 direction does not identify affected machines, product categories, manufacturing volumes or business segments within the Waluj unit.
CG Power disclosed alleged violations of the Water (Prevention and Control of Pollution) Act, 1974 and the Air (Prevention and Control of Pollution) Act, 1981. In its 5 November 2026 covering letter, CG Power said the direction was issued under the Water Act and/or the Air Act and the rules framed under those laws.
The annexure to the 5 November 2026 filing records alleged contraventions of both the 1974 Water Act and the 1981 Air Act. It does not disclose the alleged conduct, any pollution parameters, inspection findings, earlier notices or a monetary penalty linked to the Waluj plant.
When did CG Power receive the Waluj manufacturing closure order?
CG Power received the Maharashtra Pollution Control Board direction on 4 November 2026, while the board’s letter directing closure is dated 3 November 2026. CG Power made the regulatory disclosure on 5 November 2026 under reference number COSEC/115/2026-27.
The disclosed timeline runs from the board’s 3 November 2026 letter to CG Power’s receipt on 4 November 2026 and its market announcement on 5 November 2026. The filing does not state an implementation deadline, an appeal date, an interim order or any subsequent communication from the board.
CG Power’s 5 November 2026 announcement also cites a Securities and Exchange Board of India master circular dated 30 January 2026. The annexure identifies the authority, the nature of the 3 November 2026 order, the 4 November 2026 receipt date, the alleged legal breaches and the available assessment of financial impact.
Got a follow-up? Ask IRIS
What financial and operating impact has CG Power disclosed?
CG Power said the financial impact of the Waluj closure direction was not ascertainable as of 5 November 2026. The filing provides no revenue, profit, production, inventory, customer-commitment, employee or downtime figure for the Waluj plant.
The operating effect disclosed is that the order covers all manufacturing activities at one identified Waluj facility. In comparison, CG Power provided no rupee estimate or period-on-period financial comparison connecting the closure direction to quarterly, annual or plant-level earnings.
CG Power did not disclose whether production could be shifted from Waluj to another facility or whether any customer deliveries would be affected. The only quantified dates in the filing are the 3 November 2026 order date, the 4 November 2026 receipt date and the 5 November 2026 disclosure date.
How is CG Power responding to the pollution board direction?
CG Power said it was reviewing the 3 November 2026 direction and would take appropriate action. Its 5 November 2026 filing does not provide a timetable for that review or a date for any possible resumption of manufacturing at Waluj.
CG Power stated that it is committed to complying with applicable environmental laws and regulations. The filing treats the Water Act, 1974 and Air Act, 1981 matters as alleged violations and does not set out CG Power’s account of the underlying facts.
The filing does not specify whether CG Power’s response will involve a representation to the board, remedial work, a legal challenge or another measure. It also does not disclose any compliance target, restoration condition or planned update date following the 4 November 2026 receipt of the direction.
Conclusion
The Maharashtra Pollution Control Board’s 3 November 2026 direction requires closure of all manufacturing activities at CG Power’s identified Waluj plant, with CG Power receiving it on 4 November 2026. The 5 November 2026 disclosure establishes the alleged Water Act and Air Act breaches but leaves the effect on revenue, profit and production unquantified.
The next point to watch is CG Power’s stated review and its unspecified appropriate action after the 5 November 2026 filing. A further update would be needed to clarify whether the order changes, what remedial or legal measures CG Power takes, and when the financial impact can be assessed.