Deccan Gold Mines Reports ₹6.35 Crore PAT From Jonnagiri Sales
Key highlights
- Deccan Gold Mines reported ₹87.16 crore of Q1 revenue from sales of 59.001 kg of gold at Jonnagiri.
- The Q1 headline cited ₹6.35 crore PAT from Jonnagiri gold sales.
- Altyn Tor produced its first gold doré on 5 August 2026.
- Deccan Gold Mines deployed ₹32.53 crore at Altyn Tor during the quarter.
powered by IRIS

Deccan Gold Mines Limited reported ₹6.35 crore profit after tax from Jonnagiri gold sales in its Q1 update, alongside revenue of ₹87.16 crore from the sale of 59.001 kg of gold. The update also detailed progress at the Altyn Tor Gold Project in the Kyrgyz Republic, where first gold doré was produced in August 2026.
Know Deccan Gold Mines inside out
Results, valuation, peers and who's buying, in one view.
What did Deccan Gold Mines report from Jonnagiri in Q1?
Deccan Gold Mines reported Q1 revenue of ₹87.16 crore from sales of 59.001 kg of gold at Jonnagiri. The supplied Q1 headline stated that profit after tax was ₹6.35 crore from Jonnagiri gold sales. These figures place Jonnagiri at the centre of the company's reported operating update during the period.
The company is associated with Geomysore Services India Private Limited, which was separately reported to have generated gold sales and earned profit of ₹28.81 crore. Deccan Gold Mines' share of that reported profit was ₹7.49 crore. The supplied material does not provide a reconciliation between this associate-level profit figure and the ₹6.35 crore PAT cited in the Q1 headline.
How has the Altyn Tor project moved toward production?
Deccan Gold Mines said its Altyn Tor Gold Project in the Kyrgyz Republic produced its first gold doré on 5 August 2026. The project is operated through Kyrgyz subsidiary Avelum Partner LLC. The first doré production was presented as validation of the Intensive Leach System and Merrill-Crowe processing technology under operating conditions.
Earlier project updates had described the gravity plant as commissioned and the first-phase leaching circuit as expected to enable doré bar production. The company also said that semi-processed gold inventory had been generated at the site. More than 250 expatriate and local personnel were mobilised during commissioning activity, while another update referred to nearly 130 Indian technical professionals working with the local workforce.
The reported production timetable changed as commissioning progressed. The company had previously targeted commercial operations from August 2026, while another Q1 update referred to full-scale production in September or October 2026. These targets were subject to completion of trials, commissioning of the leach circuit and tailings facility, and mine-planning work.
Got a follow-up? Ask IRIS
Why is Altyn Tor important to Deccan Gold Mines?
Altyn Tor is Deccan Gold Mines' overseas gold project and its investment through Avelum Partner LLC was described as the first investment by an Indian mining and exploration company in the Kyrgyz Republic to reach the production stage. The project marks a shift beyond the company's traditional focus on gold exploration in India toward operating mining assets internationally.
The company's disclosed portfolio also includes nickel-copper-platinum group element work in Chhattisgarh, tungsten and tin projects in Spain, and lithium and tantalum interests in Mozambique. It holds a 32% stake in Kalevala Gold Oy, with an option to increase that holding to as much as 75% as the project advances. These assets indicate that the company is pursuing both gold and critical-mineral opportunities across several jurisdictions.
Altyn Tor was included in the Kyrgyz Republic's national inauguration programme scheduled for 11 September 2026 during Independence Day celebrations. A social-media post cited in the supplied material said the processing plant was inaugurated online by Kyrgyz President Sadyr N. Japarov on 12 September 2026. The supplied reports therefore contain different dates for the programme and inauguration event.
What are the financial and operational points for investors?
The Q1 sales update gives investors a reported revenue measure for Jonnagiri, while Altyn Tor remains in the commissioning and production-ramp-up phase described in the supplied material. Deccan Gold Mines deployed ₹32.53 crore toward Altyn Tor during the quarter as it progressed toward commercial operations. No share-price movement, consolidated revenue, production cost, or cash-flow figure was provided in the material.
The project has also been associated with production expectations of 300 kg to 350 kg of gold in FY27. Separate estimates cited in the material referred to 180 kg in 2026, 350 kg annually in 2027, and a peak potential of 800 kg annually in three to four years. These are company expectations and potential figures rather than reported production results.
For the broader mining sector, the development illustrates the execution requirements involved in moving from exploration to production overseas. Processing-circuit commissioning, tailings infrastructure, staffing, resource drilling and revised mine planning remain relevant operational factors at Altyn Tor. The available updates do not disclose final trial outcomes or confirm that full-scale commercial production has been achieved.
Conclusion
Deccan Gold Mines' Q1 update combines reported Jonnagiri gold sales of ₹87.16 crore with a stated PAT of ₹6.35 crore, while its Altyn Tor asset has reached first doré production. The figures show an operating gold-sales contribution from Jonnagiri and a parallel transition of the Kyrgyz project from development into commissioning and early production activity.
The next disclosed points to watch are completion of the leach circuit and tailings facility, the outcome of remaining trial runs, revised mine planning and further resource drilling at Altyn Tor. Investors can also track whether the company provides a definitive commercial-production date and reported output against its stated FY27 production expectations.