Dharan Infra-EPC CoC Approves RP Appointment, 283-Day Exclusion
MAX Plan at ₹4,999/yr
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- Dharan Infra-EPC’s CoC approved an application seeking exclusion of 283 stayed days from the CIRP period.
- The CoC approved the resolution professional’s appointment, CIRP costs and advisors on 27 November 2026.
- Dharan Infra-EPC’s first CoC meeting was scheduled for 30 October 2026.
- The NCLT Mumbai bench dismissed the CIRP withdrawal plea on 16 October 2026.
powered by IRIS

Dharan Infra-EPC Limited said on 27 November 2026 that its Committee of Creditors approved the resolution professional’s appointment and an application to exclude 283 stayed days from the Corporate Insolvency Resolution Process period. The CoC also approved CIRP costs and the appointment of advisors, marking further procedural progress in the company’s insolvency process.
Know Dharan Infra-EPC inside out
Results, valuation, peers and who's buying, in one view.
What did Dharan Infra-EPC’s Committee of Creditors approve?
Dharan Infra-EPC’s Committee of Creditors, or CoC, approved the appointment of the resolution professional, CIRP costs, advisors, and an application seeking the exclusion of 283 stayed days from the CIRP period. The decisions were disclosed as the outcome of the CoC meeting in the company’s 27 November filing.
The appointment of a resolution professional is a core step in the Corporate Insolvency Resolution Process, or CIRP. The professional manages the process in accordance with the Insolvency and Bankruptcy Code framework and works with creditors on the actions required during resolution. The filing does not name a resolution applicant, disclose a resolution plan, or state a final recovery outcome for creditors.
Approval of CIRP costs and advisors addresses the administrative and professional requirements of the ongoing process. The company did not provide a monetary break-up of these costs or identify the advisors in the information available.
Why has Dharan Infra-EPC sought exclusion of 283 days?
Dharan Infra-EPC has sought to exclude 283 days described as stayed days from the CIRP timeline. The filing says the CoC approved an application for this exclusion, but does not state the dates covered by the stay or the forum before which the application will be considered.
Under an insolvency process, periods affected by a legal stay can be relevant to calculating the effective resolution timeline. The CoC approval is for an application seeking exclusion, rather than a disclosed final order granting it. Investors should therefore distinguish the creditors’ decision to pursue the application from any subsequent judicial outcome.
The 283-day figure is the main quantified development in the filing. No updated deadline for completion of the CIRP was disclosed alongside the meeting outcome, and the company has not stated whether the requested exclusion will be allowed.
How did Dharan Infra-EPC reach this stage of the CIRP?
Dharan Infra-EPC’s latest filing follows the first CoC meeting that was scheduled for 30 October 2026. The earlier meeting agenda included a business update, approval of CIRP costs and discussion of the resolution professional’s appointment.
The company’s CIRP continued after the National Company Law Tribunal’s Mumbai bench dismissed a withdrawal plea on 16 October 2026, according to the available background disclosures. That plea was linked to a settlement with creditor Tata Capital Housing Finance, which was reported at ₹10 crore. The dismissal meant that the insolvency process continued despite that reported settlement.
Dharan Infra-EPC was formerly known as KBC Global Limited. Shareholders approved the company’s name change through a special resolution at an extraordinary general meeting held on 22 March 2025. It operates in the real-estate and construction segment, based on the sector classification in the provided information.
Got a follow-up? Ask IRIS
What are the key facts from the CoC meeting outcome?
The CoC outcome records approvals related to administration of Dharan Infra-EPC’s continuing CIRP, not an announced settlement or resolution plan. The company’s disclosure provides no terms for debt restructuring, equity restructuring, asset sale, or distributions to creditors.
The filing is consequently a procedural update from the creditor-led process. It does not establish the value of claims, the amount of admitted debt, the likely recovery for financial or operational creditors, or the treatment of public shareholders.
What does the CoC decision mean for investors and creditors?
For creditors, the resolutions provide a framework to continue the CIRP, including the formal role of the resolution professional and the costs and advisors required for the process. The proposed exclusion of 283 days may be material to the timeline if the relevant application is subsequently accepted, but no final decision on that request has been disclosed.
For shareholders, the update does not provide a resolution plan or a financial outcome. Equity investors remain dependent on later process developments, including any resolution proposal and the terms approved under applicable insolvency procedures. The company has not disclosed any immediate change to its capital structure through this filing.
The development also underlines that the process remains at an administrative and creditor-governance stage. The reported decisions enable the CIRP to proceed, but they do not by themselves indicate an operational turnaround, repayment amount, or conclusion of the insolvency proceedings.
Conclusion
Dharan Infra-EPC’s CoC has approved the resolution professional’s appointment, CIRP costs, advisors and an application to exclude 283 stayed days from the insolvency timeline. These are process-related actions that formalise key elements of the ongoing CIRP, while leaving the eventual resolution and stakeholder recoveries undisclosed.
The next points to watch are the outcome of the application for exclusion of the 283 days and any later disclosure on a resolution plan, resolution applicant, or tribunal order. The filing does not disclose a revised CIRP completion date or a timetable for these developments.