Coal and lignite promotional drilling rose about 127% in 2023-24
Key highlights
- CMPDI completed 1.743 lakh metres of promotional drilling across 29 coal and lignite blocks in 2023-24, up about 127% from the previous year.
- India’s coal resources reached 400.715 billion tonnes and lignite resources reached 47.37 billion tonnes as of 1 April 2025.
- Contractors completed 1.565 lakh of the 2.547 lakh metres of detailed drilling in non-CIL blocks during 2023-24, or about 61% of the total.
- Expected geological reports could add about 23 billion tonnes of coal resources, including 12 billion tonnes to the Measured category and 11 billion tonnes to the Indicated and Inferred categories.
powered by IRIS

Coal and lignite promotional drilling grew about 127% in 2023-24, with the Central Mine Planning and Design Institute (CMPDI) completing 1.743 lakh metres across 29 blocks. The regional programme operated alongside India’s coal resource estimate of 400.715 billion tonnes as of 1 April 2025.
Why did coal and lignite promotional drilling rise in 2023-24?
Coal and lignite promotional drilling rose because CMPDI conducted 1.743 lakh metres of regional drilling in 29 coal and lignite blocks under the Ministry of Coal’s Plan scheme, “Promotional Exploration for Coal & Lignite”, during 2023-24. The source reports growth of about 127% over the previous year, but does not give the previous year’s drilling metres or number of blocks to allow an independent calculation.
The programme forms part of continuous exploration in 64 coalfields, including 45 Gondwana and 19 Tertiary coalfields, and 15 lignite fields. Promotional, or regional, exploration seeks to identify new resources in the Indicated and Inferred categories rather than convert previously identified resources into the Measured, also termed Proved, category.
The about-127% increase therefore measures activity in one exploration programme, not coal production or mining output. Continued activity depends on the deployment of CMPDI, Mineral Exploration Corporation Limited (MECL), state government agencies and CMPDI contractual agencies, which participated in promotional exploration during 2023-24.
How large is India’s coal and lignite resource base now?
India’s updated coal resource estimate was 400.715 billion tonnes on 1 April 2025, while lignite resources were 47.37 billion tonnes. The Geological Survey of India’s National Coal Inventory of 2025 compiles estimates by CMPDI, the Geological Survey of India, MECL, Singareni Collieries Company Limited and certain public and private entrepreneurs to a maximum depth of 1,200 metres.
Coal resources increased by 48.59 billion tonnes between 1 April 2021 and 1 April 2025, according to the inventory table, while measured coal rose by 43.23 billion tonnes. Measured resources accounted for nearly 89% of the total coal-resource increase over that four-year comparison, consistent with detailed exploration’s purpose of upgrading identified resources. The table rounds the 2025 total to 400.72 billion tonnes, while the accompanying text gives 400.715 billion tonnes.
Lignite resources changed less over the same period, rising by 1.17 billion tonnes from 46.20 billion tonnes to 47.37 billion tonnes. Measured lignite increased from 7.37 billion tonnes in 2021 to 7.96 billion tonnes in 2025, while indicated lignite declined from 25.65 billion tonnes to 25.30 billion tonnes.
Got a follow-up? Ask IRIS
How was detailed drilling split between CMPDI and contractors?
Detailed drilling in non-CIL blocks reached 2.547 lakh metres in 2023-24, of which CMPDI departmental drills completed 0.983 lakh metres and outsourced drilling delivered 1.565 lakh metres. Outsourced drilling represented about 61% of the reported non-CIL total, making contractors the larger contributor to this specific detailed-drilling programme.
The Ministry of Coal’s detailed-drilling scheme is intended to move resources from the Indicated and Inferred categories into the Measured, or Proved, category within specified timelines. The source separately states that non-CIL achievement was 127%, but does not identify the target, prior-year baseline or unit definition behind that percentage; it is therefore not the same measure as the reported about-127% growth in promotional drilling.
CMPDI deployed 120 to 140 drills across detailed exploration, promotional work and consultancy blocks in 2023-24, including 67 departmental drills. MECL deployed resources across several types of blocks, while the Directorate of Geology and Mining in Nagaland and Assam used departmental resources for promotional exploration; six contractual agencies also participated in detailed drilling or exploration.
What resource additions and surveys could follow the drilling work?
The disclosed geological reports could add about 23 billion tonnes of coal resources: 19 detailed-exploration reports covering about 340 square kilometres are expected to add 12 billion tonnes to the Measured category, while 12 promotional reports covering about 261 square kilometres are expected to add 11 billion tonnes in the Indicated and Inferred categories. These are expected additions and are not stated as already included in the 1 April 2025 inventory.
The reporting periods differ. For 2023-24, the source says 31 geological reports were prepared from detailed or regional exploration conducted in earlier years. Separately, from January 2023 to March 2024, CMPDI submitted 33 detailed-exploration reports covering about 510 square kilometres with proved resources of about 18.5 billion tonnes, as well as 12 promotional reports identifying about 11 billion tonnes of new resources.
Geophysical work supplemented drilling in 2023-24. CMPDI completed 234.57 line kilometres of two-dimensional and three-dimensional seismic surveys, including about 205 line kilometres departmentally against a 190-line-kilometre target and 29.57 line kilometres through outsourcing. It also completed 4.852 lakh metres of geophysical logging in coal projects, of which contractors carried out 3.133 lakh metres, or about 65%.
For January 2023 to March 2024, CMPDI reported 403.00 line kilometres of seismic work, comprising 298.23 line kilometres departmentally and 104.77 line kilometres through outsourcing. Departmental teams also completed 77.06 line kilometres of magnetic survey, 83.506 line kilometres of resistivity survey and 365 gravity-survey stations during that 15-month period.
Conclusion
The 1.743 lakh metres of promotional drilling and reported growth of about 127% in 2023-24 show expanded regional exploration alongside a coal resource estimate that increased from 352.13 billion tonnes in 2021 to 400.72 billion tonnes in the 2025 inventory table. Detailed drilling provides a separate pathway for upgrading identified resources, with contractors delivering 1.565 lakh of the 2.547 lakh metres reported in non-CIL blocks.
The next disclosed measure is whether geological reports deliver the expected additions of about 12 billion tonnes of measured coal and 11 billion tonnes of indicated and inferred coal. The distinction between annual 2023-24 results and CMPDI’s January 2023 to March 2024 cumulative reporting also matters because the report counts, coverage areas and resource figures differ between those stated periods.