The Company directs Rs 19.36 crore to Manesar overhaul
Key highlights
- The Company has earmarked Rs 19.36 crore for three projects at its existing Manesar facility.
- Plant and machinery replacement accounts for Rs 15.05 crore, or 77.7%, of the specified spending.
- The Company plans to invest Rs 1.05 crore in in-house gold plating and Rs 3.26 crore in a 14,425-square-foot second-floor expansion.
- Civil works are targeted for completion by March 31, 2027, while machinery installation and commercial production are scheduled for June 30, 2028.
powered by IRIS

The Company has earmarked Rs 19.36 crore for a Manesar factory overhaul at its existing Gurugram facility, with Rs 15.05 crore, or 77.7%, assigned to plant and machinery replacement. The disclosed programme also includes Rs 1.05 crore for in-house gold plating and Rs 3.26 crore for a 14,425-square-foot second-floor expansion, targeted for commercial production by June 30, 2028.
How is the Rs 19.36 crore Manesar overhaul allocated?
The Company has allocated Rs 19.36 crore to three specified capital-expenditure projects at Manesar, rather than to a new manufacturing site. Machinery replacement represents Rs 15.05 crore of the stated total, followed by Rs 3.26 crore for building infrastructure and Rs 1.05 crore for backward integration through gold plating.
The Company manufactures geophones, seismic cables and connectors for the seismic industry in the energy and geoscience sector. Geophones record ground-vibration signals, while the cables and connectors support the transmission of seismic data for processing and interpretation of subsurface geological structures. The Company says advanced injection moulding and tandem extrusion are intended to streamline production, reduce lead times and allow faster responses to demand or design changes.
The Rs 19.36 crore is not the full allocation from the fresh issue because the prospectus leaves the amount for unidentified acquisitions and general corporate purposes blank. Under the Securities and Exchange Board of India Issue of Capital and Disclosure Requirements Regulations, combined spending on those two purposes cannot exceed 35% of gross proceeds; unidentified acquisitions are capped at 25% and general corporate purposes at 15% of gross proceeds or Rs 10 crore, whichever is lower.
What machinery will the Company install at Manesar?
The Company plans Rs 15.05 crore of machinery and infrastructure expenditure across six categories, with geophone manufacturing and moulding accounting for Rs 11.91 crore combined. The geophone-manufacturing department has a Rs 5.98 crore budget, including six multi-spindle force winding machines costing Rs 2.32 crore and two fixed-headstock computer numerical control, or CNC, automatic lathes costing Rs 3.42 crore.
The moulding department has a Rs 5.93 crore allocation for five machines in three Allrounder configurations: two 370e 500e machines, two 470e 1000e machines and one 570e 1800e machine. Machinery estimates are exclusive of goods and services tax, or GST, unlike the Rs 3.26 crore building-expansion estimate, which includes GST.
The remaining package broadens the overhaul beyond production machines. The Rs 1.36 crore extrusion allocation covers two high-speed extrusion lines and one 630-millimetre backlist buncher for pairing, while the Rs 94.79 lakh geophone-line extension covers quality gauges, crimping equipment, ultrasonic cleaning equipment, magnetising and demagnetising equipment, ovens, microscopes and soldering stations.
The Company has also budgeted Rs 22.64 lakh for 42 assembly workstations and Rs 60.97 lakh for fire infrastructure. The fire-system estimate includes a hydrant and sprinkler system costing Rs 32.76 lakh, along with fire pumps, hand appliances and an alarm system. The stated replacement programme therefore includes assembly, testing and safety equipment as well as manufacturing machinery.
Why is the Company bringing gold plating in house?
The Company plans to spend Rs 1.05 crore on an in-house gold-electroplating facility because it currently outsources gold plating for geophysical connector contacts. Backward integration means moving an activity performed by third-party suppliers into the Company’s operations. The Company says brass or beryllium-copper contacts need plating to provide electrical conductivity and corrosion resistance.
The project budget includes Rs 30 lakh for a gold-electroplating production line, Rs 15 lakh for an X-ray thickness measurement system, Rs 22.50 lakh for ancillary equipment and tooling, and Rs 37.50 lakh for technical infrastructure and laboratory setup. The Company says the facility is intended to give it greater operational control, better quality consistency, process standardisation and cost efficiencies.
The Company also says in-house plating could help it participate in larger government and export orders where internal capabilities can be a qualifying criterion. The prospectus does not disclose plating capacity, projected cost savings, expected revenue or identified orders. That outcome must therefore depend on commissioning the equipment and satisfying the requirements of relevant tenders.
Got a follow-up? Ask IRIS
What will the second-floor expansion add at Manesar?
The Company intends to develop approximately 14,425 square feet on the second floor of its existing Manesar factory at an estimated cost of Rs 3.26 crore. It says the new building infrastructure will provide structural capacity for an assembly line and support a workflow redesign intended to integrate manufacturing departments, reduce material transit times and improve process effectiveness.
The Rs 3.26 crore estimate includes Rs 78.22 lakh for reinforcement for reinforced cement concrete, or RCC, work, Rs 76.45 lakh for RCC work, Rs 39.27 lakh for finishing, Rs 27.68 lakh for flooring and Rs 26.54 lakh for electrical general-lighting work. BPS Structures Pvt Ltd received the construction work order on May 20, 2026.
The Company has appointed an architect and obtained Haryana State Industrial and Infrastructure Development Corporation approval for an increase in floor area ratio, or FAR. FAR is the permitted ratio of a building’s floor area to its plot area. The Company has also submitted its building plan to Haryana State Industrial and Infrastructure Development Corporation for approval, so the physical expansion remains linked to the applicable building process.
When does the Company expect the Manesar overhaul to finish?
The Company expects to deploy Rs 15.94 crore in financial year 2026-27 and Rs 3.42 crore in financial year 2027-28. The earlier period contains Rs 11.63 crore for machinery replacement, the full Rs 1.05 crore gold-plating budget and the full Rs 3.26 crore second-floor allocation; the later period is entirely machinery spending.
Civil and building works are scheduled for completion by March 31, 2027. Installation of machinery and equipment, the trial run and commencement of commercial production are each scheduled for June 30, 2028. The production target consequently requires both completion of the building work and installation of the proposed machinery.
What could alter the stated Manesar spending plan?
The Company says the funding requirements are management estimates based on current business plans and have not been appraised by a bank, financial institution or independent third party. Most machinery quotations are budgetary estimates rather than definitive supplier contracts. The Company has disclosed a purchase order dated August 31, 2026 for the two CNC lathes, while other quoted validity dates generally run from October 29, 2026 to January 14, 2027.
The Company may change equipment models, quantities, vendors or the mix of machinery when orders are placed. It says any cost escalation from freight, installation, packaging, forwarding or customs duty will be met from internal accruals. Any wider shortfall may be funded through internal accruals, borrowings or unsecured loans, and the Company had not raised bridge loans intended to be repaid from issue proceeds as of the red herring prospectus date.
Conclusion
The Company’s disclosed capital programme concentrates on retooling and enlarging one operating Manesar facility. Of the Rs 19.36 crore specified spend, machinery represents Rs 15.05 crore, while the gold-plating project brings an outsourced process in house and the second-floor project adds assembly-related building capacity.
The next milestones are civil-work completion by March 31, 2027 and machinery installation, trial runs and commercial production by June 30, 2028. Progress will depend on final procurement terms, as most quotations may change or lapse, as well as completion of the building approval process and the Company’s ability to meet any cost overruns through internal accruals or other disclosed funding sources.