KPI Green Energy Limited commissions 269 MW Coal India solar plant
Key highlights
- KPI Green Energy commissioned 200 MW AC or 269 MW DC of solar capacity for Coal India at Khavda, Gujarat.
- The full Coal India assignment covers 300 MW AC or 405 MW DC and carries a disclosed value of ₹1,311.40 crore.
- The Coal India EPC contract includes operation and maintenance services for five years.
- KPI Green Energy has stated a target of October 2026 for 250 MW AC solar and 370 MW hybrid PPA projects.
powered by IRIS

KPI Green Energy Limited has commissioned 200 MW AC, equivalent to 269 MW DC, of solar capacity for Coal India Limited at Khavda, Gujarat, as part of a larger 300 MW AC and 405 MW DC project valued at ₹1,311.40 crore. The commissioning marks progress on one of the company’s largest EPC solar assignments.
Know KPI Green Energy inside out
Results, valuation, peers and who's buying, in one view.
What has KPI Green Energy commissioned for Coal India?
KPI Green Energy has successfully commissioned a 200 MW AC or 269 MW DC solar power plant for Coal India at Khavda, Gujarat. The capacity was certified by the Gujarat Energy Development Agency, according to the company information provided. The plant forms part of a 300 MW AC or 405 MW DC grid-connected, ground-mounted solar photovoltaic project.
The project is being developed at GIPCL's Solar Park in Khavda on an engineering, procurement and construction basis. KPI Green Energy’s scope includes the solar plant and five years of operation and maintenance services. Coal India, a central public sector undertaking, awarded the larger project to the company in December 2024.
The original contract agreement specified a contract price of ₹1,311.40 crore, also described as ₹13.11 billion, for the 300 MW AC project. The agreement had indicated an expected completion date of November 2025 under the tender timeline. The reported 269 MW DC commissioning shows that a substantial part of the larger project has been brought into operation.
Khavda has become an important project location for KPI Green Energy. The company’s Coal India assignment is located close to its 200 MW AC or 240 MW DC independent power producer solar project for Gujarat Urja Vikas Nigam Limited, or GUVNL. Locating projects in the same solar park can support execution planning, although the provided information does not quantify any cost or operational benefit.
How did the Coal India solar project progress?
KPI Green Energy first disclosed the landmark Coal India order in December 2024 for a 300 MW AC or 405 MW DC ground-mounted solar PV plant. The company subsequently signed the contract agreement for the project, which includes installation and post-commissioning operation and maintenance services for five years.
The project is separate from another 300 MW AC or 405 MW DC solar assignment reported from Adani Group entities at Khavda. For the Adani-related work, KPI Green Energy said its responsibilities included electrical AC-DC works, civil works and equipment supply. The Coal India project, by contrast, was described as an EPC contract with an O&M component.
KPI Green Energy’s supplied disclosures also refer to a 405 MWp Coal India project being at an advanced stage of execution. The company’s report of 269 MW DC commissioned capacity is consistent with the project being completed in stages rather than only at final completion. The source does not state the commissioning date for the remaining capacity or confirm final completion of the entire 300 MW AC facility.
The company has also reported other Khavda activity, including a 200 MW AC or 240 MW DC solar project under a long-term PPA with GUVNL. It said this GUVNL project had commenced power supply. These projects underline the concentration of KPI Green Energy’s current utility-scale solar work in Gujarat.
Got a follow-up? Ask IRIS
What does the project mean for KPI Green Energy’s renewable portfolio?
The Coal India commissioning adds operating capacity to KPI Green Energy’s broader solar, wind, hybrid and energy-storage portfolio. The company states that it has 2,022 MWp operational capacity, while its recent disclosures also refer to a 2.17 GWp independent power producer portfolio and 965 MWp of energised capacity within that IPP portfolio.
The company operates through both independent power producer and captive power producer segments, besides undertaking EPC assignments. The Coal India contract is an EPC project, while its GUVNL solar projects and other PPA-backed developments form part of its IPP activity. This mix means its project pipeline includes construction work for customers as well as assets intended to supply electricity under long-term agreements.
Beyond solar, KPI Green Energy has signed a PPA with GUVNL for 150 MW of wind projects and secured a ₹979 crore term loan and bank guarantee facility from Canara Bank for a 150 MW wind project in Gujarat. It has also executed a battery energy storage purchase agreement with GUVNL for 445 MW and 890 MWh of standalone battery energy storage projects.
The company disclosed that it is developing 250 MW AC or 350 MWp of solar projects and 370 MW or 677 MWp of hybrid projects under PPAs signed in October 2024, with completion targeted by October 2026. These disclosed targets provide the next stated timeline for investors tracking the company’s IPP expansion.
How could the Khavda commissioning affect investors and the renewable sector?
The 269 MW DC commissioning provides a measurable execution milestone on a ₹1,311.40 crore contract and demonstrates progress on a large central public sector customer order. For KPI Green Energy, timely conversion of awarded projects into commissioned capacity is relevant to its EPC delivery record and to the expansion of its renewable operating base.
For Coal India, the project represents procurement of renewable generation through a large grid-connected solar plant. The supplied information does not provide generation estimates, tariff details or the financial effect on Coal India. It therefore cannot establish the project’s future earnings impact for either company beyond the disclosed contract value and installed capacity.
At an industry level, the project adds to the development activity at Khavda, where utility-scale solar projects are being built for public-sector and private-sector counterparties. KPI Green Energy’s disclosures also show increasing interest in hybrid generation, wind capacity and energy storage, which can complement solar capacity but are governed by separate PPAs, contracts and commissioning schedules.
Conclusion
KPI Green Energy’s commissioning of 200 MW AC or 269 MW DC for Coal India is a significant construction milestone within its larger 300 MW AC and 405 MW DC Khavda solar assignment. The project carries a disclosed value of ₹1,311.40 crore and includes five years of O&M, making it a material EPC order in the company’s reported project portfolio.
The key item to watch is the commissioning status of the remaining Coal India capacity, for which the provided information gives no final completion confirmation. Investors can also monitor progress toward the company’s October 2026 target for its 250 MW AC solar and 370 MW hybrid PPA projects, along with execution of its 150 MW wind and 445 MW battery-storage plans.