Larsen & Toubro secures ₹10,000-15,000 crore AI order
Key highlights
- L&T classified the Together AI engagement as a mega order in the ₹10,000 crore to ₹15,000 crore range.
- The Chennai AI Factory is planned to have capacity for 10,000 NVIDIA B300 GPUs.
- Vyoma.AI's Chennai campus phase I is designed for 250 MW with power infrastructure readiness of 150 MVA.
- L&T's October 2026 update targeted January 2027 for commissioning of the Chennai AI Factory.
powered by IRIS

Larsen & Toubro Limited secured a mega AI infrastructure order classified at ₹10,000-15,000 crore to deploy 10,000 NVIDIA B300 GPUs at its Chennai campus. The multi-year engagement, secured through LTN Compute for US-based Together AI, is intended to support large-scale AI training, fine-tuning and inference on Together AI's cloud platform.
Know Larsen & Toubro inside out
Results, valuation, peers and who's buying, in one view.
What has L&T announced about the Chennai AI factory?
L&T has announced that its group company LTN Compute will develop an NVIDIA B300-based AI Factory at the Vyoma.AI data centre campus in Chennai for Together AI. The company describes the project as India's largest single-cluster AI infrastructure deployment and says it marks its entry into the AI Factory business.
The order is classified by L&T as a mega order, a category that ranges from ₹10,000 crore to ₹15,000 crore. L&T has not disclosed the exact contract value, so the range reflects its order-classification framework rather than a confirmed final price for the engagement.
The planned facility will power Together AI's AI-native cloud platform. L&T said the infrastructure is designed for large-scale inference, fine-tuning and training workloads, combining accelerated computing with networking, low-latency connectivity, storage and data-centre operations.
Who is involved in the NVIDIA B300 deployment?
LTN Compute, the AI infrastructure subsidiary associated with Vyoma.AI, secured the engagement and will establish the AI Factory. Vyoma.AI is L&T's AI and data-centre business, while Together AI is the US-based AI cloud company whose platform will use the planned computing infrastructure.
The filing identifies NVIDIA B300 GPUs as the core computing equipment. The integrated AI Factory is planned to have capacity for 10,000 NVIDIA B300 GPUs. L&T's October 27, 2026 earnings-call update said the Chennai facility was being established with planned capacity exceeding 10,000 B300 GPUs and that a long-term deployment agreement with Together AI covered a significant portion of that capacity.
The project is a planned deployment rather than an operational facility. Management had indicated that commissioning was targeted for January 2027. The disclosed timeline provides an operational milestone, but L&T has not stated a revised commissioning date or disclosed the precise share of capacity covered by the long-term agreement.
Got a follow-up? Ask IRIS
Why was Chennai selected for the AI infrastructure project?
Chennai was selected because Vyoma.AI's campus has been planned as a gigawatt-scale AI infrastructure site with room for staged expansion. The campus's first phase is designed for 250 MW, and its power infrastructure has readiness of 150 MVA, according to L&T.
High-density AI computing requires substantial power, cooling, networking and physical data-centre capacity. The disclosed design parameters show the infrastructure foundation L&T is positioning for the AI Factory, although the company has not provided separate details on the power draw, construction schedule or cooling configuration for the 10,000-GPU deployment.
The order also links L&T's engineering and data-centre activities with demand for AI cloud computing. Rather than supplying only individual components, the disclosed scope covers an integrated AI infrastructure environment intended to host GPU capacity for a cloud-platform customer.
How does the order affect L&T and the AI infrastructure market?
The order adds a large classified project to L&T's AI and data-centre business pipeline, but investors should distinguish the ₹10,000-15,000 crore classification range from a disclosed contract value. L&T has not specified the revenue-recognition schedule, investment requirement, margins, payment terms or the portion of the project that may be recognised in any particular financial year.
For Together AI, the planned Chennai deployment is intended to provide infrastructure for its cloud platform's training, fine-tuning and inference workloads. For L&T, the project establishes a disclosed AI Factory engagement through LTN Compute, with the company describing the planned installation as the country's largest single-cluster deployment of its kind.
The project reflects rising infrastructure requirements for advanced AI workloads, which need concentrated GPU capacity and supporting data-centre systems. However, the filing does not provide an industry-demand forecast, customer-volume estimates or a financial outlook linked specifically to the Chennai facility. The key confirmed facts remain the order classification, the planned GPU capacity, the Chennai location and the stated commissioning target.
Conclusion
L&T's filing records a multi-year AI infrastructure engagement through LTN Compute for Together AI at the Vyoma.AI Chennai campus. The project is classified as a ₹10,000-15,000 crore mega order, while its exact value remains undisclosed, and it is planned to host 10,000 NVIDIA B300 GPUs for AI cloud workloads.
The next disclosed milestone is the January 2027 commissioning target referenced during L&T's October 2026 earnings call. Investors will watch for updates on commissioning, the final scope of deployed capacity, the exact contract value if disclosed, and the project's financial contribution to L&T's AI and data-centre operations.