Orient Cables reaches 963,096 km capacity after Bengaluru start
Key highlights
- Orient Cables reported annualised cable capacity of 963,096 kilometres in September 2026.
- Bengaluru Unit III started in May 2026 with 109,320 kilometres of annual capacity.
- Bengaluru Unit III operated at about 60.4% utilisation as of September 2026.
- Orient Cables holds 42,530 square metres of additional land for future expansion.
powered by IRIS

Orient Cables reported annualised cable capacity of 963,096 kilometres in September 2026, following the May 2026 start of Bengaluru Unit III, compared with 794,976 kilometres in March 2026. Orient Cables said the new unit had about 60.4% utilisation by September, while it also held 42,530 square metres of additional land for future expansion.
Know Orient Cables (India) inside out
Results, valuation, peers and who's buying, in one view.
How much cable capacity does Orient Cables have now?
Orient Cables had cable capacity of 963,096 kilometres per annum as of 30 September 2026, with the September figure presented on an annualised basis. This was the highest capacity figure in the presentation’s four-period series and was supported by three facilities for which individual cable capacities are disclosed: Unit I and Unit II in Bhiwadi, and Unit III in Bengaluru.
The disclosed site capacities total exactly 963,096 kilometres: Unit I accounts for 226,720 kilometres per annum, Unit II for 627,056 kilometres, and Bengaluru Unit III for 109,320 kilometres. Unit II is the largest disclosed site, representing about two-thirds of the stated total capacity, while the Bengaluru facility represents the addition beyond the two Bhiwadi units.
The capacity series shows an increase of 423,435 kilometres, or about 78%, from March 2024 to September 2026. Capacity rose by 21,277 kilometres between March 2024 and March 2025, then increased by 234,038 kilometres by March 2026 and by a further 168,120 kilometres by September 2026. The reported increases were therefore concentrated after March 2025 rather than spread evenly across the full period.
What did the Bengaluru plant add to Orient Cables capacity?
Orient Cables added 109,320 kilometres of annual cable capacity through Unit III in Bengaluru, which started in May 2026. The presentation identifies the unit as a networking-cable manufacturing facility, within a portfolio that includes LAN cables, closed-circuit television cables, patch cords and AISG cable assemblies.
Unit III’s utilisation stood at about 60.4% as of September 2026, below Orient Cables’ overall 72.1% capacity utilisation in the annualised September measure. The difference reflects the company-wide rate across established Bhiwadi operations and the new Bengaluru plant, which had been operating only since May 2026.
The September 2026 company-wide utilisation was 2.2 percentage points above the March 2026 rate of 69.9%, even as disclosed capacity increased by 168,120 kilometres. It remained below the 80.7% reported in March 2025, when total capacity was 560,938 kilometres. The presentation does not provide utilisation separately for Unit I or Unit II, so it does not establish how the Bhiwadi facilities individually performed during the expansion.
Got a follow-up? Ask IRIS
Where are Orient Cables manufacturing facilities located?
Orient Cables discloses facilities in Bhiwadi and Bengaluru, with Unit I and Unit II located in Bhiwadi and Unit III located in Bengaluru. Unit I covers 8,299 square metres and has 226,720 kilometres of annual capacity, while Unit II covers 21,207 square metres and has 627,056 kilometres of annual capacity.
The facility graphic also lists Unit IV in Bhiwadi, an upcoming plant and a land parcel purchased, but the presentation gives no separate area, capacity or commissioning date for Unit IV or the upcoming plant. Accordingly, the 963,096-kilometre total can be reconciled to the three sites with disclosed capacity, rather than to a stated output figure for every item shown in the facility graphic.
Bengaluru Unit III adds a third disclosed manufacturing location, with 109,320 kilometres of capacity, alongside the two operating Bhiwadi units. Orient Cables describes Bhiwadi and Bengaluru as strategically located facilities and refers to its product range as specialised cables and passive networking equipment. The disclosed portfolio also includes optical fibre cables, solar cable, low-tension power cable, electric-vehicle charging cable and allied products.
Does Orient Cables have room for further capacity expansion?
Orient Cables has purchased 42,530 square metres of additional land for future expansion, according to the facility presentation. This land is larger than the 29,506 square metres combined area disclosed for Unit I and Unit II, although Orient Cables does not state what capacity, product line, construction schedule or capital spending would be attached to the land.
The presentation separately identifies an upcoming plant but does not give a start date or capacity figure for it. Orient Cables’ disclosed expansion pathway therefore consists of a Bengaluru unit already started in May 2026, a purchased land parcel for future use and an upcoming-facility label, rather than a quantified target beyond the 963,096 kilometres reported as of September 2026.
The disclosed Bhiwadi sites cover 8,299 square metres at Unit I and 21,207 square metres at Unit II, compared with 42,530 square metres of land held for expansion. That comparison establishes that Orient Cables has identified physical space beyond the two Bhiwadi units, but it does not show when that space will be developed or whether its eventual output will be cable capacity, assemblies or another product category.
Conclusion
Orient Cables’ disclosed cable capacity reached 963,096 kilometres per annum in annualised September 2026 data, up from 539,661 kilometres in March 2024. The 109,320-kilometre Bengaluru Unit III, started in May 2026, is a defined component of that total, while its approximately 60.4% utilisation sits below the company-wide 72.1% rate.
The next disclosed items to watch are the ramp-up of Bengaluru Unit III, the company-wide utilisation rate after September 2026 and any quantified plan for the 42,530-square-metre land parcel or the upcoming plant. The presentation provides no completion date or capacity target for those future expansion items, leaving their timing unresolved.