Orient Green Power Company Limited reported ₹106 crore H1 profit
Key highlights
- OGPL reported ₹106 crore consolidated net profit in H1 FY27 without the prior-year ₹16 crore one-time gain.
- H1 FY27 total income rose 2% year on year to ₹233 crore and EBITDA rose 4% to ₹177 crore.
- OGPL commissioned 17.6 MW of solar capacity in Q2 FY27, taking total solar capacity to 24.6 MW.
- OGPL has a 7.8 MW wind repowering project nearing completion and a 6.6 MW wind expansion under EPC contract.
powered by IRIS

Orient Green Power Company Limited reported consolidated net profit of ₹106 crore in H1 FY27, while total income increased 2% year on year to ₹233 crore and EBITDA rose 4% to ₹177 crore. OGPL said the profit was achieved without the ₹16 crore exceptional income recorded in the prior-year first half.
Know Orient Green Power Company inside out
Results, valuation, peers and who's buying, in one view.
How did OGPL perform in H1 FY27?
OGPL recorded consolidated total income of ₹233 crore in H1 FY27, up 2% year on year, and earnings before interest, tax, depreciation and amortisation (EBITDA) of ₹177 crore, up 4%. Its H1 EBITDA margin was 76%, an increase of 147 basis points, with one basis point equal to one-hundredth of a percentage point.
The company reported ₹106 crore of consolidated net profit for H1 FY27, exceeding ₹100 crore without the ₹16 crore one-time gain included in the first half of the previous fiscal. OGPL said net profit was lower year on year because that exceptional income did not recur, even though total income and EBITDA increased.
Q2 FY27 supplied ₹147 crore of total income and ₹117 crore of EBITDA, compared with H1 FY27 totals of ₹233 crore and ₹177 crore, respectively. The quarter's year-on-year growth rates were 8% for income and 12% for EBITDA, above the corresponding H1 increases of 2% and 4%, while Q2 EBITDA margin was 80%, compared with 76% for H1.
What drove OGPL's first-half operating improvement?
OGPL attributed the H1 FY27 operating improvement to better wind availability in Q2 than in the preceding quarter, when wind conditions were moderate, alongside incremental generation from recently commissioned solar and wind capacity. Management said these factors reversed the generation deficit in the previous quarter and produced surplus generation in Q2.
The disclosed mechanism was higher generation rather than a quantified change in tariff or pricing. Management linked the reversal of the earlier generation deficit to the marginal improvement in first-half operational profit, represented by the 4% year-on-year rise in EBITDA to ₹177 crore.
The comparison distinguishes operations from the net-profit outcome in H1 FY27. Total income grew 2% and EBITDA grew 4%, but the first half of FY26 had included ₹16 crore of exceptional income, which OGPL said caused the year-on-year decline in reported net profit despite higher operating measures.
What capacity did OGPL add during Q2 FY27?
OGPL commissioned a 17.6 megawatt (MW) solar plant in Q2 FY27, taking total solar capacity to 24.6 MW when combined with the 7 MW solar plant commissioned in the previous fiscal. The company said commissioning the 17.6 MW project fulfilled one of the objectives of its rights issue.
The newly commissioned solar plant was among the assets management cited as contributing incremental generation in the quarter. The 17.6 MW addition and the 7 MW plant commissioned in FY26 together support the disclosed 24.6 MW solar portfolio, although the announcement does not provide generation or revenue separately for either project.
OGPL operates about 381.7 MW of wind capacity across Tamil Nadu, Andhra Pradesh, Gujarat and Karnataka, as well as a 10.5 MW wind farm in Croatia and a 24.6 MW solar plant in Tamil Nadu. The release does not disclose H1 FY27 generation by technology, state or geography for these operating assets.
Got a follow-up? Ask IRIS
What projects and approvals could affect OGPL next?
OGPL said its 7.8 MW wind repowering project is nearing completion and is anticipated to be commissioned in the upcoming quarter, subject to regulatory approvals. The project involves repowering old wind turbines to improve operating efficiencies, but the filing does not give a fixed commissioning date.
The company has also entered into an engineering, procurement and construction contract to expand wind power capacity by 6.6 MW. Management said the repowering project and contracted wind expansion are expected to be available in their entirety for the next wind season, conditional on completion and the stated approvals.
These projects follow the 17.6 MW solar commissioning in Q2 FY27, which lifted OGPL's solar capacity to 24.6 MW. The announcement does not disclose capital expenditure, project costs, power purchase arrangements, or expected revenue and generation from the 7.8 MW repowering programme or 6.6 MW wind expansion.
What changed in OGPL's credit ratings?
OGPL said CRISIL upgraded the rating of a material subsidiary to BBB, while ICRA assigned a BBB rating to its solar subsidiary. The announcement does not identify the material subsidiary, prior rating, rating outlook, debt amount or effective date of either rating action.
The company cited capacity additions and improved credit ratings as factors that helped sustain H1 FY27 profit above ₹100 crore without the prior-year ₹16 crore one-time gain. The filing does not quantify any resulting change in borrowing costs, financing availability or interest expense.
For context, OGPL reported FY26 consolidated total income of ₹315.57 crore, EBITDA of ₹205.45 crore and net profit of ₹71.57 crore. H1 FY27 EBITDA of ₹177 crore was ₹28.45 crore below FY26 EBITDA, while H1 FY27 total income of ₹233 crore was ₹82.57 crore below the FY26 full-year figure; the company gave no FY27 full-year forecast.
Conclusion
The half-year result reflects a recovery in generation during Q2 FY27, when improved wind conditions and newly commissioned capacity reversed the preceding quarter's deficit. Q2 total income grew 8% year on year and EBITDA grew 12%, while the absence of the prior-year exceptional item affected the reported profit comparison.
The next disclosed milestones are regulatory approvals and anticipated upcoming-quarter commissioning of the 7.8 MW repowering project, followed by availability of the 6.6 MW contracted wind expansion for the next wind season. OGPL's ability to bring those projects online as planned, alongside the contribution from its 24.6 MW solar portfolio, is the stated operational development to watch.