Suntech Infra Solutions Limited reports Rs 61 crore temple work
Key highlights
- SIS has three disclosed foundation projects marked in progress across Gadarwara, Virat Ramayan Mandir and Nabinagar.
- SIS’s Virat Ramayan Mandir scope totals Rs 61 crore, including Rs 17 crore of BCIS piles and Rs 44 crore of civil works.
- The Gadarwara assignment involves 3,285 piles, approximately 28-metre depths and 4,435 MT of reinforcement.
- SIS’s Nabinagar bored-piling work is valued at Rs 17.94 crore and comprises 1,200 piles.
powered by IRIS

Suntech Infra Solutions Limited (SIS) reports three foundation projects in progress, led by Rs 61 crore of piling and civil work at Bihar’s Virat Ramayan Mandir; the other disclosed jobs are at NTPC Gadarwara and Nabinagar thermal power plants in Madhya Pradesh and Bihar, respectively.
Know Suntech Infra Solutions inside out
Results, valuation, peers and who's buying, in one view.
What foundation projects is SIS currently executing?
SIS is executing bored-pile or BCIS-pile work across three disclosed sites: NTPC Gadarwara Super Thermal Power Project in Madhya Pradesh, Virat Ramayan Mandir in East Champaran, Bihar, and the Nabinagar thermal power plant in Bihar. The presentation marks all three assignments as in progress and identifies the Gadarwara job as contracted through L&T Constructions and the Nabinagar work through Tata Projects.
The three jobs differ in scale and customer setting. Virat Ramayan Mandir has 3,310 piles, marginally exceeding Gadarwara’s 3,285 piles by 25, while Nabinagar has 1,200 piles. Gadarwara has the deepest disclosed piles at approximately 28 metres, compared with 23 metres at the temple project and 22 metres at Nabinagar.
The disclosed values are concentrated in the Bihar temple assignment rather than the two power-plant projects. SIS lists Rs 17 crore for BCIS piles and Rs 44 crore for civil works at Virat Ramayan Mandir, totalling Rs 61 crore. It discloses a Rs 17.94 crore project value for the Nabinagar piling work, while no contract value is stated for Gadarwara.
What is SIS building at NTPC Gadarwara?
SIS is installing 3,285 BCIS piles for the NTPC Gadarwara Super Thermal Power Project, using approximately 28-metre pile depths, 4,435 metric tonnes (MT) of reinforcement and M30 and M35 concrete grades. The scope includes initial and routine vertical, lateral and pull-out load tests, plus pile-integrity testing on 500 piles.
Gadarwara carries the largest reinforcement commitment of the three disclosed projects. Its 4,435 MT is more than four times the 1,061 MT specified for Virat Ramayan Mandir and above Nabinagar’s 794 MT. SIS has assigned six rigs and seven service cranes to Gadarwara, making it the only one of the three jobs with more service cranes than rigs.
The host plant is an operational 1,600-megawatt (MW) coal-based facility with two 800 MW units, according to the presentation. NTPC is planning Stage II with two additional 800 MW ultra-supercritical units, potentially taking total capacity to 3,200 MW; SIS’s disclosed scope is piling work, while L&T has the main plant contract for the expansion.
How large is SIS’s Virat Ramayan Mandir mandate?
SIS’s Virat Ramayan Mandir mandate totals Rs 61 crore, comprising Rs 17 crore of BCIS piles and Rs 44 crore of civil works. The foundation scope calls for 3,310 bored piles at a depth of 23 metres, using 1,061 MT of reinforcement and M30 concrete, with six rigs and six service cranes assigned.
Testing requirements at the Bihar site include initial and routine vertical, lateral and pull-out load tests, along with pile-integrity testing on 500 piles. Those 500 tests match the disclosed pile-integrity count at Gadarwara, although the temple project uses one fewer service crane than the six-rig, seven-crane Gadarwara deployment.
The assignment supports a larger temple development in East Champaran that the presentation describes as a Rs 500 crore, three-storey project spanning about 3.76 lakh square feet. Foundation work began in 2023 and the development is expected to be completed around 2026-2027, while SIS separately identifies its piling and civil scope as in progress.
Got a follow-up? Ask IRIS
What is SIS doing at Nabinagar thermal power plant?
SIS is undertaking bored-piling work valued at Rs 17.94 crore at the Nabinagar thermal power plant through Tata Projects. The job comprises 1,200 BCIS piles, each 22 metres deep, with 794 MT of reinforcement, M25 concrete, three rigs and three service cranes.
The Nabinagar work is smaller than SIS’s other two disclosed sites by pile count, equipment allocation and reinforcement. Its 1,200 piles are 2,110 fewer than the 3,310 piles at Virat Ramayan Mandir, while its three rigs are half the six rigs listed for each of the temple and Gadarwara assignments. Like the other projects, its test scope covers initial and routine vertical, lateral and pull-out load testing.
The Nabinagar Super Thermal Power Project’s Phase I comprises three 660 MW units, or 1,980 MW, according to the presentation. Phase II is planned as three 800 MW units, or 2,400 MW; environmental clearance was granted in February 2025 after terms of reference in April 2024, and the foundation stone was laid in May 2025.
What equipment platform supports SIS’s project execution?
SIS says its execution platform includes more than 130 company-owned machines and setups, supported by a dedicated yard and mechanical support. The presentation lists piling rigs, stone-column rigs, service cranes and diaphragm-wall rigs, alongside batching plants, boom placers, excavators, dumpers, vibro rollers and vibro hammers.
The three current projects show the disclosed equipment allocations. Gadarwara has 13 primary units when its six rigs and seven service cranes are combined, Virat Ramayan Mandir has 12, and Nabinagar has six. These allocations total 31 rigs and service cranes, although the presentation does not state whether they represent the full fleet or simultaneous deployment across all sites.
SIS also reports an in-house design desk for design optimisation and value engineering, nationwide mobilisation capability, and monitoring systems using enterprise resource planning and management-information dashboards. It reports more than 95% repeat business from key clients and 100% statutory compliance in labour, safety and environmental norms, both described by the company as reported measures.
Conclusion
SIS’s three in-progress foundation assignments span a Rs 61 crore temple piling-and-civil mandate, a 3,285-pile job at Gadarwara, and a Rs 17.94 crore Nabinagar piling contract. The comparison shows that the temple project has the highest pile count, while Gadarwara requires the greatest depth, reinforcement volume and service-crane allocation among the disclosed sites.
The next milestones disclosed in the presentation are tied to the host developments rather than completion dates for SIS’s individual contracts. Virat Ramayan Mandir is expected around 2026-2027, while Nabinagar’s Phase II units are targeted for commissioning between 2029 and 2030; SIS does not provide project-level completion schedules, revenue-recognition timing or a contract value for Gadarwara.