Supreme Petrochem sets second mABS line for December 2028
Key highlights
- Supreme Petrochem entered the second 70 KTPA mABS technology agreement on November 12, 2026.
- The second mABS line is estimated for mechanical completion by December 2028.
- Supreme Petrochem has disclosed Rs 450 crore of investment for the second line, funded through internal accruals.
- The existing 70 KTPA mABS line was reported at 60% utilisation.
powered by IRIS

Supreme Petrochem Ltd entered a technology agreement with Versalis S.p.A. Italy on November 12, 2026 for a second 70 KTPA mABS line, estimated for mechanical completion in December 2028. The Rs 450 crore project would complete its disclosed two-line 140 KTPA plan and is to be funded through internal accruals.
Know Supreme Petrochem inside out
Results, valuation, peers and who's buying, in one view.
What did Supreme Petrochem agree with Versalis?
Supreme Petrochem agreed with Versalis S.p.A. Italy on technology for the second 70 KTPA mABS line on November 12, 2026. The company disclosed the agreement on November 17, 2026 under Regulation 30 of the Securities and Exchange Board of India (SEBI) Listing Obligations and Disclosure Requirements Regulations, 2015. It said the signed copy of the agreement was received on the morning of its November 17 announcement.
The November 2026 agreement follows disclosures dated December 3, 2021 and January 21, 2022, when Supreme Petrochem said it planned two mABS lines of 70 KTPA each. The company also said a technology agreement with Versalis for the first 70 KTPA line had already been executed at that stage. The current filing does not disclose the technology fee, contract duration, equipment suppliers, plant location or interim construction milestones for the second line.
How will the second line change Supreme Petrochem's mABS capacity?
The second line will add 70 KTPA, or thousand tonnes per annum, to Supreme Petrochem's existing first-line capacity of 70 KTPA, taking the disclosed two-line mABS capacity plan to 140 KTPA. The annexure classifies the first 70 KTPA as existing capacity and the second 70 KTPA as a proposed capacity addition. The proposed addition is therefore equal to the existing line's nameplate capacity.
The agreement advances the second half of the 140 KTPA plan rather than increasing the ultimate capacity target disclosed in December 2021 and January 2022. Supreme Petrochem reported 60% utilisation for the existing 70 KTPA line, while it gave no utilisation target for the proposed second line. The filing also does not identify the period covered by the 60% figure or disclose actual mABS production in tonnes.
Got a follow-up? Ask IRIS
What will the second mABS line cost and when is it due?
Supreme Petrochem has put the investment required for the second 70 KTPA mABS line at Rs 450 crore and identified internal accruals as its financing mode. The Rs 450 crore figure in the November 17, 2026 annexure applies to the second line, not to the aggregate 140 KTPA two-line plan. No allocation between technology, construction, utilities or other project costs was provided.
The company estimates mechanical completion of the second 70 KTPA line by December 2028, following the November 12, 2026 technology agreement. This gives a disclosed implementation timetable of just over two years from agreement execution to the stated completion milestone. Supreme Petrochem did not provide a commissioning date, commercial-production date, trial-run schedule or annual spending plan after the December 2028 mechanical-completion estimate.
Why is Supreme Petrochem adding a second mABS line?
Supreme Petrochem cited growing demand for ABS products in India as the rationale for the additional 70 KTPA mABS line. The statement is the company's disclosed rationale for the Rs 450 crore project, rather than a quantified market forecast. Its November 2026 filing gives no Indian demand-growth rate, customer order volume, product pricing assumption or sales projection for the added capacity.
The expansion is being pursued while the existing 70 KTPA first line is reported at 60% utilisation. The filing presents that utilisation measure alongside the proposed 70 KTPA addition and the December 2028 target, but does not explain the operational period behind the percentage. It also does not disclose customer commitments, feedstock arrangements or the expected ramp-up path once the second line is mechanically complete.
Conclusion
The November 2026 agreement gives Supreme Petrochem a technology step toward the second 70 KTPA mABS line in its previously disclosed 140 KTPA plan. The proposed capacity addition matches the existing 70 KTPA line, while the first line was reported at 60% utilisation. The company has attached Rs 450 crore of investment and internal-accrual funding specifically to the second line.
The next disclosed project milestone is mechanical completion in December 2028. Investors will need to watch for future Supreme Petrochem announcements on construction progress, commissioning and commercial production, as well as any update on utilisation of the existing 70 KTPA line or a target for the new line after completion.