VijayPD targets Q1 FY28 API start after ₹10.83 crore capex
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- VijayPD has fully utilised ₹10.83 crore of IPO capex for Phase 1 of its Shrirampur API facility.
- Construction of the Shrirampur plant is more than 70% complete, with commercial production targeted in Q1 FY28.
- Phase 1 is planned with 5 reactors, compared with 12 reactors at the proposed full build-out.
- VijayPD has technology in hand for 45 molecules, including 3 ready for commercialisation.
powered by IRIS

VijayPD targets Q1 FY28 commercial production at its Shrirampur active pharmaceutical ingredient (API) facility after fully utilising ₹10.83 crore of initial public offering (IPO) capex and completing more than 70% of construction. Phase 1 is planned with five reactors, while three of the 45 molecules are ready for commercialisation through technology transfer.
Know Vijaypd Ceutical inside out
Results, valuation, peers and who's buying, in one view.
When will VijayPD start API production?
VijayPD targets commissioning and commercial production at the Shrirampur facility in Q1 FY28. The presentation presents this as a target for a greenfield project, rather than reporting that API production has already started.
The facility is located at Shrirampur MIDC Industrial Area in Ahmednagar district, Maharashtra, about 250 km from Mumbai. VijayPD says the plant will operate under the same Maharashtra state regulator as its distribution premises, including its three licensed centres in the Mumbai region.
VijayPD has designed the facility for generic APIs, pharmaceutical intermediates and specialty chemicals, with design and documentation intended to meet European Union Good Manufacturing Practice (EU-GMP) standards. The presentation does not disclose a completed EU-GMP certification, inspection outcome or product approval for the site.
How much IPO capex has VijayPD used for the plant?
VijayPD says it has fully utilised the ₹10.83 crore of IPO capex earmarked for the Shrirampur plant, while construction is more than 70% complete. The funding covers the five-reactor Phase 1 of the manufacturing project.
The disclosed status marks progress from funding allocation to construction, but the source does not provide a separate cost-to-complete amount, revised project budget or monthly commissioning timetable. The Q1 FY28 date therefore remains management's stated production target rather than an achieved operational milestone.
The plant is a greenfield expansion into manufacturing, whereas VijayPD's existing distribution footprint covers the western suburbs, the Central line and the northern corridor of Mumbai. Its Goregaon West warehouse and corporate office covers 6,000 square feet, while the plant is roughly 250 km away in Shrirampur.
What manufacturing capacity is planned at VijayPD's Shrirampur plant?
VijayPD plans five reactors in Phase 1 and 12 reactors at full build-out. The IPO-funded first phase includes 1 kilolitre (KL) vessels for small batches, while the seven additional reactors are planned after Phase 1 becomes commercial.
VijayPD says the reactor configuration will use a mix of vessel sizes, including 1 KL reactors, to support small production batches. Management describes this format as suitable for high-value, limited-volume APIs and for contract manufacturing organisation (CMO) and contract development and manufacturing organisation (CDMO) work.
The full 12-reactor configuration is not described as current construction funded by IPO proceeds. VijayPD says the additional seven reactors will be financed from internal accruals once the five-reactor Phase 1 has reached commercial operation.
Got a follow-up? Ask IRIS
Which API products can VijayPD launch first?
VijayPD has technology in hand for 45 molecules and says three are fully ready for commercialisation through technology transfer without a development cycle. The presentation does not identify the names of those three launch-ready molecules.
The portfolio is divided across six therapeutic groups, led by 10 central nervous system molecules, eight cardiovascular and antihypertensive molecules, and seven anti-diabetic molecules. Anticoagulants and antiplatelets account for six molecules, corticosteroid and anti-inflammatory products account for three, and 11 fall across lipid-lowering, gastrointestinal, urology, anti-infective and other categories.
VijayPD has also disclosed customer and technical arrangements ahead of plant operations. Ann Finechem LLP signed a memorandum of understanding for bulk purchases of two anti-malarial APIs worth ₹30.2 crore over one year, although VijayPD says this engagement has been substantially executed through sourced supply.
Squadron Pharmaceuticals LLP has submitted an expression of interest for export contract manufacturing of Sitagliptin, Apixaban and Rivaroxaban. Acute Research Private Limited is to provide route selection, process development, scale-up, technology transfer, analytical validation, regulatory documentation and audit support.
How does VijayPD plan to expand beyond Phase 1?
VijayPD plans to add seven reactors from internal accruals after Phase 1 is commercial, increasing the facility from five to 12 reactors. This plan makes the larger reactor count dependent on commercialisation of the initial IPO-funded phase.
The company has submitted an application under the Government of India's Production Linked Incentive (PLI) Scheme and describes the facility as eligible for benefits. The presentation does not state that PLI support has been approved, quantify a potential incentive or report that any amount has been received.
VijayPD also plans an export programme across more than 20 countries, including the United States, Europe, Japan, the Commonwealth of Independent States, the Middle East and North Africa, and Latin America. Its stated API export sequence is Europe first, followed by other regulated and semi-regulated markets.
Conclusion
VijayPD has committed the full ₹10.83 crore of disclosed IPO capex to a manufacturing project that is more than 70% constructed and targeted to begin commercial production in Q1 FY28. The five-reactor first phase combines three launch-ready molecules, a 45-molecule technology portfolio and externally disclosed customer, technical and regulatory-support arrangements, but production has not yet been reported.
The next disclosed matters to watch are completion and commissioning of the five-reactor Phase 1 facility, progress against the Q1 FY28 commercial-production target and the outcome of the submitted PLI application. VijayPD's plan to install seven further reactors also depends on internal accruals after Phase 1 becomes commercial.