Vishnu Prakash R Punglia Limited books Rs 35.692 crore provisions
Key highlights
- VPRPL recorded Rs 35.692 crore of exceptional items in the quarter ended September 30, 2026.
- The Bikaner charge comprised Rs 19.947 crore of ECL and Rs 15.745 crore of WIP provision.
- VPRPL reported a September-quarter loss before tax of Rs 32.645 crore, compared with a Rs 3.366 crore profit a year earlier.
- Trade receivables were Rs 591.540 crore and cash and cash equivalents were Rs 39.5 lakh at September 30, 2026.
powered by IRIS

Vishnu Prakash R Punglia Limited booked Rs 35.692 crore of exceptional items in the quarter ended September 30, 2026, following the rescission of a Bikaner station contract, including Rs 19.947 crore for encashed guarantees and forfeited deposits and Rs 15.745 crore for work-in-progress at the site.
Know Vishnu Prakash R Punglia inside out
Results, valuation, peers and who's buying, in one view.
Why did VPRPL book Rs 35.692 crore of exceptional items?
VPRPL booked Rs 35.692 crore because North Western Railway rescinded the engineering, procurement and construction contract for the major upgradation of Bikaner Railway Station that had been awarded to the VPRPL-KSIPL BKN JV. Chief Engineer (Construction-I), North West Railway, Jaipur issued the termination notice on May 11, 2026, according to the financial-results notes.
The railway authority encashed the performance bank guarantee and forfeited the security deposit of Rs 19.947 crore on October 5, 2026. VPRPL recognised this amount as an expected credit loss, or ECL, provision. Expected credit loss is an accounting estimate of the amount that may not be recovered from a financial exposure.
VPRPL also provided Rs 15.745 crore for expected loss in work-in-progress, or WIP, inventory at the Bikaner site. The two components total Rs 35.692 crore and were reported as exceptional items in both the quarter and half year ended September 30, 2026. The provision reflects the reported accounting treatment of the contract action while the related court case remains pending.
What was the earlier Jaipur-Sawai Madhopur contract impact?
VPRPL had previously recognised an ECL provision of Rs 9.964 crore after the Jaipur-Sawai Madhopur Doubling Project contract was rescinded on January 13, 2026. Chief Engineer (Construction)-III, North Western Railway subsequently encashed the performance bank guarantee and forfeited the security deposit for an aggregate Rs 9.964 crore.
That charge was disclosed as an exceptional item in the quarter ended December 31, 2025 and year ended March 31, 2026, rather than in the September 2026 quarter. It therefore differs from the Rs 35.692 crore exceptional item recorded for the Bikaner contract during the current reporting period.
The two disclosed railway-contract matters represent Rs 45.656 crore of stated provisions or adverse recoverability effects: Rs 9.964 crore for Jaipur-Sawai Madhopur and Rs 35.692 crore for Bikaner. The Bikaner charge is larger because it includes both the Rs 19.947 crore ECL on guarantees and deposits and the Rs 15.745 crore WIP provision, whereas the earlier matter disclosed only the ECL provision.
How did the Bikaner provisions affect VPRPL's September results?
VPRPL reported a loss before tax of Rs 32.645 crore for the quarter ended September 30, 2026, compared with a profit before tax of Rs 3.366 crore in the quarter ended September 30, 2025. Before exceptional items, it reported profit before tax of Rs 3.047 crore, so the Rs 35.692 crore exceptional charge moved the quarter into a pre-tax loss.
Revenue from operations declined to Rs 168.186 crore in the September 2026 quarter from Rs 295.685 crore a year earlier. The filing nevertheless shows an increase from Rs 137.878 crore in the preceding June 2026 quarter, the quarter-on-quarter revenue change cited by management in its going-concern assessment.
For the half year ended September 30, 2026, revenue from operations was Rs 306.364 crore, down from Rs 575.600 crore in the prior-year half year. Loss before tax was Rs 83.010 crore, against profit before tax of Rs 13.879 crore a year earlier, while loss after tax was Rs 64.611 crore compared with profit after tax of Rs 10.655 crore.
Got a follow-up? Ask IRIS
What legal action has VPRPL taken over the rescissions?
VPRPL has filed Civil Writ Petition S.A.W. No. 1214/2026 against Chief Engineer (Construction-I), North West Railway, Jaipur and others over the Bikaner termination. The matter was pending for final hearing and adjudication before the Rajasthan High Court, Jodhpur when the September 30, 2026 results were issued on November 14, 2026.
VPRPL has also filed S.A.W. No. 1213/2026 against Chief Engineer (Construction)-III, North Western Railway over the Jaipur-Sawai Madhopur project. That matter was likewise pending for final hearing and adjudication, following the January 13, 2026 termination and the Rs 9.964 crore encashment and forfeiture.
Management said it expects to succeed in both proceedings and sees a high likelihood of contract restoration and reversal of the adverse actions, based on what it described as legal and factual grounds. This is management's view rather than a court outcome, and the company recorded the Rs 9.964 crore and Rs 35.692 crore provisions despite that expectation.
What do VPRPL's ECL and liquidity disclosures show?
VPRPL said that it changed its ECL estimates for trade receivables under Indian Accounting Standard 109, Financial Instruments, during the period, reducing ECL provision and loss by Rs 64.007 crore for the September 2026 quarter and half year. Separately, the quarterly results state that other expenses were negative because of a reversal of a Rs 15.760 crore ECL provision made in the June 2026 quarter.
Trade receivables stood at Rs 591.540 crore at September 30, 2026, compared with Rs 576.768 crore at March 31, 2026. Cash and cash equivalents fell to Rs 39.5 lakh from Rs 81.6 lakh over the same six-month period, while total assets declined to Rs 1,831.223 crore from Rs 1,880.251 crore.
VPRPL said delayed collection from government departments and government-backed authorities had created temporary liquidity constraints and led it to temporarily slow operations. Management said improved debtor realisation, the increase in quarterly revenue, promoter support and continuing operations support its assessment that it can meet obligations as they fall due.
The limited-review auditor drew attention to delayed receivable realisation and said the resulting severe cash crunch may create uncertainty about operations and the ability to continue as a going concern. The auditor did not modify its conclusion and separately highlighted the two railway-related exceptional items and the ECL-estimate reversal.
Conclusion
The September 2026 charge principally concerns the Bikaner Railway Station contract, where VPRPL provided Rs 19.947 crore for the encashed guarantee and forfeited deposit and Rs 15.745 crore for site WIP. Alongside the earlier Rs 9.964 crore Jaipur-Sawai Madhopur provision, the filing identifies Rs 45.656 crore of reported adverse effects from two North Western Railway contract rescissions.
The next disclosed events to watch are final hearings in S.A.W. No. 1213/2026 and S.A.W. No. 1214/2026, where management seeks restoration of the contracts and reversal of the adverse actions. The filing also leaves receivable collection unresolved, with Rs 591.540 crore of trade receivables and Rs 39.5 lakh of cash and cash equivalents at September 30, 2026.