W.S. Industries wins Rs 48 crore in two CMK civil subcontracts
Key highlights
- W.S. Industries secured approximately Rs 48 crore of civil-related subcontracts excluding GST on November 18, 2026.
- The approximately Rs 25 crore NMDC housing subcontract covers nine towers with 360 Type-III quarters.
- The approximately Rs 23 crore HAL Helicopter Factory contract covers Phase I smart-township infrastructure.
- Both contracts have a 12-month execution period and are subject to quarterly Audit Committee review as related-party transactions.
powered by IRIS

W.S. Industries (India) Limited secured approximately Rs 48 crore of civil-related subcontracts, excluding goods and services tax (GST), from promoter-group entity CMK Projects Private Limited on November 18, 2026, comprising approximately Rs 25 crore for NMDC housing work and Rs 23 crore for a HAL Helicopter Factory township project. Each work order is proposed to be executed within 12 months from its respective commencement date.
Know W S Industries (India) inside out
Results, valuation, peers and who's buying, in one view.
What contracts has W.S. Industries secured from CMK Projects?
W.S. Industries has secured two domestic civil-related subcontracts from CMK Projects worth approximately Rs 48 crore excluding GST, which its board noted on November 18, 2026. The Audit Committee approved the transactions at its meeting held on the same date, according to the disclosure. The announced consideration comprises an approximately Rs 25 crore NMDC civil package and an approximately Rs 23 crore HAL Helicopter Factory civil package.
The NMDC package is the larger of the two awards at approximately Rs 25 crore, exceeding the HAL package by approximately Rs 2 crore. The filing describes all three values as approximate and expressly excludes GST. CMK Projects is the awarding entity for both work orders, while W.S. Industries is to execute the subcontracted civil work under the respective work-order terms.
What work is included in the NMDC and HAL packages?
W.S. Industries will construct nine residential towers for the approximately Rs 25 crore NMDC package, comprising 360 Type-III quarters at NMDC Donimalai Township in Karnataka. Each tower is specified as stilt plus 10 floors. The announcement calls the assignment civil-related sub-works and does not disclose a tower-wise or unit-wise division of the approximately Rs 25 crore value.
The approximately Rs 23 crore HAL package covers infrastructure development for a smart township of the HAL Helicopter Factory at Biderahalla Kaval, Gubbi Taluk, Tumakuru District, Karnataka. W.S. Industries identified this assignment as Phase I. Unlike the NMDC order, the filing does not give a count of buildings, homes or units for the HAL work, but defines its scope as township infrastructure development.
The two Karnataka packages cover different civil-work segments: residential construction at NMDC Donimalai Township and infrastructure for the HAL smart township. At approximately Rs 25 crore, the NMDC residential package accounts for more of the approximately Rs 48 crore combined value than the approximately Rs 23 crore HAL Phase I package. W.S. Industries has not disclosed commencement dates, project milestones, billing schedules or revenue-recognition timing for either order.
Got a follow-up? Ask IRIS
Why are the civil subcontracts related-party transactions?
The two subcontracts are related-party transactions because CMK Projects is in the promoter group of W.S. Industries. The filing also states that C.K. Venkatachalam, Managing Director of W.S. Industries, is a director of CMK Projects. That director overlap and the promoter-group relationship are the disclosed connections relating to the approximately Rs 48 crore work orders.
W.S. Industries said the transactions are governed by applicable provisions of the Companies Act, 2013 and the Securities and Exchange Board of India listing regulations. These requirements cover approval, disclosure, monitoring and review of related-party transactions. The Audit Committee approved the subcontracts on November 18, 2026, before the board took note of them at its meeting that day.
W.S. Industries did not state that the transactions had already been certified as being at arm's length. Instead, it said the arm's-length nature will be reviewed by the Audit Committee every quarter with other related-party transactions. The review is to be conducted in accordance with shareholder approvals obtained at W.S. Industries' 63rd Annual General Meeting, wherever applicable.
When will W.S. Industries execute the work and what happens next?
W.S. Industries proposes to execute each subcontract within 12 months of its respective commencement date, in line with the terms and conditions of the work orders. The announcement identifies CMK Projects as a domestic entity and classifies both awards as domestic civil-related subcontracts. It does not provide the physical start dates or a project-by-project completion calendar.
The board meeting that noted the approximately Rs 48 crore subcontracts started at 16:02 hours and ended at 17:06 hours on November 18, 2026. At the same meeting, the board considered separate in-principle initiatives in data centres, digital infrastructure and investments in engineering, procurement and construction, or EPC, entities. The company described those initiatives as exploratory or at an in-principle stage, unlike the civil subcontracts it said it had secured.
For the proposed data-centre activity, W.S. Industries approved engagement of The Boston Consulting Group (India) Private Limited and The Boston Consulting Group UK LLP as consultants. It also gave in-principle approval to lease up to 100 acres of its Sunguvarchatram, Tamil Nadu land holdings to its wholly owned subsidiary and to make EPC investments of up to Rs 3 crore to seek controlling interests. The company said these proposals remain subject to further corporate, shareholder and statutory approvals where applicable.
Conclusion
The approximately Rs 48 crore award gives W.S. Industries two disclosed civil-work assignments in Karnataka: approximately Rs 25 crore to construct 360 NMDC residential units across nine towers and approximately Rs 23 crore for HAL smart-township infrastructure. The promoter-group status of CMK Projects and the directorship held by W.S. Industries' Managing Director at CMK Projects place the work within the company's related-party transaction oversight process.
The next disclosed operational milestone is execution of the two work orders within 12 months from their respective commencement dates, alongside quarterly Audit Committee review of their arm's-length nature. W.S. Industries also said its proposed lease of up to 100 acres for digital infrastructure, its up to Rs 3 crore EPC investment plan and its data-centre initiatives require further evaluation or approvals, and may be modified, deferred or not pursued.