Adani Energy Solutions Acquires Vikramshila Power for ₹18.53 Crore
Key highlights
- Adani Energy Solutions acquired 100% of Vikramshila Power Transmission for ₹18.53 crore on November 21, 2026.
- The transfer covers 50,000 equity shares and all assets and liabilities of the project SPV.
- The SPV will implement transmission infrastructure to evacuate 2,400 MW from the Pirpainti project in Bihar.
- The project includes 881 circuit km of lines, 3,160 MVA of capacity and a fourth-quarter 2028 delivery target.
powered by IRIS

Adani Energy Solutions Limited acquired 100% of Vikramshila Power Transmission Limited for ₹18.53 crore on November 21, 2026, taking ownership of the special purpose vehicle for evacuating power from Bihar’s planned 2,400 MW Pirpainti thermal project. The transfer moves the project into its implementation phase under the successful bidder.
Know Adani Energy Solutions inside out
Results, valuation, peers and who's buying, in one view.
What did Adani Energy Solutions acquire?
Adani Energy Solutions Limited acquired the entire share capital of Vikramshila Power Transmission Limited from REC Power Development and Consultancy Limited, a wholly owned subsidiary of REC Limited. The Share Purchase Agreement was executed on November 21, 2026, following the completion of the tariff-based competitive bidding process.
The transaction covers 50,000 equity shares, representing 100% of Vikramshila Power Transmission. RECPDCL confirmed receipt of consideration of ₹18,53,10,081, inclusive of applicable taxes, professional fees and reimbursement of expenses. All assets and liabilities associated with the project-specific special purpose vehicle were transferred to AESL.
Following the transfer, Vikramshila Power Transmission ceased to be a subsidiary of RECPDCL and REC from the agreement date. REC stated that the SPV’s contribution to its turnover, revenue and net worth was negligible.
Why did AESL buy Vikramshila Power Transmission?
AESL bought the SPV to develop the transmission system titled “Evacuation of Power from 3X800 MW STPP Pirpainti.” The project is intended to carry electricity from the upcoming 2,400 MW Pirpainti thermal power plant and reinforce Bihar’s intra-state transmission network.
The acquisition follows AESL’s selection as the successful bidder through the tariff-based competitive bidding route. Under this framework, RECPDCL acted as bid process coordinator and formed the SPV for the project before transferring it to the winning developer.
AESL is to implement the project on a Build, Own, Operate and Transfer basis. The company has indicated that the transmission system is targeted for delivery by the fourth quarter of 2028. The company has said the project is expected to earn an annual transmission tariff of about ₹500 crore once commissioned.
What infrastructure is planned for the Pirpainti evacuation project?
The planned system includes 881 circuit kilometres of transmission lines and 3,160 MVA of transformation capacity. Its purpose is to connect the proposed generation facility with Bihar’s grid infrastructure through high-voltage transmission corridors and substations.
The disclosed scope includes four gas-insulated substations at Jhanjharpur, Bethauli and Begusarai, alongside associated transformation infrastructure. It also includes 400 kV double-circuit transmission lines linking Pirpainti with Jhanjharpur and Begusarai, and a line between Begusarai and Bakhtiyarpur.
Other works include 220 kV double-circuit lines between Jhanjharpur and Bethauli and within Begusarai, along with line-in-line-out arrangements for existing 220 kV and 132 kV lines at Jhanjharpur. The scheme also provides for 400 kV line bays at the Bakhtiyarpur grid substation.
Got a follow-up? Ask IRIS
How does the transfer affect REC and AESL?
For REC, the sale completes the disposal of a project-specific SPV after the bidding process. The company said Vikramshila Power Transmission’s financial contribution was negligible, indicating that the transfer is not material to REC’s operating revenue or net worth on the facts disclosed.
REC also clarified that the transaction is not a slump sale and is not a related-party transaction. AESL is not part of REC’s promoter or promoter group. The disposal was completed in accordance with Ministry of Power guidelines applicable to the project process.
For AESL, ownership of the SPV provides the project vehicle through which the Pirpainti evacuation infrastructure will be developed. The acquisition consideration reflects the transfer of the SPV and related expenses, while the broader transmission construction and operational programme will be carried out under the BOOT project structure.
What does the project mean for Bihar’s transmission network?
The project is designed to support evacuation from the proposed 3x800 MW Pirpainti thermal power plant. Without adequate transmission capacity, generation from a new power station cannot be delivered efficiently into the network, making the associated grid infrastructure integral to the power project’s operation.
The proposed substations, transformation capacity and transmission corridors are also intended to strengthen Bihar’s network. AESL has stated that the system will reinforce the state’s transmission backbone and improve supply reliability, although the infrastructure remains subject to execution and commissioning by the stated target date.
Conclusion
AESL’s ₹18.53 crore acquisition of Vikramshila Power Transmission formalises its control of the SPV created for the Pirpainti power evacuation scheme. REC and RECPDCL have exited the project vehicle after the competitive bidding process, while AESL assumes responsibility for developing the planned transmission assets.
The next disclosed milestone is delivery of the system by the fourth quarter of 2028. Investors can monitor project execution, progress on the planned 881 circuit km of lines and 3,160 MVA of transformation capacity, and any updates to the expected annual tariff of about ₹500 crore after commissioning.