Allcargo Terminals maps Rs 400 crore capex and debt option
Key highlights
- Allcargo Terminals outlined about Rs 400 crore of capex across Farukhnagar, Chennai, JNPT expansion and Speedy JNPT renovation.
- Management said Allcargo Terminals could raise about Rs 200 crore to Rs 250 crore of debt and potentially move towards a 1:1 debt-equity level.
- Allcargo Terminals expects Chennai construction to begin in the first quarter of the next financial year and take about nine months.
- Speedy JNPT throughput is targeted to rise from about 8,000 TEUs to close to 18,000 TEUs after renovation.
powered by IRIS

Allcargo Terminals Limited said during its Q2 and H1 FY27 earnings call that it plans about Rs 400 crore of expansion capital expenditure and may raise Rs 200 crore to Rs 250 crore of debt over one to one-and-a-half years. The spending pipeline includes Chennai, Farukhnagar, JNPT expansion and Speedy JNPT renovation.
Know Allcargo Terminals Ltd Partly Paidup inside out
Results, valuation, peers and who's buying, in one view.
What does Allcargo Terminals' Rs 400 crore capex plan cover?
Allcargo Terminals said its current expansion pipeline requires about Rs 400 crore of capital expenditure across its Farukhnagar inland container depot, Chennai facility, JNPT expansion, other facility expansion and the renovation of Speedy JNPT. Management did not provide a project-level allocation, return target or individual commissioning cost during the Q2 and H1 FY27 call.
The programme follows higher throughput and high reported utilisation at existing locations. Allcargo Terminals handled 1,90,100 twenty-foot equivalent units (TEUs) in Q2 FY27, up 12.6% year on year, and 3,66,599 TEUs in H1 FY27, up 10%. Management said terminals were operating at about 90% to 95% capacity and that October recorded the company's highest monthly volume, without disclosing October TEUs.
Revenue increased by Rs 72 crore in H1 FY27, while earnings before interest, tax, depreciation and amortisation (EBITDA), excluding other income, increased by Rs 31 crore. In Q2 FY27, revenue was Rs 252 crore, up 21.5% year on year and 17.4% sequentially, while EBITDA rose 45.9% year on year to Rs 59 crore.
How will Allcargo Terminals fund the expansion?
Allcargo Terminals said it is currently unleveraged and may add debt as growth opportunities arise, potentially moving towards a 1:1 debt-equity level. Management cited an ability to raise about Rs 200 crore to Rs 250 crore of debt, but did not disclose a lender, borrowing cost, maturity profile or a completed financing arrangement.
Management said the Rs 400 crore was available internally and that the combined internal and debt capacity could allow deployment of Rs 650 crore over one to one-and-a-half years. This was management's assessment of potential funding capacity, rather than a commitment to spend Rs 650 crore or an announced acquisition budget.
The potential borrowing is linked to organic opportunities and merger-and-acquisition possibilities under evaluation. Management said it would assess dividend payout over the next six months as those opportunities develop, but did not identify targets, transaction values or timelines for any acquisition, joint venture or tie-up.
When will Allcargo Terminals build its Chennai facility?
Allcargo Terminals expects to finalise land for the Chennai facility by the end of the month of the call, apply for customs clearance and begin construction in the first quarter of the next financial year. Management estimated that construction and operational readiness would take about nine months after work starts, without providing a specific commissioning date.
The Chennai site is intended to be close to the Kattupalli and Ennore terminals, where management said another round of container-terminal capital expenditure is planned. Management linked the location to expected growth around those terminals, but did not disclose Chennai project cost, committed customer volumes or a capacity figure on the call.
The project remains subject to the land and customs steps identified by management. Its ramp-up would follow an H1 FY27 base of 3,66,599 TEUs, while the company said container volumes in Q2 FY27 were 12.6% higher year on year.
Got a follow-up? Ask IRIS
When will Allcargo Terminals' Farukhnagar ICD start operations?
Allcargo Terminals said its Farukhnagar inland container depot, or ICD, is on track, with construction of the PFT expected to finish by the end of the financial year. Management expects limited PFT operations at the beginning of the next financial year while ICD construction continues.
Management's stated target is to complete ICD construction by the end of the third quarter of the next financial year and begin full-fledged ICD operations in the fourth quarter. Allcargo Terminals said discussions with potential customers had begun and received positive responses, but it did not disclose signed contracts or contracted volumes.
Farukhnagar forms part of the Rs 400 crore pipeline alongside new Chennai capacity and upgrades at existing assets. Management said it is also evaluating hinterland opportunities, capacity additions within its portfolio, joint ventures and tie-ups, although it said no arrangement was sufficiently committed to disclose.
Can Speedy JNPT replace fading transshipment gains?
Allcargo Terminals expects the Speedy JNPT renovation to raise volume from about 8,000 TEUs currently to close to 18,000 TEUs after the upgrade. Management said the facility has been underutilised because of infrastructure-related reasons and that the higher utilisation could partly make up for transshipment business that may decline.
Management expects the transshipment margin contribution to continue in the short run, possibly through the next quarter, before tapering as Gulf-related conditions normalise. It estimated the transshipment effect at roughly Rs 500 per TEU on margin; reported Q2 FY27 EBITDA per TEU was Rs 3,366, including an estimated Rs 400 to Rs 450 contribution from transshipment shipments.
Revenue per TEU was Rs 14,388 in Q2 FY27, including about Rs 488 of transshipment impact, according to management. It said revenue per TEU excluding that effect would have been Rs 13,900, while rate increases introduced in the quarter should largely remain in place in coming quarters.
Conclusion
Allcargo Terminals is pairing an about Rs 400 crore expansion programme with a potential shift from an unleveraged position towards debt funding of up to Rs 250 crore. The plan covers new capacity at Chennai and Farukhnagar as well as Speedy JNPT renovation, against H1 FY27 revenue of Rs 466 crore and EBITDA excluding other income of Rs 106 crore.
The next disclosed milestones are Chennai land finalisation and customs clearance, construction beginning in the first quarter of the next financial year, Farukhnagar's limited initial operations at that year's start and full ICD operations in its fourth quarter. Investors can also watch Speedy JNPT's planned move from about 8,000 TEUs to close to 18,000 TEUs and management's six-month review of growth opportunities and dividend payout.