Ashoka Buildcon Is L1 for ₹865.90 Crore NHAI Expressway Work
Key highlights
- Ashoka Buildcon was declared L1 for an NHAI project with a quoted EPC price of ₹865.90 crore excluding GST.
- The project covers 26.6 km from Km 128.0 to Km 154.6 on the Vadodara-Mumbai Expressway in Gujarat.
- Ashoka Buildcon has an 18-month execution timeline for the eight-lane expressway balance work.
- The contract terms include a 10-year defect liability period.
powered by IRIS

Ashoka Buildcon Limited has been declared the lowest bidder for an ₹865.90 crore, excluding GST, National Highways Authority of India project to complete a 26.6-km eight-lane Vadodara-Mumbai Expressway section in Gujarat within 18 months. The L1 outcome places Ashoka Buildcon in the lead position in the tender process for the balance construction work under the EPC model.
Know Ashoka Buildcon inside out
Results, valuation, peers and who's buying, in one view.
What NHAI project has Ashoka Buildcon become L1 for?
Ashoka Buildcon has become L1 for the balance work of Package IX on the Vadodara-Mumbai Expressway, covering the Karvad to Jujuwa section in Gujarat. The scope involves constructing an eight-lane, access-controlled expressway from Km 128.0 to Km 154.6.
The National Highways Authority of India, or NHAI, is the project authority. Ashoka Buildcon disclosed in its regulatory filing dated November 5, 2026 that it had submitted a bid and was declared the lowest bidder for the package.
The quoted engineering, procurement and construction, or EPC, price is ₹865.90 crore excluding Goods and Services Tax. The project is domestic in nature, and the company stated that it does not involve a related-party transaction.
L1 refers to the bidder with the lowest evaluated price in a tender process. The disclosed status is a bid-stage development and indicates that Ashoka Buildcon has offered the lowest evaluated bid for the specified work.
What are the commercial terms of the Gujarat expressway work?
The Gujarat expressway project has an execution period of 18 months and a defect liability period of 10 years. Ashoka Buildcon's quoted EPC price of ₹865.90 crore excludes GST, which means the stated figure is the pre-tax contract value disclosed in the filing.
Under an EPC structure, the contractor is responsible for engineering, procurement and construction activities within the defined project scope. The assignment concerns unfinished or balance work on an existing expressway package rather than an entirely new route announcement.
The Karvad to Jujuwa stretch is part of the Vadodara-Mumbai Expressway and spans from Km 128.0 to Km 154.6. The distance between these chainages is 26.6 km. The work will create an eight-lane access-controlled corridor across this section in Gujarat.
Got a follow-up? Ask IRIS
How did the Ashoka Buildcon NHAI bid unfold?
Ashoka Buildcon submitted its bid for the NHAI package and was subsequently declared L1, according to its November 5 disclosure. The company identified the work as balance construction for the Vadodara-Mumbai Expressway section in Gujarat.
The announcement initially communicated the L1 status, the ₹865.90 crore quoted EPC price and the 18-month construction timeframe. Subsequent project details identified the assignment as Package IX, running between Karvad and Jujuwa.
The company has described NHAI as a domestic entity for this project. Its filing also noted that the transaction does not fall within the category of related-party transactions.
The reported project terms include a 10-year defect liability period after construction. This period forms part of the disclosed contract conditions and extends the contractor's responsibility for defects beyond the 18-month execution schedule.
Why does the L1 status matter for Ashoka Buildcon and the road sector?
The L1 declaration identifies Ashoka Buildcon as the bidder with the lowest evaluated price for a project valued at ₹865.90 crore excluding GST. For the company, it adds a sizeable potential EPC assignment linked to national highway development, subject to the tender process and applicable project formalities.
For the road construction sector, the tender concerns balance work on an access-controlled expressway. Such projects require execution across civil works, procurement and construction activities under defined schedules, with the 18-month timeline indicating the planned construction period for this package.
The project also has relevance for operations on the Vadodara-Mumbai Expressway corridor because it covers a 26.6-km section that remains subject to balance construction. The disclosed scope is limited to the Karvad-Jujuwa stretch and does not provide financial guidance, profit estimates or a revised company order-book figure.
Investors should distinguish between being declared L1 and the completion of all subsequent tender and contractual processes. Ashoka Buildcon's filing establishes its bid position, quoted price, scope and execution conditions, but it does not disclose revenue recognition timing or project-level profitability.
Conclusion
Ashoka Buildcon's L1 status for the ₹865.90 crore NHAI package places it at the lowest evaluated price for balance work on the eight-lane Karvad-Jujuwa section of the Vadodara-Mumbai Expressway. The project is an EPC assignment with an 18-month execution schedule and a 10-year defect liability period, while the quoted value excludes GST.
The next disclosed milestone to watch is the progression from the L1 bid-stage outcome through the applicable tender and contract process. Investors can also track execution against the stated 18-month timeline once the project moves into implementation.