HCC pursues ₹85,907 crore pipeline with transport-led backlog
Key highlights
- HCC reported a ₹12,901 crore order book in Q2 FY27.
- Transport represented 62% of HCC's order book, compared with 19% for hydro and 16% for water.
- HCC said it was pursuing a ₹85,907 crore pipeline, including 16 bids worth about ₹34,805 crore under evaluation.
- HCC reported ₹524 crore of new orders and ₹1,557 crore as its share of L1 bids in Q2 FY27.
powered by IRIS

Hindustan Construction Company Ltd. (HCC) reported a ₹12,901 crore order backlog in Q2 FY27, with transport accounting for 62%, while pursuing a ₹85,907 crore project pipeline, according to its November 5, 2026 presentation. The pipeline is prospective, while HCC separately identifies the backlog as its order book.
Know Hindustan Construction Company inside out
Results, valuation, peers and who's buying, in one view.
How is HCC's ₹12,901 crore order book allocated?
HCC's ₹12,901 crore order book is led by transport at 62%, followed by hydro at 19% and water at 16%. These three disclosed business lines account for 97% of the Q2 FY27 backlog; the presentation legend also includes nuclear and buildings but does not print its percentage share.
HCC also presents the order book geographically across Uttarakhand, Bihar, Maharashtra, Gujarat, Manipur, Tamil Nadu, Madhya Pradesh, Jammu and Kashmir, Bhutan, Rajasthan and others. The geographical chart displays shares of 32%, 17%, 10%, 9%, 8%, 8%, 7%, 3%, 3% and 2%, but the supplied presentation extract does not reliably associate each label with a named location.
The ₹12,901 crore backlog is separate from the ₹524 crore of new orders HCC reported in Q2 FY27. The presentation does not give a comparable prior-quarter or prior-year backlog figure, so it does not establish whether the total order book increased or decreased over those periods.
How concentrated is HCC's order book in transport?
HCC's order book is concentrated in transport because the segment's 62% share exceeds hydro and water combined at 35%. Transport is 43 percentage points above hydro, the next-largest disclosed segment at 19%, while water represents 16% of the Q2 FY27 backlog.
HCC's operating updates identify several transport-related projects under execution. At Indore Metro, tunnel-boring machine, or TBM, 1 and 2 lowering was completed, mining commenced from Airport Station, excavation was progressing across five stations, and cut-and-cover work was under way at two locations.
At Patna Metro PC 05 and PC 06, HCC said the Factory Acceptance Test had been completed, while casting-yard and infrastructure development were under way. The company also reported progress on foundations and bridge-segment construction at Agardanda Creek Bridge, although it did not disclose the individual values of these projects within the ₹12,901 crore backlog.
HCC said its Mumbai Coastal Road Project, Package II, received the Best Project award in the bridge and tunnel category at the 2026 Engineering News-Record Global Best Projects awards. The recognition does not change the 62% transport allocation, but it identifies bridge and tunnelling as part of HCC's disclosed transport execution activity.
Got a follow-up? Ask IRIS
What opportunities are included in HCC's ₹85,907 crore pipeline?
HCC is pursuing a ₹85,907 crore project pipeline, which is materially larger than its ₹12,901 crore order book but is not presented as secured work. The company distinguishes the pipeline from the order backlog and from orders received during Q2 FY27.
Within the pipeline, HCC reported 16 bids under evaluation worth about ₹34,805 crore, with HCC's share at about ₹32,386 crore. The difference between total bid value and HCC's share indicates that the disclosed tenders include bid structures where HCC does not hold the full tender value.
HCC also reported L1 bids worth ₹2,010 crore, of which its share was ₹1,557 crore. The presentation does not state when these bids may be awarded, which projects they cover, or how much of the ₹85,907 crore pipeline has advanced to the evaluation stage.
What does the Q2 FY27 update show about HCC's operating context?
HCC reported standalone turnover of ₹895.8 crore and standalone net profit of ₹36.8 crore in Q2 FY27, alongside ₹524 crore of new orders. Consolidated revenue was ₹896.8 crore and consolidated profit was ₹22.6 crore for the quarter, though the presentation does not allocate these financial measures between transport, hydro and water.
Standalone earnings before interest, tax, depreciation and amortisation, or EBITDA, margin was 12.2% in Q2 FY27, compared with 16.1% in Q2 FY26. This was a decline of 3.9 percentage points year on year; the presentation does not provide an explanation for the change.
HCC prepaid ₹100 crore of debt in Q2 FY27 and said management targeted a further ₹108 crore prepayment by December 2026. The company also said the Supreme Court upheld a ₹210 crore award in its favour and that the related monies were to be released in Q3 FY27.
Conclusion
HCC's disclosed workload position combines a ₹12,901 crore order book, dominated by transport at 62%, with a ₹85,907 crore pipeline under pursuit. The comparison is important because the order book represents HCC's identified secured workload, while the pipeline, the 16 bids under evaluation and the L1 bids remain subject to further tender and award processes.
The next disclosed items to watch are management's target to prepay another ₹108 crore of debt by December 2026 and the expected Q3 FY27 release of ₹210 crore from the Supreme Court-upheld award. Conversion of the ₹1,557 crore HCC share of L1 bids and about ₹32,386 crore of bids under evaluation into orders would also change the order-book position.