Hi-Tech Pipes reaches 1 million tonnes, targets 2m by FY29
Key highlights
- Hi-Tech Pipes achieved 1 million tonnes of installed annual capacity after Sikandrabad Unit-III started commercial production.
- Sikandrabad Unit-III adds 120,000 MTPA of ERW pipe and hollow-section capacity.
- Hi-Tech Pipes management targets 2 million tonnes of installed capacity by FY29.
- API pipes, the Sanand DFT facility and Hindupur expansion are expected by Q4 FY27.
powered by IRIS

Hi-Tech Pipes Limited has achieved 1 million tonnes of installed annual manufacturing capacity after starting commercial production at the 120,000-metric-tonnes-per-annum Sikandrabad Unit-III facility. Hi-Tech Pipes management is targeting 2 million tonnes of installed capacity by FY29, with API-grade pipes, a Sanand DFT facility and Hindupur expansion expected by Q4 FY27.
Know Hi-Tech Pipes inside out
Results, valuation, peers and who's buying, in one view.
How did Hi-Tech Pipes reach 1 million tonnes of installed capacity?
Hi-Tech Pipes reached 1 million tonnes of installed annual capacity when commercial production commenced at Sikandrabad Unit-III in Uttar Pradesh. The greenfield facility adds 120,000 metric tonnes per annum, or MTPA, and is focused on electric resistance welded, or ERW, pipes and hollow sections.
Hi-Tech Pipes said the Sikandrabad commissioning, together with recently commissioned capacities at other locations, delivered the 1 million-tonne milestone. The facility is intended to strengthen the company’s footprint in North and Central India, serving infrastructure, construction, water distribution, fabrication and industrial customers through closer access to consumption centres.
The milestone follows a rise in reported volume from 485,000 tonnes in FY25 to 532,000 tonnes in FY26, an increase of 47,000 tonnes. Hi-Tech Pipes reported 321,000 tonnes of volume in H1FY27, while EBITDA per metric tonne was Rs 3,299, compared with Rs 3,260 in FY26.
What do Sanand, Kathua and Sikandrabad add to Hi-Tech Pipes?
Hi-Tech Pipes’ Sanand Unit-II, Phase-II expansion adds 100,000 MTPA and is designed for large-diameter ERW pipes, jumbo hollow sections, and structural and fabrication-grade steel products. The Gujarat site is positioned to serve Western India’s solar, fabrication, engineering and infrastructure clusters and to enable exports of large-diameter ERW pipes and heavy hollow sections.
Hi-Tech Pipes said the Sanand project can reduce logistics costs to industrial hubs in Gujarat and neighbouring regions while improving its product mix toward larger diameters and value-added grades. The presentation also identifies the facility’s role in supplying solar, fabrication and infrastructure customers, rather than disclosing separate production or sales targets for the expansion.
The Kathua greenfield plant in Jammu and Kashmir has 80,000 MTPA of installed capacity for ERW steel pipes, coated products and other value-added steel products. Hi-Tech Pipes said the plant has modern manufacturing infrastructure, enhanced automation and quality-control systems, and can supply Jammu and Kashmir, Punjab and Himachal Pradesh.
Together, the three named facilities account for 300,000 tonnes per annum of disclosed capacity additions or installed capacity. Sikandrabad contributes 120,000 tonnes per annum, Sanand contributes 100,000 tonnes per annum and Kathua contributes 80,000 tonnes per annum, while their product focus differs across hollow sections, coated products and larger-diameter ERW pipes.
Got a follow-up? Ask IRIS
What is Hi-Tech Pipes’ capacity target for FY29?
Hi-Tech Pipes management is targeting 2 million tonnes of installed capacity by FY29, requiring a further 1 million tonnes beyond the newly achieved 1 million-tonne level. Management linked the roadmap to India’s infrastructure and industrial growth and described its aim as building a pan-India and globally competitive manufacturing platform.
The FY29 target is substantially above Hi-Tech Pipes’ reported production volumes to date. Annual volume increased from 277,000 tonnes in FY22 to 532,000 tonnes in FY26, a gain of 255,000 tonnes over four financial years, while H1FY27 volume of 321,000 tonnes equalled about 60% of the FY26 full-year total.
Hi-Tech Pipes reported revenue of Rs 4,200.07 crore in FY26, up from Rs 3,067.64 crore in FY25, and EBITDA of Rs 173.55 crore, compared with Rs 160.03 crore. In H1FY27, revenue was Rs 2,879.04 crore and EBITDA was Rs 105.95 crore; the presentation lists EBITDA margin as 3.68% for the half year and 4.13% for FY26.
The presentation does not disclose a capacity-utilisation target, capital expenditure figure or volume forecast for the additional 1 million tonnes planned by FY29. It instead identifies regional manufacturing reach, value-added products and the scheduled FY27 projects as parts of the broader expansion roadmap.
Which Hi-Tech Pipes projects are due by Q4 FY27?
Hi-Tech Pipes expects its API-grade oil and gas pipe facility to be completed by Q4 FY27. Management said the project is intended to serve oil and gas, industrial-pipeline and water-transmission applications, expand the addressable market and increase the share of high-value, precision-engineered products.
Hi-Tech Pipes also expects the new DFT facility at Sanand Unit-2, Phase-3 to be operational by Q4 FY27. Management said the facility is expected to improve production efficiency, optimise capacity utilisation across key product lines, shorten turnaround times and support entry into or deeper penetration of specialised pipe segments.
The fully integrated Hindupur expansion is likewise expected to become operational by Q4 FY27. Hi-Tech Pipes said the plant will manufacture ERW pipes, specialised solar pipes and other value-added steel products, and is intended to improve backward and forward integration while serving infrastructure, renewable-energy and industrial demand.
No capacity addition or project-spending figure is disclosed for the API, DFT or Hindupur projects. The stated schedule therefore provides the next operational markers, while the size of their contribution to the FY29 target remains unspecified in the presentation.
Conclusion
Hi-Tech Pipes has combined its 1 million-tonne installed-capacity milestone with a wider product and regional expansion programme. The 120,000-tonne-per-annum Sikandrabad unit, 100,000-tonne-per-annum Sanand expansion and 80,000-tonne-per-annum Kathua facility add different capabilities across ERW pipes, hollow sections, coated products and larger-diameter products.
The next disclosed milestones are completion of the API facility and operationalisation of the Sanand DFT and Hindupur facilities by Q4 FY27. Progress against those dates, along with any future disclosure on their capacity, spending and contribution to management’s 2 million-tonne FY29 target, will determine how the stated expansion roadmap develops.