K2 Infragen’s Rs 906.9 crore backlog is road-led, rail-heavy
Key highlights
- K2 Infragen reports Rs 906.9 crore of unexecuted work from total project value of Rs 1,185.8 crore.
- Roads account for 44.12% of pending work, equivalent to Rs 400.13 crore.
- Railways have Rs 343.14 crore unexecuted, equal to 88.1% of their Rs 389.56 crore segment order book.
- K2 Infragen lists 11 active projects, including a Rs 390.9 crore HAM-labelled project group and a Rs 222.1 crore railway electrification assignment.
powered by IRIS

In the presentation, K2 Infragen reports a Rs 906.9 crore unexecuted backlog led by roads at 44.12% and railways at 37.84%, which together account for 81.96% of work awaiting execution. Total project value is Rs 1,185.8 crore, and the company lists 11 active projects across roads, power, railways and civil construction.
Know K2 Infragen inside out
Results, valuation, peers and who's buying, in one view.
What is K2 Infragen’s unexecuted order book?
K2 Infragen’s unexecuted order book is Rs 906.9 crore, compared with total project value of Rs 1,185.8 crore. The arithmetic difference is Rs 278.9 crore, representing the portion of the aggregate portfolio that has been executed. The presentation’s sector distribution covers roads, railways, power, renewable energy and civil work projects.
Roads account for 44.12% of the unexecuted balance, while railways account for 37.84%. Their combined 81.96% share makes transport-related assignments the principal source of work pending execution. Power represents a further 17.16%, leaving renewable energy at 0.84% and civil work projects at 0.04%.
The presentation does not provide award dates, contract completion dates or a company-wide execution schedule for the Rs 906.9 crore balance. It therefore shows the value and sector composition of work yet to be delivered, rather than revenue expected in a specified financial year. It does identify 11 active projects in roads, power transmission, railways and civil building construction.
Which sectors make up K2 Infragen’s pending work?
K2 Infragen’s roads and bridges segment has Rs 400.13 crore unexecuted, ahead of railways at Rs 343.14 crore and power transmission and distribution at Rs 155.66 crore. Together, these three segments account for Rs 898.93 crore of the aggregate Rs 906.9 crore unexecuted order book.
Railways have a smaller total order book than roads, Rs 389.56 crore against Rs 593.18 crore, but a larger proportion remains unfinished. The railway portfolio is 88.1% unexecuted, compared with 67.5% for roads. Power has an 81.1% unexecuted share, leaving Rs 155.66 crore outstanding from its Rs 191.95 crore segment order book.
The two smallest categories have different execution positions. Renewable energy has Rs 7.62 crore unexecuted from a Rs 8.11 crore order book, while civil work projects have Rs 33 lakh outstanding from Rs 3.01 crore. K2 Infragen describes renewable energy as a strategic entry segment and says it is expanding towards an independent power producer model with annuity-based revenue and long-term asset ownership.
Got a follow-up? Ask IRIS
Which active projects does K2 Infragen identify?
K2 Infragen identifies projects valued at Rs 390.9 crore under the HAM label and Rs 134.4 crore under the NWR-KRCL label. The Rs 390.9 crore project group is the largest specifically identified group in the active-project list, ahead of the Rs 222.1 crore railway electrification assignment and the Rs 142.1 crore Gujarat highway project.
Railway work includes the Bhildi-section project in Jodhpur Division, involving a two-by-25 kilovolt system and carrying a stated value of Rs 222.1 crore. K2 Infragen also lists Rs 33.1 crore for design, supply, erection, testing and commissioning of two-by-25 kilovolt high-rise overhead electrification and associated modifications. A road-over-bridge at level crossing No. 242 on the Itarsi-Jabalpur section is valued at Rs 23.6 crore.
The active road portfolio includes the Rs 142.1 crore Gujarat highway project and a Rs 48.3 crore Uttar Pradesh highway project. In power, the company lists an Rs 86 crore project for a 110/11 kilovolt substation, two 20 megavolt-ampere units and a 110 kilovolt double-circuit line. Other listed power assignments include a Rs 34.6 crore transmission-substation augmentation in Madhya Pradesh and a Rs 28.5 crore 66/11 kilovolt gas-insulated substation.
The active-project list also contains Rs 48.2 crore of other projects. K2 Infragen does not state the completed proportion, expected finish date or remaining value for each named contract. The list consequently indicates project types and contract scale, but does not reconcile each assignment with the segment-level unexecuted balances.
How have K2 Infragen’s segment revenues changed?
K2 Infragen’s road revenue rose from Rs 3.2 crore in financial year 2024 to Rs 62.7 crore in financial year 2025 and Rs 143.4 crore in financial year 2026. Revenue was Rs 23.8 crore in the first half of financial year 2027, a partial-year period that is not directly comparable with the earlier full-year figures.
Railway revenue increased from Rs 2.6 crore in financial year 2024 to Rs 13.6 crore in financial year 2025 and Rs 14.5 crore in financial year 2026, before reaching Rs 20.3 crore in the first half of financial year 2027. This segment has Rs 343.14 crore still unexecuted and the highest pending proportion among the three largest segments, at 88.1%.
Power revenue was Rs 65,000 in financial year 2024, Rs 6.8 crore in financial year 2025, Rs 21.8 crore in financial year 2026 and Rs 8.4 crore in the first half of financial year 2027. Its Rs 155.66 crore unexecuted balance is 81.1% of the power segment’s Rs 191.95 crore order book.
Water-supply revenue was Rs 59.5 crore in financial year 2023, Rs 101.4 crore in financial year 2024, Rs 62.3 crore in financial year 2025 and Rs 9 crore in the first half of financial year 2027, although water is absent from the disclosed order-book distribution. Civil-work revenue moved from Rs 1.1 crore in financial year 2024 to Rs 1.2 crore in financial year 2025 and Rs 5 crore in financial year 2026, then Rs 10 lakh in the first half of financial year 2027.
Conclusion
K2 Infragen’s disclosed pipeline is concentrated in three infrastructure segments, with roads providing the largest absolute balance and railways retaining the greatest unexecuted share among the main categories. The active portfolio spans highways, railway electrification, substations, transmission lines and civil works, which aligns with the sector composition of its Rs 1,185.8 crore total project value.
The next disclosed area to watch is progress in converting the Rs 343.14 crore railway and Rs 155.66 crore power balances, alongside the Rs 390.9 crore active-project group identified under the HAM label. K2 Infragen also says it is moving towards an independent power producer model and exploring tariff-based competitive bidding in renewable energy, but gives no project timing, capacity target or award value for that plan.