LCC Projects Limited JV wins Rs 728.51 crore Rajasthan order
Max Plan at ₹4,999/yr₹8,999
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- LCC Projects’ joint venture received a Rs 728.51 crore EPC turnkey contract, excluding Goods and Services Tax.
- LCC Projects holds a 15.00% share in the joint venture awarded the Rajasthan project.
- The Manoharthana Major Irrigation Project has a disclosed construction period of 36 months.
- The scope includes a dam, pressurised piped irrigation network, testing, commissioning, operation and maintenance.
powered by IRIS

LCC Projects Limited said on November 26, 2026 that its joint venture received a Letter of Acceptance for a Rs 728.51 crore Rajasthan engineering, procurement and construction, or EPC, turnkey order, excluding Goods and Services Tax, for dam and pressurised irrigation works. The construction period is 36 months and LCC Projects holds a 15.00% share in the venture.
Know LCC Projects inside out
Results, valuation, peers and who's buying, in one view.
What contract has LCC Projects received in Rajasthan?
LCC Projects has disclosed a Letter of Acceptance awarded to M/s Laxmi Civil Engineering Services Pvt. Ltd - LCC (JV) for the Manoharthana Major Irrigation Project in Rajasthan. The contract is valued at Rs 728.51 crore excluding Goods and Services Tax, and covers construction of a dam and development of a pressurised irrigation network for the project command area.
The November 26, 2026 filing classifies the award as an EPC turnkey contract. Its scope combines survey, design, construction, testing and commissioning, rather than identifying only one civil-work package. It also includes operation and maintenance of the dam and pressurised piped irrigation system, although the filing gives a 36-month construction period and no separate duration for operation and maintenance.
Who awarded the Rs 728.51 crore irrigation contract?
The Office of the Executive Engineer, Water Resources Division, Aklera, District Jhalawar, Rajasthan awarded the Rs 728.51 crore contract to the joint venture. LCC Projects identified the awarding party as a domestic entity and described the order as domestic, with the site located in Tehsil Manoharthana, District Jhalawar, Rajasthan.
The project falls under the Manoharthana Major Irrigation Project and is intended to irrigate its command area through a dam and pressurised piped network. The filing does not disclose the command-area size, the dam’s storage capacity, pipe-network length, or water-delivery capacity for the Rs 728.51 crore project.
LCC Projects said its promoters, promoter group and group companies have no interest in the awarding entity. It also stated that the order is not a related-party transaction, distinguishing the domestic award from a contract with a group-linked counterparty.
What work will the Manoharthana project include?
The Manoharthana project will include survey, design, construction, testing and commissioning of a dam and a pressurised piped irrigation system. The Rs 728.51 crore turnkey scope therefore extends beyond dam construction to development of the network intended to carry water to the command area in Tehsil Manoharthana.
Operation and maintenance are included alongside testing and commissioning in the announced scope. This means the joint venture’s disclosed responsibilities go beyond physical construction and include activities required to put the dam and irrigation system into service. However, LCC Projects has not disclosed milestones, payment terms, pipe quantities, or separate values for the dam and irrigation-network portions.
LCC Projects described the work as part of its regular civil-construction and contracting activities. That statement does not specify when revenue may be recognised, what margins may arise, or how the Rs 728.51 crore gross contract value may affect any existing order book.
Got a follow-up? Ask IRIS
What does LCC Projects’ 15.00% joint-venture share mean?
LCC Projects holds a disclosed 15.00% share in the joint venture that received the Rs 728.51 crore Letter of Acceptance. The announced value is therefore the gross contract value for M/s Laxmi Civil Engineering Services Pvt. Ltd - LCC (JV), rather than an order stated as being wholly executed by LCC Projects.
Applying the disclosed 15.00% share to the Rs 728.51 crore contract produces an arithmetic indication of Rs 109.28 crore. This calculation is not a separate order value, revenue figure or profit figure disclosed by LCC Projects, and it does not establish the company’s billing or work allocation under the joint-venture arrangement.
The filing does not state how the partners will divide construction work, costs, guarantees, billing, cash flows or profits. Compared with an order awarded directly to one company, the key disclosed change is that the entire Rs 728.51 crore value belongs to the joint venture while LCC Projects has a 15.00% stated participation. No prior-period order value or segment comparison was supplied.
When must the Rajasthan irrigation work be completed?
The construction period for the Rs 728.51 crore EPC turnkey project is 36 months, according to the annexure filed on November 26, 2026. LCC Projects did not provide a construction start date, interim milestones or a specific scheduled completion date.
The 36-month timetable applies to construction, while operation and maintenance are separately included in the project scope. The filing does not say whether operation and maintenance will begin during construction or after commissioning, and it does not give a duration or separate consideration for that component.
LCC Projects said it would update the market on further developments relating to the project. Until such an update, the disclosed facts remain the Letter of Acceptance, the Rs 728.51 crore value excluding Goods and Services Tax, the 15.00% joint-venture share, the Rajasthan site and the 36-month construction period.
Conclusion
The announced order gives the joint venture a Rs 728.51 crore, excluding Goods and Services Tax, dam and pressurised irrigation EPC project in Rajasthan. LCC Projects’ disclosed interest is 15.00%, while the scope combines survey and design with construction, testing, commissioning, operation and maintenance of the dam and piped irrigation system.
The next item to watch is execution against the disclosed 36-month construction period and any project update from LCC Projects. The filing leaves unresolved the division of work and economics within the joint venture, the payment and milestone schedule, and the duration of the operation-and-maintenance component.