Markolines wins Rs 234.8334744 crore in three orders
Key highlights
- Markolines disclosed three domestic orders worth Rs 234.8334744 crore on 16 November 2026.
- The Rs 120.282639 crore Middle Strait Creek bridge subcontract has an 18-month execution period.
- Two RKEC Projects Limited awards total Rs 178.12194 crore.
- The Rs 56.7115344 crore Andhra Pradesh complete-overlay order has a 180-day period including mobilisation.
powered by IRIS

Markolines Pavement Technologies Limited disclosed on 16 November 2026 that it had received three domestic road and bridge orders worth Rs 234.8334744 crore, including applicable goods and services tax (GST), led by an Rs 120.282639 crore bridge subcontract in the Andaman & Nicobar Islands. The stated execution windows range from 180 days to 18 months.
Know Markolines Pavement Technologies inside out
Results, valuation, peers and who's buying, in one view.
What orders did Markolines receive?
Markolines received two Letters of Award from RKEC Projects Limited and one Work Order from Ranastalam Anandapuram Road Limited. The largest award is for sub-contracting balance construction work on a major bridge over Middle Strait Creek, between Km. 106.590 and Km. 108.553 of NH-04, connecting South Andaman and Baratang Island in the Union Territory of Andaman & Nicobar Islands.
The Middle Strait Creek award has a consideration of Rs 120.282639 crore, including applicable GST, and is to be executed over 18 months. The filing describes the work as infrastructure and bridge-construction sub-contracting on an engineering, procurement and construction (EPC) basis, subject to the Letter of Award terms and subsequent documentation between the parties.
The second RKEC award covers rehabilitation, upgradation and completion of balance work from Km. 155.00 to Km. 181.00 of NH-4, from End of Jarwa to Rangat in the Andaman & Nicobar Islands. This road sub-contracting assignment is valued at Rs 57.839301 crore, including applicable GST, and has a stated execution period of six months.
The third order is from Ranastalam Anandapuram Road for major maintenance through complete overlay from Km. 634+000 to Km. 681+000 in Andhra Pradesh. Its consideration is Rs 56.7115344 crore, including applicable GST, and the Work Order specifies completion within 180 days, including mobilisation, from the commencement date.
How much are Markolines' three orders worth?
Markolines' three disclosed orders total Rs 234.8334744 crore, including applicable GST in each award. The Rs 120.282639 crore Middle Strait Creek bridge package is the biggest individual order, exceeding both the Rs 57.839301 crore Andaman road-rehabilitation award and the Rs 56.7115344 crore Andhra Pradesh overlay order.
The two awards from RKEC together amount to Rs 178.12194 crore, compared with Rs 56.7115344 crore for the Ranastalam Anandapuram Road order. The disclosed value is therefore weighted towards the two Andaman & Nicobar Islands assignments, while the bridge package alone accounts for more value than either road-focused award separately.
All three considerations are stated by Markolines as including applicable GST. The filing does not provide a split between the underlying work value and tax, nor does it disclose payment milestones, billing terms or the proportion of each order that may be recognised in any particular financial period.
What work will Markolines perform under the contracts?
Markolines will perform bridge construction, road rehabilitation, road upgradation and maintenance overlay work under the three domestic orders. The Rs 120.282639 crore RKEC bridge subcontract covers balance works over Middle Strait Creek on the NH-04 section between Km. 106.590 and Km. 108.553, with an 18-month execution timeline.
The Rs 57.839301 crore RKEC order involves rehabilitating, upgrading and completing balance work on the NH-4 section between Km. 155.00 and Km. 181.00. Unlike the bridge assignment, which is explicitly described as EPC-based work, this award is described in the filing as road rehabilitation and upgradation sub-contracting work.
Ranastalam Anandapuram Road's Rs 56.7115344 crore Work Order has a maintenance-oriented scope. Markolines is to provide a complete overlay over the Andhra Pradesh section from Km. 634+000 to Km. 681+000, under the scope and terms specified in that Work Order.
The three scopes differ by mechanism as well as location: bridge balance construction is in the Andaman & Nicobar Islands, rehabilitation and upgradation is also in the islands, and complete overlay maintenance is in Andhra Pradesh. Markolines classified the first as infrastructure and bridge construction, the second as road rehabilitation and upgradation, and the third as major maintenance and complete road overlay.
Got a follow-up? Ask IRIS
When must Markolines complete the projects?
Markolines has disclosed an 18-month execution period for the Rs 120.282639 crore Middle Strait Creek bridge order and a six-month period for the Rs 57.839301 crore NH-4 rehabilitation order. The bridge timeline is three times the period stated for the other RKEC assignment.
Both RKEC awards are subject to the respective Letters of Award and subsequent documentation between the parties. The filing does not state calendar start dates, interim construction milestones or scheduled completion dates for the two Andaman & Nicobar Islands projects beyond their stated 18-month and six-month periods.
The Rs 56.7115344 crore Andhra Pradesh overlay order must be executed in 180 days, including mobilisation, from the commencement date. Markolines did not disclose that commencement date, so the filing does not establish a calendar deadline for the work or indicate whether mobilisation had started as of 16 November 2026.
The different schedules place the 180-day overlay work and six-month rehabilitation work ahead of the 18-month bridge assignment on the disclosed timetable. However, the announcement contains no progress targets, financial-period revenue schedule or completion-certification mechanism for any of the three orders.
Who awarded the orders and are they related-party transactions?
Markolines identified RKEC Projects Limited as the awarding entity for the Rs 120.282639 crore bridge subcontract and the Rs 57.839301 crore road-rehabilitation award. Ranastalam Anandapuram Road Limited awarded the Rs 56.7115344 crore complete-overlay maintenance work in Andhra Pradesh.
Each of the three orders was awarded by a domestic entity and is classified as domestic in the filing. The two RKEC awards have a combined value of Rs 178.12194 crore, while the single Ranastalam Anandapuram Road order has a value of Rs 56.7115344 crore.
Markolines stated separately for each award that its promoter, promoter group and group companies have no interest in the entity awarding the order. It also stated that none of the Rs 120.282639 crore, Rs 57.839301 crore and Rs 56.7115344 crore orders falls within related-party transactions.
The disclosure identifies the counterparties, locations, values and contractual periods, but does not state the date of the Letters of Award or Work Order, apart from the company's 16 November 2026 disclosure date. It also does not disclose subcontracting margins, mobilisation advances or performance-security requirements.
Conclusion
The announced package combines three distinct domestic assignments worth Rs 234.8334744 crore: an 18-month bridge balance-work subcontract, a six-month highway rehabilitation award and a 180-day overlay-maintenance order. RKEC Projects Limited accounts for Rs 178.12194 crore across the two Andaman & Nicobar Islands awards, while the Andhra Pradesh overlay work accounts for Rs 56.7115344 crore.
What to watch next is progress against the disclosed six-month, 180-day and 18-month timelines. The RKEC awards remain subject to subsequent documentation, and the Andhra Pradesh order runs from an undisclosed commencement date; the filing provides no start dates, billing milestones or completion updates for the three projects.