NLC India Renewables Limited signs 275 MW Gujarat BESPA
Key highlights
- NIRL executed a BESPA with GUVNL for 275 MW and 550 MWh of standalone battery storage on 18 November 2026.
- The project allocates 150 MW and 300 MWh to Choraniya and 125 MW and 250 MWh to Virpore.
- GUVNL’s Phase IX tender covered 450 MW and 900 MWh, versus NIRL’s 275 MW and 550 MWh agreement.
- The filing does not disclose the BESPA tariff, project cost, agreement value or commissioning schedule.
powered by IRIS

NIRL executed a Battery Energy Storage Purchase Agreement with Gujarat Urja Vikas Nigam Limited for a 275 MW, 550 MWh standalone battery energy storage project in Gujarat, disclosed on 18 November 2026 after its successful bid in GUVNL’s 450 MW, 900 MWh Phase IX tender.
Know NLC India inside out
Results, valuation, peers and who's buying, in one view.
What agreement did NIRL sign?
NIRL signed a Battery Energy Storage Purchase Agreement, or BESPA, with Gujarat Urja Vikas Nigam Limited, or GUVNL, for a standalone Battery Energy Storage System, or BESS, with 275 MW of power capacity and 550 MWh of energy capacity. The agreement was disclosed by NLC India Limited on 18 November 2026 under Regulation 30 of the Securities and Exchange Board of India (Listing Obligations and Disclosure Requirements) Regulations, 2015.
The BESPA follows a Letter of Intent, or LoI, issued by GUVNL after NIRL was declared the successful bidder in the tender. NIRL is identified in the filing as a wholly owned subsidiary of NLC India Limited, while GUVNL is the entity that floated the Phase IX tender for 450 MW and 900 MWh of standalone storage.
The filing confirms that the agreement has been executed by NIRL and GUVNL, rather than only recording a bid result or an LoI. It does not state the date on which GUVNL issued the LoI or declared NIRL successful, so the time between the bid decision and the 18 November 2026 BESPA disclosure cannot be calculated from the announcement.
Where will NIRL's Gujarat battery capacity be located?
NIRL’s 275 MW and 550 MWh capacity is divided between 150 MW and 300 MWh at the 400 kilovolt Choraniya AIS substation and 125 MW and 250 MWh at the 220 kilovolt Virpore AIS substation. The two allocations total the full capacity covered by the BESPA.
Choraniya’s allocation is 25 MW and 50 MWh larger than Virpore’s allocation. The larger site accounts for 150 MW of the 275 MW contracted total, while Virpore accounts for the remaining 125 MW; their respective energy capacities are 300 MWh and 250 MWh.
At both substations, the disclosed energy capacity is twice the stated power capacity: 300 MWh against 150 MW at Choraniya and 250 MWh against 125 MW at Virpore. This comparison is based on the capacities in the filing; the announcement does not specify an operating-duration obligation, dispatch schedule, battery chemistry or technical configuration.
How does NIRL's agreement compare with GUVNL's tender?
NIRL’s BESPA covers 275 MW and 550 MWh, compared with GUVNL’s Phase IX tender for 450 MW and 900 MWh, leaving a difference of 175 MW and 350 MWh. The agreement therefore represents part, rather than all, of the tendered capacity disclosed by GUVNL.
The LoI and BESPA relate to a cumulative 275 MW and 550 MWh award across the two named substations. The filing does not identify the bidders selected for the remaining 175 MW and 350 MWh of the 450 MW and 900 MWh tender, or state whether that balance was awarded through the same process.
The tender and the executed agreement use the same power-to-energy relationship: 450 MW with 900 MWh in the tender and 275 MW with 550 MWh in NIRL’s contract. MW and MWh remain separate measures in the filing, with MW describing power capacity and MWh describing energy capacity.
Got a follow-up? Ask IRIS
What commercial details has NIRL disclosed?
NIRL disclosed the 275 MW and 550 MWh capacity, the Choraniya and Virpore substations, and GUVNL as counterparty, but did not disclose the BESPA tariff, agreement value or project cost. The one-page announcement also contains no revenue, payment, performance-guarantee or agreement-tenure terms.
Without a disclosed tariff, the filing does not permit a calculation of annual revenue from the 275 MW and 550 MWh project. Without a capital-expenditure figure, it also does not provide a basis for calculating the project’s cost per MW or per MWh.
NIRL did not provide a commissioning date, construction timeline or delivery milestone for either the 150 MW Choraniya component or the 125 MW Virpore component. The filing establishes execution of the BESPA on the 18 November 2026 disclosure date, but does not say when the storage assets are to be installed, tested or made available to GUVNL.
The announcement also does not state how the standalone BESS will be charged, dispatched or integrated with generation assets. It does not say whether the 275 MW and 550 MWh capacity will be developed in one phase or separately at the 400 kilovolt and 220 kilovolt substations.
What does the executed BESPA confirm for NIRL?
The executed BESPA confirms a contracted 275 MW and 550 MWh standalone storage project for NIRL after its successful participation in GUVNL’s 450 MW and 900 MWh Phase IX tender. The agreement is split between 150 MW and 300 MWh at Choraniya and 125 MW and 250 MWh at Virpore.
The filing distinguishes the tender process from the contracted outcome: GUVNL first issued an LoI after declaring NIRL successful, and NIRL subsequently executed the BESPA. It does not disclose commercial value, tariff or a completion milestone, so the filing confirms contract execution rather than the financial or construction timetable for the project.
Conclusion
NIRL’s agreement converts its successful tender outcome into a BESPA for 275 MW and 550 MWh of standalone battery storage across two Gujarat substations. The contract covers 150 MW and 300 MWh at Choraniya and 125 MW and 250 MWh at Virpore, compared with GUVNL’s wider 450 MW and 900 MWh Phase IX tender.
What to watch next is whether NIRL or GUVNL discloses the currently unstated tariff, contract value, project cost, construction milestones or commissioning schedule. The 18 November 2026 filing records BESPA execution but does not provide a scheduled completion event or financial target for either substation.