NMDC Starts Tokisud North Production, Plans Rohne in FY27
Key highlights
- NMDC began production at the 2.30 million tonnes per annum Tokisud North thermal coal block in January 2026.
- NMDC plans to open the Rohne coking-coal block in Jharkhand in FY27.
- NMDC reported Q1 FY27 revenue from operations of ₹6,795.25 crore and consolidated net profit of ₹1,976.33 crore.
- Iron ore production rose 26% year on year to 151.17 lakh tonnes in Q1 FY27.
powered by IRIS

NMDC Limited began production at its 2.30 million tonnes per annum Tokisud North thermal coal block in Jharkhand in January 2026 and expects its Rohne coking-coal block to open in FY27, expanding the miner into coal used by power generators and steelmakers.
Know NMDC inside out
Results, valuation, peers and who's buying, in one view.
What has NMDC started at Tokisud North?
NMDC has started production at the Tokisud North thermal coal block, which has an allocated capacity of 2.30 million tonnes per annum. The block is located in Jharkhand and commenced production in January 2026, marking the company's entry into thermal coal operations.
Thermal coal is used mainly by power generators. The start of production gives NMDC an operating coal asset alongside its established iron ore business. The company has not disclosed production volumes, sales volumes, revenue contribution, investment cost, or the customer base for the block in the information available.
The development is significant because it adds a new mineral category to NMDC's operating portfolio. The company is moving beyond iron ore while retaining its core mining operations, although the available material does not quantify the scale of coal's expected contribution to overall financial performance.
When is the Rohne coking-coal block expected to open?
NMDC expects the Rohne coking-coal block in Jharkhand to open in FY27. This would give the company exposure to coking coal, a key input used in the steelmaking process, in addition to the thermal coal produced at Tokisud North.
The two allocated blocks serve different end markets. Tokisud North is a thermal coal asset associated with the power sector, while Rohne is a coking-coal block connected to steel production. The source does not provide a production capacity for Rohne, a precise commissioning date within FY27, or details of its development progress.
The planned opening also has relevance for NMDC's wider business links with the steel industry. NMDC reported iron ore segment revenue of ₹6,802.12 crore in the June 2026 quarter, while it also disclosed segment revenue from HR Coil and Sheets of ₹2,947.31 crore and Pellets & Others of ₹287.75 crore. These segment disclosures show the company's existing connection to steel-related activities, though they do not indicate any revenue from the new coal blocks.
How did NMDC perform financially in the June 2026 quarter?
NMDC reported consolidated revenue from operations of ₹6,795.25 crore and consolidated net profit of ₹1,976.33 crore for Q1 FY27, the quarter ended June 30, 2026. Standalone revenue from operations was also reported at ₹6,795.25 crore, with standalone net profit of ₹2,007.27 crore.
The company's Q1 FY27 operating data showed a rise in iron ore production, while sales growth was more modest. Iron ore production increased 26% year on year to 151.17 lakh tonnes, and iron ore sales rose 2% to 117.30 lakh tonnes. Average domestic realisation increased 4% to ₹5,548 per tonne.
The reported EBITDA margin of 41% was unchanged year on year. Profit before tax was ₹2,692 crore, compared with ₹2,644 crore in Q1 FY26. These figures indicate that NMDC's earnings in the reported quarter continued to be driven by its existing operations rather than the newly started coal business.
Got a follow-up? Ask IRIS
Why do the Jharkhand coal blocks matter for NMDC's business mix?
The Jharkhand blocks matter because they give NMDC access to both thermal coal and coking coal, two products with separate industrial uses. Tokisud North has already entered production, while Rohne is scheduled for FY27, subject to the timeline disclosed by the company.
For investors, the distinction between the two assets is important. Thermal coal demand is linked primarily to power generation, while coking coal is used in producing steel. NMDC's established iron ore operations are also closely tied to the steel cycle, making Rohne relevant to the company's broader presence in steel-related raw materials.
The available disclosures do not state how much output NMDC expects from Rohne or how the company will market the coal. They also do not provide a target for coal revenue, margins, capital expenditure, or the date when either asset may make a measurable contribution to consolidated earnings. Therefore, the immediate financial impact cannot be calculated from the reported information.
What are the market and operational implications of the expansion?
The expansion adds operating exposure to coal without changing the fact that iron ore remains NMDC's main reported revenue source. In Q1 FY27, the iron ore segment recorded revenue of ₹6,802.12 crore, which underlines the scale of the company's core business relative to the newly disclosed coal operations.
The start at Tokisud North gives NMDC a physical foothold in Jharkhand's coal sector. The planned Rohne opening could extend that foothold into coking coal, but execution details remain undisclosed. Investors will need further company updates on commissioning, output, sales arrangements and financial contribution to assess the expansion's operational significance.
NMDC has also said that it remains confident about recovering large outstanding receivables from NMDC Steel Limited and Rashtriya Ispat Nigam Limited, citing government revival plans and operational scale-up. Separately, the company noted that contingent liabilities could arise if the Karnataka Mineral Rights Tax Bill is enacted, while provisions exist to recover applicable amounts from customers. These matters remain relevant alongside the coal expansion when assessing the company's broader financial position.
Conclusion
NMDC's January 2026 start at Tokisud North establishes a 2.30 million tonnes per annum thermal coal operation in Jharkhand, while the planned Rohne opening in FY27 would add coking-coal exposure. The move broadens the company's mineral portfolio, but its reported Q1 FY27 earnings were still anchored in iron ore operations, which generated ₹6,802.12 crore of segment revenue.
The next key development is the scheduled FY27 opening of Rohne. Investors will watch for disclosures on its commissioning date, production capacity, output ramp-up, sales arrangements, capital spending and the contribution of both coal blocks to NMDC's consolidated financial results.