Oswal Pumps secures Rs 235.92 crore repeat MSEDCL order
Key highlights
- Oswal Pumps secured an additional MSEDCL order worth approximately Rs 235.92 crore, including GST.
- The order covers 10,000 off-grid DC solar photovoltaic water pumping systems for farmer sites in Maharashtra.
- The systems include 3 HP, 5 HP and 7.5 HP pump capacities, but the capacity-wise mix was not disclosed.
- Oswal Pumps must provide warranty, repair, maintenance and remote monitoring for five years after installation.
powered by IRIS

Oswal Pumps Limited has secured an additional Maharashtra State Electricity Distribution Company Limited order for 10,000 off-grid DC solar photovoltaic water pumping systems worth approximately Rs 235.92 crore, including goods and services tax (GST). Oswal Pumps must complete installation within 60 days of the Notice to Proceed or work order, while providing warranty, maintenance and remote monitoring for five years.
Know Oswal Pumps inside out
Results, valuation, peers and who's buying, in one view.
What has Oswal Pumps won from MSEDCL?
Oswal Pumps has won a repeat order from Maharashtra State Electricity Distribution Company Limited (MSEDCL) for 10,000 off-grid DC solar photovoltaic water pumping systems. The October 30, 2026 announcement values the additional order at approximately Rs 235.92 crore, including GST, and identifies MSEDCL as a domestic entity.
The award is a further order under the PM Kusum B Scheme, described in the filing as the “Magel Tyala Saur Krishi Pump” Yojana. Oswal Pumps said the repeat award extends its association with MSEDCL in Maharashtra, but the disclosure does not state the quantity or value of any earlier MSEDCL order.
The 10,000 systems will be installed at identified farmers’ sites in districts of Maharashtra. The filing does not name those districts, disclose a per-system price, or split the Rs 235.92 crore consideration between equipment, installation and the five-year service obligations.
What work is included in the MSEDCL solar-pump order?
The Rs 235.92 crore order requires Oswal Pumps to design, manufacture, supply, transport, install, test and commission the 10,000 solar photovoltaic water pumping systems. The scope therefore runs from equipment production to operational commissioning at identified farmer locations in Maharashtra.
The systems comprise 3 horsepower (HP), 5 HP and 7.5 HP pump capacities. While the order spans three capacity categories, MSEDCL and Oswal Pumps did not disclose how many of the 10,000 units fall into each category or whether their prices differ.
The contract also includes complete-system warranty, repair and maintenance, and a Remote Monitoring System (RMS) for five years. The obligation changes after installation: commissioning is due within 60 days of the Notice to Proceed or work order, whereas maintenance and RMS support continue for five years after the systems enter service.
When must Oswal Pumps complete the installations?
Oswal Pumps must complete installation within 60 days from the date MSEDCL issues a Notice to Proceed (NTP) or work order. Although the company disclosed the order on October 30, 2026, it did not disclose the NTP or work-order date, so a calendar completion date cannot be calculated from the announcement.
The 60-day requirement applies to the installation of all 10,000 systems, not to the five-year warranty, repair, maintenance and RMS commitments. The filing does not provide district-level rollout milestones, a monthly installation target, manufacturing allocation or procurement schedule for the 3 HP, 5 HP and 7.5 HP units.
The company also did not disclose payment terms, penalties, advance payments or acceptance conditions for the Rs 235.92 crore order. As a result, the announced consideration establishes the approximate contract size including GST, but does not show the timing of cash collection or the value attached to post-installation services.
Got a follow-up? Ask IRIS
How does the order operate under the PM Kusum B Scheme?
The 10,000-system contract is to be executed under the PM Kusum B Scheme’s “Magel Tyala Saur Krishi Pump” Yojana. Under the disclosed terms, Oswal Pumps will deploy off-grid DC solar photovoltaic water pumping systems at farmer sites identified in Maharashtra.
The product requirement covers three pump sizes, from 3 HP to 7.5 HP, rather than a single standard specification. However, the October 30, 2026 filing does not state solar-module ratings, water-delivery capacity, technical details of the RMS, subsidy terms, or the contribution required from participating farmers.
Vivek Gupta, chairman and managing director of Oswal Pumps, said the additional 10,000-pump award reaffirmed institutional confidence in the company’s capabilities. He said Maharashtra remained a key market and referred to timely execution, product reliability and solar-powered irrigation, without setting a revenue forecast or a separate target for this Rs 235.92 crore order.
Is the MSEDCL order a related-party transaction?
No, Oswal Pumps stated that no promoter, promoter-group or group-company interest exists in MSEDCL in relation to the Rs 235.92 crore order. The company also said the order does not fall within related-party transactions.
The disclosure was made under Regulation 30 of the Securities and Exchange Board of India’s Listing Obligations and Disclosure Requirements Regulations, 2015. It records MSEDCL as the domestic awarding entity and specifies the 60-day installation period alongside the five-year warranty, repair, maintenance and RMS scope.
In the accompanying October 30, 2026 press release, Oswal Pumps said it holds ISO 9001:2015, ISO 45001:2018 and ISO 14001:2015 certifications and is listed under the Ministry of New and Renewable Energy’s Approved List of Models and Manufacturers. Those company statements describe its stated solar-pump operations and do not alter the disclosed 10,000-system contract terms.
Conclusion
The repeat MSEDCL award adds a disclosed Rs 235.92 crore, 10,000-system assignment to Oswal Pumps’ Maharashtra work pipeline. Its scope combines delivery and commissioning of 3 HP, 5 HP and 7.5 HP off-grid solar pumps with five years of warranty, repair, maintenance and remote monitoring, rather than limiting the arrangement to equipment supply.
The next disclosed trigger is issuance of the NTP or work order, which starts the 60-day installation clock for the 10,000 systems. The filing leaves the date of that trigger, the capacity-wise system mix and the value allocated to the five-year RMS and maintenance programme unresolved.