Power Grid Corporation of India Limited merger effective Nov 2
Key highlights
- POWERGRID’s two merger schemes became active on November 2, 2026.
- Two Ministry of Corporate Affairs confirmation orders dated November 2, 2026 cover 28 transferor companies.
- POWERGRID Ghiror Transmission Limited will receive 17 wholly owned subsidiaries.
- The transferor scope increased from 11 subsidiaries in December 2025 to 28 in March 2026.
powered by IRIS

POWERGRID’s merger of 28 wholly owned subsidiaries into two wholly owned transferee companies became effective on November 2, 2026, after two Ministry of Corporate Affairs confirmation orders dated the same day. The 28 transferor companies are being amalgamated into POWERGRID Ghiror Transmission Limited and POWERGRID South Olpad Transmission Limited.
Know Power Grid Corporation of India inside out
Results, valuation, peers and who's buying, in one view.
When did POWERGRID’s 28-subsidiary merger become effective?
POWERGRID’s two merger schemes became active on November 2, 2026. The company disclosed the legal effectiveness on November 3, 2026, after the Regional Director, Northern Region Directorate I, Ministry of Corporate Affairs, confirmed the schemes through two separate orders dated November 2, 2026.
The orders are numbered Sec 233/AC5797011/RD Delhi and Sec 233/AC5816474/RD Delhi. They cover 28 transferor companies, each a wholly owned subsidiary, and two wholly owned transferee companies. POWERGRID said the orders specified that the schemes would be active from the second day of November 2026.
The effective date follows POWERGRID’s board approval on March 19, 2026, which was subject to statutory, regulatory, government or institutional approvals where applicable. The November 3 disclosure records the confirmation of both schemes, but does not state financial consideration, asset values, share-exchange ratios or transaction costs.
Which companies will receive the 28 POWERGRID subsidiaries?
POWERGRID Ghiror Transmission Limited will receive 17 transferor companies, while POWERGRID South Olpad Transmission Limited will receive 11. The 17-company Group-C scheme falls under order Sec 233/AC5797011/RD Delhi, and the 11-company Group-D scheme falls under order Sec 233/AC5816474/RD Delhi.
The Group-C transferors include POWERGRID Kudankulam Transmission Limited, POWERGRID Barmer I Transmission Limited, POWERGRID Bikaner IV Transmission Limited, POWERGRID Siwani Transmission Limited and POWERGRID Fatehgarh Barmer Augmentation Transmission Limited. The remaining 12 are POWERGRID Ramgarh Transmission Limited, POWERGRID Bhadla Transmission Limited, POWERGRID Fatehgarh Transmission Limited, POWERGRID Bikaner Transmission System Limited, POWERGRID Narela Transmission Limited, POWERGRID Khetri Transmission System Limited, POWERGRID Ajmer Phagi Transmission Limited, POWERGRID Varanasi Transmission System Limited, POWERGRID Neemuch Transmission Limited, POWERGRID Mithilanchal Transmission Limited, POWERGRID Medinipur Jeerat Transmission Limited and POWERGRID Mahan Rewa Transmission Limited.
The Group-D transferors are POWERGRID Sirohi Transmission Limited, POWERGRID Mandsaur Transmission Limited, POWERGRID Mewar Transmission Limited, POWERGRID Beawar-Mandsaur Transmission Limited, POWERGRID Kurawar Transmission Limited and POWERGRID Sirohi Khandwa Transmission Limited. Its other five companies are POWERGRID ER NER Transmission Limited, POWERGRID Chitradurga Bellary Transmission Limited, POWERGRID Kurnool-III CPETA Transmission Limited, POWERGRID Jam Khambhaliya Transmission Limited and POWERGRID Banaskantha Augmentation Transmission Limited.
Got a follow-up? Ask IRIS
How did POWERGRID’s merger plan change from December 2025?
POWERGRID expanded the transferor scope to 28 subsidiaries from 11 subsidiaries in the December 2025 proposal, an increase of 17 companies. Its board approved the expanded plan on March 19, 2026, explicitly stating that it superseded the earlier proposal approved on December 20, 2025.
The December 20, 2025 filing referred to 13 wholly owned subsidiaries in total: 11 transferors proposed to merge into two other wholly owned subsidiaries. In contrast, the March 19, 2026 approval identified 28 transferor subsidiaries merging into two transferees, meaning 30 entities were involved in the enlarged structure.
The number of receiving subsidiaries remained at two across both plans, but the confirmed November 2 schemes allocated 17 transferors to POWERGRID Ghiror Transmission Limited and 11 to POWERGRID South Olpad Transmission Limited. The earlier December filing did not identify the transferor companies or name the transferee companies in the material provided.
Why did POWERGRID consolidate these wholly owned subsidiaries?
POWERGRID said on December 20, 2025 that the proposed schemes were intended to consolidate business for creating larger unified entities and reduce the number of entities within the group. It also cited operational and management efficiencies, simplified administrative tasks and a simplified organisational structure.
Those objectives were disclosed with the initial plan involving 11 transferors and two transferees. The November 3, 2026 filing confirms the legal effectiveness of the expanded 28-transferor arrangement, but does not provide a revised estimate of cost savings, staffing changes, project-transfer values or operating benefits for either transferee.
The disclosure confines the action to wholly owned subsidiaries, rather than describing an acquisition of outside companies or a merger with an unrelated counterparty. The mechanism is merger or amalgamation under two Ministry of Corporate Affairs orders, both dated November 2, 2026, with the schemes active from that date.
Conclusion
POWERGRID has moved from a December 2025 plan covering 11 transferors to legally effective November 2, 2026 schemes covering 28 transferors. The group simplification places 17 named project subsidiaries into POWERGRID Ghiror Transmission Limited and 11 into POWERGRID South Olpad Transmission Limited, while retaining two wholly owned receiving entities.
The next matter to watch is whether POWERGRID later quantifies the operational, management or administrative effects cited in its December 20, 2025 plan. The November 3, 2026 filing provides no savings target, financial impact, integration timetable or further scheduled approval after the two schemes became active on November 2, 2026.