Ratnaveer Targets 85% First-Line CCL Utilisation by April
Max Plan at ₹4,999/yr₹8,999
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- Ratnaveer targets 85% utilisation of its first CCL line by April 2027.
- Ratnaveer plans its second, third, fourth and fifth CCL lines for June 2027, September 2027, January 2028 and April 2028.
- The first CCL project was about 75% complete as of the November 3, 2026 earnings call.
- Ratnaveer reported revenue from operations of Rs 387 crore, up 35.46% year on year, in its Q2 FY27 financial update.
powered by IRIS

Ratnaveer Precision Engineering Limited targets 85% utilisation of its first copper clad laminate (CCL) line by April 2027, following a planned December 2026-January 2027 trial period, while management plans to install all five lines by April 2028. The first CCL project was about 75% complete when management spoke on November 3, 2026.
Know Ratnaveer Precision Engineering inside out
Results, valuation, peers and who's buying, in one view.
When will Ratnaveer commission its first CCL line?
Ratnaveer plans to begin trial production on its first CCL line around December 15-20, 2026, with about one month set aside for trial runs and product development. Management said civil work was nearly complete, machinery was expected in India between November 15 and November 20, and commissioning and erection were expected to take 45 to 50 days.
The timetable reflected a project that Ratnaveer said was about 75% complete during its Q2 and H1 FY27 earnings call. Management said construction, machinery delivery and approvals were on schedule on November 3, 2026, although synchronising the machines, preparing prepreg formulations and setting glass-fabric speeds could cause initial teething issues of two to three weeks.
Ratnaveer has arranged technical support for the launch through 22 engineers scheduled to arrive for installation. Management said one additional Chinese technical specialist would remain for two years to support plant setup, production and quality, while a Chinese chief technical officer with 30 years of experience had been appointed to oversee installation, product development and systems.
How will Ratnaveer reach 85% CCL utilisation by April 2027?
Ratnaveer targets 30% utilisation in February 2027, 60% in March 2027 and 85% in April 2027 for the first CCL line. These are management operating targets rather than reported production because the line had not begun commercial output at the time of the November 2026 call.
The ramp depends on completing the trial and product-development stage after installation. Ratnaveer said its first task is to establish quality equivalent to imported material before expanding capacity. The proposed line can produce products from 140 to 180 Tg, or glass transition temperature, including FR4 material, prepreg, single-sided and double-sided products, and multi-layer applications.
The line is intended to serve printed circuit board customers in automotive, electric vehicles, drones, satellite equipment, aerospace and electronics. Management specified copper thicknesses of 15, 17, 18 and 35 microns, alongside product thicknesses between 0.8 millimetre and 3.2 millimetre, and said critical-component applications currently use up to 180 Tg.
When will Ratnaveer install all five CCL lines?
Ratnaveer plans to install its second CCL line in June 2027, the third in September 2027, the fourth in January 2028 and the fifth in April 2028. Management said it intended to place orders for the second and third lines during December 2026-January 2027, followed by orders for the remaining two lines.
This rollout differs from the first-line timetable because Ratnaveer intends to use the first facility to establish product quality, delivery and service. Management said it would demonstrate products across grades up to 180 Tg before expanding the remaining four lines over the following 18 months. It did not provide utilisation targets for lines two through five.
Ratnaveer disclosed planned CCL investment of Rs 338 crore over two to three years under the Electronics Components Manufacturing Scheme, or ECMS. The wider plan also includes Rs 86 crore for a captive solar plant. Management said the five lines are mostly covered by term loans, with bank funding available if required.
Got a follow-up? Ask IRIS
What customer demand has Ratnaveer disclosed for CCL?
Ratnaveer said it had received some domestic orders, long-term contracts and soft confirmations before commercial production, but did not disclose customer names, volumes or contract values. Management said it had made 57 visits to key printed circuit board customers and expected to announce order bookings and long-term contracts within two or three weeks of the November 3 call.
The initial customer focus is India, where management said CCL supply was short and printed circuit board manufacturers were seeking material. Ratnaveer also reported enquiries from Japan, the United States and Europe. Management cited local delivery, lower logistics costs, reduced foreign-exchange exposure and shorter waiting times as advantages over imported material.
Management said initial pricing could be at parity with Chinese supply or 0.5% to 1% below it. It also said CCL prices had risen by more than 300% over the preceding year, while raw-material prices had risen by an estimated 40% to 50%. These were management market assessments, and Ratnaveer said it would provide revised financial guidance after gaining further clarity on pricing and contracts.
What could the CCL expansion mean for Ratnaveer's financial targets?
Ratnaveer's existing stated target is Rs 150 crore of revenue from each CCL line, or Rs 750 crore from five lines, with management previously guiding for 20% earnings before interest, tax, depreciation and amortisation (EBITDA) margin and 13% profit after tax (PAT) margin. Management said changing CCL prices could lead it to revise those targets, but had not announced replacement numbers.
The CCL plan sits beside Ratnaveer's fasteners, tubes and pipes, washers, clips and sheet-metal components businesses. Management said revenue was Rs 1,080 crore in the prior year, targeted Rs 1,315 crore in FY27 and was expected to reach Rs 1,800 crore by FY28. A separate Phase 2 capital expenditure programme of about Rs 58 crore for fasteners, tubes, pipes, sheet-metal components and clips is under way.
Management reported revenue from operations of Rs 387 crore, up 35.46% year on year, EBITDA of Rs 42.13 crore, up 38.85%, and PAT of Rs 24.07 crore, up 55.97%, in its Q2 FY27 financial update. It said FY27 PAT margin was expected to be around 6.25% and attributed the gross-margin decline from 10.33% in Q1 to 9.44% in Q2 to expenses for new products being booked before related sales arrived.
Conclusion
Ratnaveer's CCL expansion is defined by a near-term sequence of machinery arrival in November 2026, trials from December 2026 into January 2027, and a targeted 85% utilisation level for the first line in April 2027. The company has paired that schedule with engineering support, domestic customer outreach and a five-line installation plan extending to April 2028.
The next items to watch are the first-line trial outcome, customer-contract disclosures and any revised CCL revenue or margin guidance. Management said it expected order announcements within weeks of the November 3, 2026 call and planned to order the second and third lines in December 2026-January 2027, milestones that will test the April 2028 five-line timetable.