Ratnaveer Details ₹338 Crore Phased CCL Project Rollout
Max Plan at ₹4,999/yr₹8,999
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- Ratnaveer Precision Engineering plans five CCL lines with combined annual capacity of 79.2 lakh sheets.
- The CCL project carries a planned investment of ₹338 crore.
- Supply agreements and confirmed orders cover nearly 50% of planned CCL capacity.
- Ratnaveer projects FY29 CCL revenue of ₹2,004.75 crore, with commercial production expected from February 2027.
powered by IRIS

Ratnaveer Precision Engineering Limited detailed its ₹338 crore Copper Clad Laminate project update on November 26, 2026, outlining five production lines with combined annual capacity of 79.2 lakh sheets. The company expects phased commissioning from February 2027 and has projected ₹2,004.75 crore of CCL revenue in FY29.
Know Ratnaveer Precision Engineering inside out
Results, valuation, peers and who's buying, in one view.
What did Ratnaveer Precision Engineering disclose in its CCL project update?
Ratnaveer Precision Engineering said its upcoming Copper Clad Laminate, or CCL, facility is progressing under the planned execution schedule. The project is designed to operate five production lines with aggregate annual capacity of 79.2 lakh sheets, marking the company's planned entry into the CCL segment.
The company said it has secured long-term supply agreements and order confirmations for nearly 50% of the planned capacity. It also said discussions for the remaining capacity are at an advanced stage, supported by customer meetings, enquiries and orders from participants in India's printed circuit board, or PCB, industry.
Machinery for the project is expected to arrive shortly, after which installation and associated preparatory work will be undertaken. The filing does not provide a revised project cost, capacity figure or commercial-production date beyond the disclosed plan.
When is Ratnaveer expected to begin CCL production?
Ratnaveer expects SKU-level trial runs during December 2026 and January 2027, followed by commercial production from February 2027. The commissioning is planned in phases rather than as a simultaneous start-up of all five lines.
The company has stated that the machinery arrival will be followed by installation and preparation for trials. The sequencing matters because trial runs are intended to validate individual product specifications before commercial output begins.
Earlier project updates indicated that the first line would be commissioned before the other lines, which are intended to be brought on stream progressively. The November 26 filing continues to place the first commercial-production stage in February 2027, while the full five-line capacity remains a phased build-out.
Got a follow-up? Ask IRIS
What are the financial targets for Ratnaveer's CCL business?
Ratnaveer has planned an investment of ₹338 crore for the CCL project and projected CCL revenue of ₹2,004.75 crore in FY29. This revenue figure is a company projection linked to the planned ramp-up of the new facility, not reported revenue from operations.
The CCL unit was not yet in commercial production at the time of the update. As a result, the agreements covering nearly half of planned capacity indicate customer commitments before the production start, but they do not represent recognised CCL revenue.
The CCL expansion is separate from Ratnaveer's existing stainless-steel-focused operations. The company had previously reported 35.5% year-on-year revenue growth and 56.1% year-on-year growth in profit after tax for the second quarter of FY27 in its existing business, according to information available in the project context.
Why does the CCL update matter for investors and the PCB industry?
Ratnaveer's update matters because it provides specific execution markers for a new business segment, including trials, commercial production, capacity and planned investment. Supply agreements and order confirmations for nearly half of capacity provide an early indication of customer interest, though the project remains pre-commercial.
Copper clad laminates are a core input for PCB manufacturing. Ratnaveer's planned facility is aimed at serving PCB industry customers, and the company's discussions for the uncommitted portion of capacity show that the order book is still being developed alongside project execution.
For investors, the main points to monitor are machinery installation, completion of trial runs, the start of commercial production and the pace of phased commissioning. The filing does not disclose a share-price reaction, production volumes, capacity utilisation or CCL profitability, so these cannot be assessed from the update.
For customers and industry participants, commercial output from the facility is scheduled to begin only after trials are completed. The company has not disclosed the names of customers, the duration of supply agreements, pricing terms or order values.
Conclusion
Ratnaveer Precision Engineering's November 26 update sets out a defined route to commercialisation for its ₹338 crore CCL project. The facility is planned to have five lines and annual capacity of 79.2 lakh sheets, while long-term supply agreements and orders cover nearly half of that capacity before operations begin.
The next disclosed milestones are SKU-level trials in December 2026 and January 2027 and the expected start of commercial production in February 2027. Investors will also watch whether the phased commissioning remains on schedule and how the company progresses discussions for the remaining planned capacity against its FY29 CCL revenue projection of ₹2,004.75 crore.