SJVN Limited retains Rs 4,215.28 crore in disputed projects
Key highlights
- SJVN continues to recognise Rs 4,215.28 crore invested in three disputed Himachal Pradesh projects as at September 30, 2026.
- The three projects have planned capacity of 658 MW, comprising Luhri Stage-1, Sunni Dam and Dhaulasidh.
- Capital work-in-progress represents Rs 3,350.66 crore of the recognised expenditure, while Rs 864.62 crore is held in property, plant and equipment or intangible assets.
- SJVN's standalone total assets rose to Rs 28,567.82 crore at September 30, 2026, from Rs 27,596.43 crore at March 31, 2026.
powered by IRIS

SJVN Limited continues to recognise Rs 4,215.28 crore invested in three Himachal Pradesh hydropower projects as at September 30, 2026. The balance includes Rs 864.62 crore in property, plant and equipment or intangible assets and Rs 3,350.66 crore in capital work-in-progress, while implementation agreements remain unsigned and the state has indicated a possible take-back.
Know SJVN inside out
Results, valuation, peers and who's buying, in one view.
How much has SJVN invested in the three projects?
SJVN has recognised combined expenditure of Rs 4,215.28 crore on the 210 megawatt (MW) Luhri Hydro Electric Project Stage-1, 382 MW Sunni Dam Hydro Electric Project and 66 MW Dhaulasidh Hydro Electric Project as at September 30, 2026. The projects have aggregate planned capacity of 658 MW, and the expenditure remains in SJVN's standalone statement of assets and liabilities pending final decisions.
Capital work-in-progress (CWIP) accounts for Rs 3,350.66 crore of the recognised amount, while Rs 864.62 crore is carried under property, plant and equipment or intangible assets. SJVN did not disclose a project-by-project split of these balances among Luhri Stage-1, Sunni Dam and Dhaulasidh.
Why are the implementation agreements still unsigned?
The implementation agreements remain unsigned because the Government of Himachal Pradesh seeks to renegotiate previously agreed terms, conditions and relaxations before signing them, according to SJVN's disclosure. The three projects were allotted to SJVN through a memorandum of understanding (MoU), under which detailed implementation-agreement terms were to be formulated with mutual consent.
The state sent what SJVN described as a mutually agreed implementation agreement for signing on August 6, 2022, but no agreement has been executed for the 210 MW, 382 MW or 66 MW project. SJVN said it commenced work while signing was pending to avoid time and cost overruns, which led to the state notice concerning work undertaken without implementation agreements.
What action has Himachal Pradesh taken against SJVN?
Himachal Pradesh has issued a notice concerning the commencement of work without signed implementation agreements and has sought revised terms before execution. SJVN said it replied to the notice and filed a petition in the High Court of Himachal Pradesh over the three projects, which carry recognised expenditure of Rs 4,215.28 crore.
The High Court directed the state not to take coercive action against SJVN regarding the dispute. The case remained pending when SJVN's board approved its unaudited standalone results on October 30, 2026, and the direction does not settle the agreement negotiations or determine the eventual status of the 658 MW portfolio.
Could Himachal Pradesh take back the three projects?
Himachal Pradesh indicated in a letter dated April 22, 2025 that it intended to consider taking back the three projects and appointing an evaluator. SJVN's disclosure records an intention to consider that action rather than a completed transfer, and the company continues to recognise the Rs 4,215.28 crore expenditure while final decisions remain pending.
SJVN did not disclose a valuation by the proposed evaluator, a compensation mechanism or a deadline for a state decision. The company said it was actively engaged in resolving the matter, while the assets remain recognised across CWIP and property, plant and equipment or intangible-asset categories.
Got a follow-up? Ask IRIS
How does the dispute affect SJVN's September balance sheet?
The disputed-project expenditure remains within SJVN's asset base rather than being classified as held for sale as at September 30, 2026. Standalone CWIP was Rs 3,952.02 crore at September 30, compared with Rs 3,522.69 crore at March 31, 2026, an increase of Rs 429.33 crore over the six-month period.
SJVN's standalone total assets increased to Rs 28,567.82 crore at September 30, 2026 from Rs 27,596.43 crore at March 31, 2026. The Rs 4,215.28 crore recognised for the three Himachal projects comprises Rs 3,350.66 crore of CWIP and Rs 864.62 crore of property, plant and equipment or intangible assets within that wider asset base.
What other project accounting changes did SJVN disclose?
SJVN separately classified Rs 738.52 crore of assets relating to the 3,097 MW Etalin Hydro Electric Project as held for sale after the Ministry of Power reassigned the project to NHPC Limited. Associated liabilities of Rs 0.11 crore were also classified separately after termination of the memorandum of agreement with the Government of Arunachal Pradesh.
That treatment differs from the three Himachal projects because SJVN continues to recognise their Rs 4,215.28 crore expenditure pending final decisions. In Uttarakhand, survey and investigation work on the Devasari Hydro Electric Project remained on hold under Ministry of Power directions issued on July 6, 2021, with expenditure of Rs 251.50 crore at September 30, 2026, including CWIP of Rs 200.73 crore.
Devasari expenditure was Rs 251.38 crore at March 31, 2026, including Rs 200.34 crore of CWIP, compared with Rs 251.50 crore and Rs 200.73 crore respectively at September 30. Management said it expected the hold on Devasari activities to be withdrawn, while SJVN's Himachal disclosure identifies a pending court case and implementation-agreement negotiations.
Conclusion
SJVN's September 2026 accounts show that the Himachal Pradesh dispute has not resulted in derecognition or held-for-sale classification for the three projects. The company continues to carry Rs 4,215.28 crore for the 658 MW portfolio, including Rs 3,350.66 crore of CWIP, despite unsigned implementation agreements and the state's consideration of a potential take-back.
The next developments to watch are the pending High Court case, negotiations on the revised implementation-agreement terms and any action on the state's April 22, 2025 indication that it may consider taking back the projects and appointing an evaluator. SJVN has not disclosed a valuation, settlement framework or decision date for the expenditure recognised at September 30, 2026.