SPML Infra reports Rs 186.41 crore POWERGRID order, LOA awaited
Key highlights
- SPML Infra reported an approximately Rs 186.41 crore domestic EPC order from POWERGRID on November 4, 2026.
- The order covers extensions at the 765/400/220 kV Bhadla-III Substation and Ramgarh Pooling Station.
- The approximately Rs 186.41 crore consideration excludes GST and carries a 27-month execution period from the LOA.
- SPML Infra received email intimation, but the formal Letter of Award remains awaited.
powered by IRIS

SPML Infra Limited reported a domestic Rs 186.41 crore engineering, procurement and construction order from Power Grid Corporation of India Limited for extensions at Bhadla-III Substation and Ramgarh Pooling Station, but said the formal Letter of Award remained awaited as of its November 4, 2026 disclosure. The stated execution period is 27 months from the Letter of Award.
Know SPML Infra inside out
Results, valuation, peers and who's buying, in one view.
What order did SPML Infra receive from POWERGRID?
SPML Infra reported an approximately Rs 186.41 crore domestic EPC, or engineering, procurement and construction, order from Power Grid Corporation of India Limited, referred to in the filing as POWERGRID. The announced consideration excludes goods and services tax, or GST. SPML Infra described the contract as an extension of two extra-high-voltage substations rather than a new standalone substation project.
SPML Infra made the disclosure under Regulation 30 of the SEBI Listing Obligations and Disclosure Requirements Regulations, 2015, on November 4, 2026. The filing identifies POWERGRID as a Maharatna central public-sector enterprise and names it as the awarding entity. The annexure classifies the order as domestic.
The Rs 186.41 crore figure appears in SPML Infra's covering exchange letter, while the annexure describes the consideration as approximate and excluding GST. The filing does not provide a split of the consideration between Ramgarh and Bhadla, or identify the value of any individual engineering, procurement or construction component.
What work is covered by the SPML Infra contract?
SPML Infra said the contract covers extension of the 765/400/220 kilovolt, or kV, Bhadla-III Substation and Ramgarh Pooling Station. The disclosure identifies 765 kV, 400 kV and 220 kV voltage levels. It states that the two extensions form part of transmission-system augmentation at Bhadla-III, Ramgarh PS and Kanpur.
The November 4, 2026 filing classifies the work as EPC but does not separately quantify its engineering, equipment procurement or construction portions within the approximately Rs 186.41 crore consideration. It also does not disclose the number of bays, transformers, transmission lines or other assets covered by the substation extensions.
The disclosed scope spans two locations, Bhadla-III and Ramgarh Pooling Station, while the wider augmentation system also names Kanpur. SPML Infra's stated work is limited to the two substation extensions, and the filing does not allocate any portion of the approximately Rs 186.41 crore consideration to Kanpur.
Got a follow-up? Ask IRIS
When will SPML Infra execute the POWERGRID order?
SPML Infra said the order is to be executed within 27 months from the date of the formal Letter of Award, or LOA, subject to that document's terms. The 27-month period does not run from the November 4, 2026 exchange disclosure because the LOA was still awaited. The filing gives no calendar completion date.
SPML Infra said it received intimation of the order by email, while the formal LOA had not been issued at the time of disclosure. The email intimation established the reported approximately Rs 186.41 crore order, but the LOA will set the applicable contractual terms and start the stated execution period.
The filing does not disclose a mobilisation date, site-work start date, billing schedule or intermediate project milestones for the 27-month period. It also does not provide payment terms, performance guarantees, liquidated-damages provisions or a revenue-recognition schedule for the EPC contract.
What remains unresolved before the SPML Infra contract is formalised?
The principal disclosed pending step is POWERGRID's formal LOA, despite SPML Infra having received email intimation of the approximately Rs 186.41 crore order. The filing does not say when POWERGRID will issue the document. It consequently does not state the award date from which the 27-month execution schedule will begin.
SPML Infra also did not disclose a detailed scope schedule, project milestones, margin estimate or annual execution profile for the domestic EPC work. The November 4, 2026 announcement provides the broad scope, contract type, approximate consideration excluding GST and 27-month term, but not financial-year-wise execution details.
On governance disclosures, SPML Infra said its promoters, promoter group and group companies have no interest in POWERGRID. It also stated that the order is not a related-party transaction. Those disclosures concern the relationship with the awarding entity, while the LOA remains the outstanding procedural item.
Conclusion
SPML Infra's November 4, 2026 filing reports an approximately Rs 186.41 crore domestic EPC order, excluding GST, for extensions at Bhadla-III Substation and Ramgarh Pooling Station. The work is linked to transmission-system augmentation at Bhadla-III, Ramgarh PS and Kanpur, and SPML Infra disclosed no promoter-group interest or related-party transaction involving POWERGRID.
The next disclosed event to watch is the formal LOA from POWERGRID because it will start the stated 27-month execution period and set the governing contract terms. SPML Infra has not disclosed the LOA date, component-wise scope allocation, milestones or annual execution profile.