V.L.Infraprojects Limited profit falls 21% despite revenue growth
Key highlights
- V.L.Infraprojects reported September-half revenue from operations of Rs 71.70 crore, up 14% year on year.
- V.L.Infraprojects’ profit for the period fell 21% year on year to Rs 3.18 crore.
- Subcontract expenses rose 63% year on year to Rs 31.11 crore.
- Net cash used in operating activities was Rs 8.03 crore for the September 2026 half.
powered by IRIS

V.L.Infraprojects Limited reported profit for the period of Rs 3.18 crore for the six months ended September 30, 2026, down 21% from Rs 4.02 crore a year earlier, despite revenue from operations rising 14% to Rs 71.70 crore. Subcontract expenses increased 63% to Rs 31.11 crore, while total expenses grew faster than revenue.
Know V.L.Infraprojects inside out
Results, valuation, peers and who's buying, in one view.
Why did V.L.Infraprojects’ profit decline despite higher revenue?
V.L.Infraprojects’ profit declined as total expenses increased 17% year on year to Rs 67.55 crore in the six months ended September 30, 2026, compared with a 14% rise in revenue from operations to Rs 71.70 crore. Profit before tax fell to Rs 4.24 crore from Rs 5.30 crore, and profit for the period decreased from Rs 4.02 crore to Rs 3.18 crore.
The largest movement among costs was in subcontract expenses, which rose to Rs 31.11 crore from Rs 19.10 crore in the corresponding six months ended September 30, 2025. That Rs 12.01 crore increase exceeded the Rs 8.86 crore increase in revenue. Cost of materials consumed declined to Rs 27.47 crore from Rs 31.29 crore, partly offsetting the higher subcontract expense.
The reported figures imply a net profit margin of about 4.4% for the September 2026 half, calculated as Rs 3.18 crore of profit for the period divided by Rs 71.70 crore of revenue from operations. The comparable calculation was about 6.4% in the September 2025 half, based on Rs 4.02 crore of profit and Rs 62.83 crore of revenue. These margins are calculations from the reported figures, not margins disclosed by V.L.Infraprojects.
How did V.L.Infraprojects’ September 2026 half compare with March 2026?
V.L.Infraprojects’ September 2026 half was below the immediately preceding six months ended March 31, 2026, when revenue from operations was Rs 86.90 crore and profit for the period was Rs 4.40 crore. Revenue was 18% lower than the March-half figure, while profit for the period was 28% lower.
Subcontract expenses were Rs 31.11 crore in the September half, compared with Rs 45.91 crore in the March half, while material costs rose to Rs 27.47 crore from Rs 25.12 crore. Total expenses decreased to Rs 67.55 crore from Rs 80.92 crore, but total income also declined to Rs 71.79 crore from Rs 87.12 crore. Profit before tax fell to Rs 4.24 crore from Rs 6.20 crore.
Basic and diluted earnings per equity share were Rs 2.02 for the September 2026 half, against Rs 2.80 in the March 2026 half and Rs 2.56 in the September 2025 half. Paid-up equity share capital was unchanged at Rs 15.71 crore across the three reported periods, with a face value of Rs 10 per share. The lower per-share earnings therefore coincided with the lower reported profit for the period.
Which expenses changed most at V.L.Infraprojects?
V.L.Infraprojects’ subcontract expenses recorded the sharpest year-on-year increase, rising by Rs 12.01 crore to Rs 31.11 crore in the September 2026 half. Based on the reported revenue figures, subcontracting represented about 43% of revenue from operations, versus about 30% in the corresponding September 2025 half.
Other expenses increased to Rs 5.18 crore from Rs 3.55 crore, employee benefits expenses rose to Rs 1.30 crore from Rs 1.28 crore, and depreciation and amortisation increased to Rs 39.12 lakh from Rs 37.15 lakh. Finance costs also rose to Rs 2.09 crore from Rs 2.01 crore. These cost movements accompanied the decline in profit before tax to Rs 4.24 crore from Rs 5.30 crore.
The cost pattern also differed between the two latest full financial years. For the year ended March 31, 2026, subcontract expenses were Rs 65.01 crore and material costs were Rs 56.41 crore on revenue from operations of Rs 149.74 crore. For the year ended March 31, 2025, subcontract expenses were Rs 36.60 crore while material costs were Rs 62.87 crore on revenue of Rs 121.04 crore.
Got a follow-up? Ask IRIS
What do V.L.Infraprojects’ balance sheet and cash flows show?
V.L.Infraprojects reported total assets of Rs 117.65 crore at September 30, 2026, compared with Rs 106.00 crore at March 31, 2026. Current assets rose to Rs 97.77 crore from Rs 89.46 crore, including trade receivables of Rs 27.14 crore against Rs 23.12 crore and other current assets of Rs 54.78 crore against Rs 51.09 crore.
Total equity and liabilities were also Rs 117.65 crore at September 30, 2026. Short-term borrowings increased to Rs 34.02 crore from Rs 26.51 crore, while long-term borrowings rose to Rs 4.03 crore from Rs 1.66 crore. Shareholders’ funds increased to Rs 53.51 crore from Rs 50.33 crore, with reserves and surplus of Rs 37.79 crore compared with Rs 34.61 crore at March 31, 2026.
Net cash used in operating activities was Rs 8.03 crore for the half year ended September 30, 2026, compared with Rs 4.10 crore used in the year ended March 31, 2026. The half-year cash-flow statement records increases in trade receivables of Rs 4.02 crore, loans and advances of Rs 3.68 crore, inventories of Rs 65.80 lakh and other assets of Rs 3.63 crore. Net cash from financing activities was Rs 7.99 crore, including Rs 9.88 crore in proceeds from borrowings.
Cash and cash equivalents were Rs 22.67 lakh at September 30, 2026, down from Rs 1.22 crore at March 31, 2026. The closing balance comprised Rs 2.47 lakh of cash on hand and Rs 20.19 lakh held with scheduled banks. The September 30 balance sheet also reported other bank balances of negative Rs 1.38 crore.
What did the limited review cover?
V.L.Infraprojects’ unaudited standalone results for the six months ended September 30, 2026 were reviewed by statutory auditor PARY & Co. The board approved the results on November 14, 2026 after they were reviewed and recommended by the audit committee.
The auditor stated that nothing had come to its attention to indicate that the financial-results statement did not disclose the information required under Regulation 33 of the Securities and Exchange Board of India listing regulations, or that it contained a material misstatement. The auditor also stated that a review is substantially less extensive than an audit and does not provide an audit opinion.
V.L.Infraprojects said its activities fall within a single primary business segment and that it has no separate reportable geographical segment under Accounting Standard 17. The filing also states that Indian Accounting Standards, or Ind AS, are not currently applicable to V.L.Infraprojects, which is listed on the National Stock Exchange of India’s SME Emerge platform.
Conclusion
V.L.Infraprojects delivered 14% year-on-year growth in September-half revenue, but the increase in subcontract expenses and other costs resulted in a 21% fall in profit for the period. The comparison with both the September 2025 and March 2026 half-year periods shows lower profit before tax, lower earnings per share and a reduced calculated profit margin.
The November 14, 2026 filing does not disclose revenue or profit guidance, an order target or management’s explanation for the increase in subcontract expenses. The unresolved matters are whether subcontracting costs, trade receivables of Rs 27.14 crore and operating cash use of Rs 8.03 crore change in subsequent reported results.