Adisoft plans Rs 700 crore Bhosari capacity in four years
MAX Plan at ₹4,999/yr
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- Adisoft plans partial manufacturing at Bhosari in January and February, followed by a full move by March-end or the first week of April.
- The 70,000-square-foot Bhosari project has an approximate Rs 33 crore budget funded by initial public offering proceeds.
- Adisoft had spent approximately Rs 10 crore to Rs 12 crore on the Bhosari facility at the time of the call.
- Management plans about Rs 700 crore of peak revenue capacity at Bhosari in around three to four years.
powered by IRIS

Adisoft plans peak revenue capacity of about Rs 700 crore from its 70,000-square-foot Bhosari facility in roughly four years, with partial manufacturing use expected in January and February and a full shift planned by March-end or the first week of April. The project has an approximate Rs 33 crore capital expenditure budget funded through initial public offering proceeds.
Know Adisoft Technologies inside out
Results, valuation, peers and who's buying, in one view.
When will Adisoft’s Bhosari facility become operational?
Adisoft expects to begin manufacturing from part of the Bhosari facility in January and February, followed by a complete shift by March-end or the first week of April. Management said the overall development comprises a basement plus four floors and was planned for completion by Q3. It expects whichever portion of the two manufacturing floors becomes available first to support production during the final three months of the financial year.
The January-to-March period is important because management said it is significant for overall billing. Adisoft expects added working and storage area to help it make faster billings, rather than waiting for the entire 70,000-square-foot building to be ready. The planned site includes two floors for manufacturing and ready-material storage, while two floors are intended for seating employees.
Adisoft’s current Pune setup has about 4,000 square feet of office space and 12,000 square feet of working space. Management said the company has nevertheless generated revenue at several levels from the existing premises, including Rs 75 crore, Rs 100 crore, Rs 130 crore and Rs 165 crore, and recorded Rs 72 crore in the first half discussed on the call. The Bhosari site is intended to remove the current working-area and storage constraint.
How is Adisoft funding the Rs 33 crore Bhosari project?
Adisoft is funding the approximately Rs 33 crore Bhosari capital expenditure through initial public offering proceeds, management said. It had spent approximately Rs 10 crore to Rs 12 crore at the time of the call. Management also said all long-term debt had been closed using IPO proceeds, leaving the company with short-term working-capital finance.
Adisoft said it did not plan to take long-term loans for the project. That position separates the funding of the facility from its remaining short-term working-capital finance, although management did not quantify that finance on the call. The stated spending range of Rs 10 crore to Rs 12 crore indicates that part of the Rs 33 crore budget remained to be deployed when management provided the update.
The building plan is tied to a workforce expansion. Adisoft said its 250-person maximum seating capacity was designed to accommodate manpower growth for at least the next four to five years, compared with roughly 100 to 110 people then based in Pune. Management’s rationale was that the company sees business opportunities but has been limited by available space and manpower.
Got a follow-up? Ask IRIS
What revenue capacity does Adisoft expect at Bhosari?
Adisoft is planning for about Rs 700 crore of peak revenue capacity at Bhosari, which management said may take around three to four years to reach. This is management’s capacity plan, not reported revenue or a formal near-term revenue forecast. Management said execution within the available time would remain the principal limitation after the new facility addresses space and manpower constraints.
The proposed Rs 700 crore capacity is more than three times the approximately Rs 215 crore revenue plan management discussed for the current year. Adisoft had delivered Rs 72 crore in the first half from its current premises, while management described Rs 165 crore as the prior-year revenue level. The comparison shows that management expects the new site to support a considerably larger operating scale than the existing Pune arrangement.
Adisoft’s revenue model combines design, assembly and software integration. Management said it designs complete mechanical and electrical systems, has vendors manufacture electrical panels and mechanical components to its specifications, and integrates the equipment in-house. The company then adds software applications, proves the machine to customer requirements and dispatches it, normally within three to four months of receiving an order.
How could the new site affect Adisoft’s execution and billing?
Adisoft expects the Bhosari site to improve execution and billing by providing more space for manufacturing and storage in January, February and March. Management said that even partial use of the two production floors would be helpful during this period. The planned full move by March-end or early April would make the whole facility available for use in the next financial year.
The company’s active work base provides context for the additional capacity. Management cited a Rs 50 crore order book and a further pipeline of around Rs 40 crore that was under negotiation or quotation. It said the normal order-visibility period is three to four months, and described its conversion rate as around 95% to 98%, expecting more than Rs 35 crore to Rs 36 crore from the Rs 40 crore pipeline.
Automotive was the major sector in the order book and pipeline, although Adisoft had not prepared a formal sector split at that point. Management also cited pharma, white goods and e-commerce as segments it was pursuing. In automotive, it said new plants, expanded shops and upgrades needed for new vehicle models can coexist as order sources, but it did not quantify the split between those categories.
Conclusion
The Bhosari project combines an approximately Rs 33 crore IPO-funded investment with a larger manufacturing, storage and workforce footprint. Adisoft expects the 70,000-square-foot facility to address the constraints of its 12,000-square-foot current working space, while management’s Rs 700 crore capacity plan sets the intended scale over about three to four years.
The next disclosed milestones are the availability of manufacturing space in January and February and the planned complete relocation by March-end or the first week of April. Investors can also watch whether Adisoft converts its approximately Rs 40 crore pipeline, executes orders within its usual three-to-four-month cycle, and expands staffing toward the facility’s 250-person seating capacity.