Allcargo Terminals plans up to Rs 650 crore growth deployment
Key highlights
- Allcargo Terminals said it could deploy up to Rs 650 crore over one to 1.5 years.
- Management identified about Rs 400 crore of capital expenditure across Farukhnagar, Chennai, a JNPT expansion, facility expansion and Speedy JNPT renovation.
- Allcargo Terminals said it could raise Rs 200 crore to Rs 250 crore of debt despite having no leverage at the time of the call.
- Q2 FY27 volume rose 12.6% year on year to 190,100 TEUs, while revenue rose 21.5% to Rs 252 crore.
powered by IRIS

Allcargo Terminals Limited said during its Q2 FY27 earnings call that it could deploy up to Rs 650 crore over one to 1.5 years for terminal expansion, new facilities and possible acquisitions, combining about Rs 400 crore available internally with an ability to raise Rs 200 crore to Rs 250 crore of debt.
Know Allcargo Terminals inside out
Results, valuation, peers and who's buying, in one view.
What is Allcargo Terminals' Rs 650 crore deployment plan?
Allcargo Terminals' management said it has the ability to deploy up to Rs 650 crore over one to 1.5 years, depending on how identified growth opportunities develop. The named pipeline includes Farukhnagar, Chennai capacity, a JNPT expansion, other facility expansion and renovation of the Speedy JNPT facility. Management put the capital-expenditure requirement for those named projects at about Rs 400 crore before discussing additional organic and inorganic possibilities.
The Rs 650 crore figure is potential capital-deployment capacity, rather than a disclosed approved budget for a single project. Management said it was examining other growth opportunities through mergers and acquisitions and organic expansion, but did not disclose targets, transaction values or schedules. It also said it was evaluating joint ventures and tie-ups that could increase volumes and market share, while stating that it could not discuss proposals until they are committed.
How will Allcargo Terminals fund its expansion?
Allcargo Terminals said it had no leverage at the time of the Q2 FY27 call and may add debt when growth opportunities arise. Management said it could move to a 1:1 level, without specifying the balance-sheet measure used for that ratio. Its stated debt-raising ability was Rs 200 crore to Rs 250 crore, alongside Rs 400 crore available internally, forming the funding framework behind the potential Rs 650 crore deployment.
Management did not announce a debt issue, borrowing facility or acquisition-financing arrangement during the call. Instead, it said the company would assess how opportunities evolve over the following six months before evaluating dividend payout. The stated Rs 400 crore capital-expenditure pipeline, possible acquisitions and other organic opportunities therefore remain relevant to any future decision on distributions.
Which Allcargo Terminals projects are moving toward operations?
Allcargo Terminals said its Farukhnagar ICD project remained on track. Management expects construction of the PFT to finish by the end of the current financial year, allowing limited PFT operations from the beginning of the following financial year while ICD construction continues. It expects ICD construction to be completed by the end of the third quarter of the next financial year and full-fledged ICD operations in the fourth quarter.
The company also said it was finalising land for a Chennai facility designed for 120,000 twenty-foot equivalent units, or TEUs, of capacity. Management expected land finalisation by the end of the month of the call, followed by a customs-clearance application. Construction was expected to start in the first quarter of the next financial year and take about nine months, with the facility located close to the Kattupalli and Ennore terminals.
Got a follow-up? Ask IRIS
What existing-terminal upgrades are part of Allcargo Terminals' plan?
Allcargo Terminals is renovating its Speedy JNPT facility, which management said is underutilised because of infrastructure-related reasons. The facility currently handles close to 8,000 TEUs, and management expects it to handle close to 18,000 TEUs once the upgrade is complete. The planned increase at the existing site is separate from the proposed 120,000-TEU Chennai facility and the Farukhnagar ICD project.
The upgrade also forms part of management's response to a temporary earnings factor in Q2 FY27. Allcargo Terminals reported earnings before interest, tax, depreciation and amortisation, or EBITDA, of Rs 3,366 per TEU for the quarter, with about Rs 400 to Rs 450 per TEU attributed to transshipment shipments. Management expects that transshipment benefit to continue in the short run, potentially up to the next quarter, before tapering as Gulf-related conditions normalise; it said greater Speedy JNPT utilisation could offset some of that effect.
What operating evidence supports Allcargo Terminals' capacity push?
Allcargo Terminals reported Q2 FY27 volume of 190,100 TEUs, up 12.6% year on year, while H1 FY27 volume reached 366,599 TEUs, up 10% from H1 FY26. Revenue rose 21.5% year on year to Rs 252 crore in Q2 FY27 and increased to Rs 466 crore in H1 FY27 from Rs 394 crore a year earlier. The faster quarterly revenue growth than volume growth coincided with higher rates, a better cargo mix and transshipment business, according to management.
Profitability also increased during the period, although management identified the transshipment contribution. Q2 FY27 EBITDA excluding other income was Rs 59 crore, up 45.9% year on year, while H1 FY27 EBITDA was Rs 106 crore against Rs 75 crore in H1 FY26. Q2 FY27 net profit was Rs 21 crore, up 85% year on year, and H1 FY27 net profit was Rs 27 crore versus Rs 20 crore in H1 FY26. Management said October delivered the highest volumes in Allcargo Terminals' history, supported by JNPA, Chennai and Kolkata.
Conclusion
Allcargo Terminals has presented a broad expansion and funding framework rather than a final, project-by-project investment programme. The company identifies about Rs 400 crore of capital expenditure across Farukhnagar, Chennai capacity, a JNPT expansion, other facility additions and Speedy JNPT renovation, while management said Rs 200 crore to Rs 250 crore of borrowing ability could take potential deployment to Rs 650 crore. The plan follows H1 FY27 volume growth of 10% to 366,599 TEUs and H1 FY27 EBITDA growth to Rs 106 crore from Rs 75 crore.
The next disclosed execution markers are completion of Farukhnagar's PFT construction by the end of the current financial year, Chennai construction beginning in the first quarter of the next financial year, and full Farukhnagar ICD operations in the fourth quarter of that following year. Management also said investors should allow the next six months for acquisition, joint-venture, tie-up and organic opportunities to develop before it evaluates dividend payout.