Amtech Esters starts Haryana resin output, capacity reaches 7,760 MTPA
Key highlights
- Amtech Esters began commercial production at its Asoda, Haryana facility on November 2, 2026.
- The new plant adds 4,800 MTPA of Unsaturated Polyester Resins capacity.
- Total resin capacity increased from 2,960 MTPA to 7,760 MTPA.
- Amtech Esters disclosed investment required at approximately Rs 2 crore, funded through internal accruals.
powered by IRIS

Amtech Esters Limited began commercial production at its Asoda, Haryana plant on November 2, 2026, adding 4,800 Metric Tonnes Per Annum (MTPA) of Unsaturated Polyester Resins (UPR) capacity and taking its total resin manufacturing capacity from 2,960 MTPA to 7,760 MTPA.
Know Amtech Esters inside out
Results, valuation, peers and who's buying, in one view.
What capacity did the Asoda plant add for Amtech Esters?
Amtech Esters added installed capacity of 4,800 MTPA of UPR at the new manufacturing facility in Asoda Todran, Jhajjar, Haryana. The company reported that installation and commissioning at the Balaji Industrial Area plant had been completed before commercial production started on November 2, 2026. UPR is the sole product capacity specified in the filing for this expansion.
The 4,800-MTPA addition is larger than Amtech Esters' former 2,960-MTPA resin capacity by 1,840 MTPA. Consequently, total installed resin capacity reached 7,760 MTPA, or about 2.62 times the pre-expansion level. The increase of 4,800 MTPA represents roughly 162% of the previous installed capacity, so the new facility more than doubled the scale of the resin manufacturing business.
The comparison is between installed capacity, rather than reported production or sales volume. Amtech Esters disclosed existing capacity utilisation of 89.11% in the annexure to its November 3, 2026 announcement, but did not provide a production-volume figure for the new 4,800-MTPA facility. Therefore, 7,760 MTPA states the combined rated manufacturing capacity after the commissioning event, not current output.
When did Amtech Esters start commercial production in Haryana?
Amtech Esters commenced commercial production at the Asoda facility with effect from November 2, 2026. The company made the disclosure to BSE Limited on November 3, 2026 under Regulation 30 of the Securities and Exchange Board of India Listing Obligations and Disclosure Requirements Regulations, 2015. It said the start followed the successful completion of installation and commissioning.
The November 2 start date completes the capacity-addition period identified in the disclosure. Amtech Esters referred to an earlier disclosure dated October 3, 2026, while its latest filing confirms that the proposed 4,800 MTPA had moved into commercial production one month later. The announcement does not state the date on which construction began, the duration of commissioning, or the number of days the plant had operated by November 3.
Commercial production is the operational milestone reported by Amtech Esters, whereas the 89.11% utilisation figure is presented as existing capacity utilisation in the annexure. The company did not disclose a utilisation percentage for the combined 7,760-MTPA capacity after November 2, 2026. It also did not state monthly output, initial orders, revenue contribution or product grades to be made at the Haryana site.
Got a follow-up? Ask IRIS
How much did the Haryana plant cost and how was it funded?
Amtech Esters disclosed investment required for the expansion at approximately Rs 2 crore and said it financed the project through internal accruals. This funding disclosure covers the 4,800-MTPA UPR capacity addition that was commissioned on November 2, 2026. The amount is described as approximate in the company's Regulation 30 annexure.
Internal accruals are the only financing mode identified by Amtech Esters for the Rs 2 crore project. The filing does not identify a separate bank borrowing, equity issue, external investor, government support or other financing instrument for the Asoda plant. It also does not split the approximate Rs 2 crore between land, building, equipment, installation or commissioning expenses.
The reported spending should be read alongside the disclosed capacity change from 2,960 MTPA to 7,760 MTPA. Amtech Esters did not provide a planned return, payback period, margin effect or revenue target associated with the new capacity. As a result, the filing establishes the funding source and approximate investment, but not a financial forecast from the November 2 production start.
Why did Amtech Esters expand its UPR manufacturing capacity?
Amtech Esters said the rationale for the 4,800-MTPA addition was to enhance manufacturing capabilities, increase UPR production capacity, meet growing market demand and support future business growth. These are management's stated reasons in the November 3, 2026 filing, rather than quantified market forecasts. The announced project is specifically a resin manufacturing expansion.
The numerical change gives the rationale greater operating scale: the Haryana plant's 4,800 MTPA exceeds the company's earlier 2,960 MTPA installed resin base. After commencement, Amtech Esters has 7,760 MTPA of total resin capacity, compared with 2,960 MTPA before the project. However, the company did not disclose the size of the market demand it cited, expected customer additions or the share of new capacity expected to be sold in any period.
The 89.11% existing-capacity-utilisation disclosure provides context for the decision to add 4,800 MTPA. It shows that the pre-expansion resin base was operating at the utilisation level reported in the annexure before the new plant started. Amtech Esters did not provide a target utilisation level for the larger 7,760-MTPA base, so the pace at which the additional capacity is absorbed remains undisclosed.
Conclusion
Amtech Esters has completed and started its Haryana UPR project, increasing installed resin capacity by 4,800 MTPA to 7,760 MTPA from 2,960 MTPA. The November 2, 2026 commencement follows completed installation and commissioning, while the company has put the approximate investment at Rs 2 crore, funded through internal accruals.
The next point to watch is utilisation of the added 4,800 MTPA and whether it translates into reported output or sales. Amtech Esters disclosed 89.11% utilisation for its existing capacity but gave no utilisation target, production forecast, sales estimate or further expansion schedule for the post-commissioning 7,760-MTPA resin business.