Annu Projects Limited expects stronger H2 FY27 execution recovery
Key highlights
- H1 FY27 revenue from operations was Rs 35.65 crore, compared with Rs 6.51 crore in H1 FY26.
- Annu Projects had a Rs 1,018.39 crore order book across 30 projects as of September 30, 2026.
- Telecom accounted for 81.23% of the order book, while BharatNet Kerala represented about Rs 741 crore.
- Trade receivables fell to Rs 142 crore from Rs 156 crore in March, and receivable days declined to 192 from 237.
powered by IRIS

Annu Projects Limited expects execution momentum to strengthen in Q3 and particularly Q4 FY27 after reporting H1 FY27 revenue from operations of Rs 35.65 crore, as monsoon disruption, project approvals and milestone billing constrained earlier execution. Management cited a Rs 1,018.39 crore order book but declined to provide a numerical FY27 revenue target.
Know Annu Projects inside out
Results, valuation, peers and who's buying, in one view.
Why does Annu Projects expect stronger H2 FY27 execution?
Annu Projects expects a stronger second half because its engineering, procurement and construction, or EPC, work and billing are historically concentrated in Q3 and Q4. Management illustrated this pattern with FY26 figures: H1 FY26 revenue from operations was Rs 6.51 crore, while full-year FY26 revenue was about Rs 241 crore.
The Q2 FY27 run rate was lower than Q1 because revenue from operations was Rs 15.74 crore in Q2 versus an implied Rs 19.91 crore in Q1, based on the Rs 35.65 crore H1 total. Chief Financial Officer Mayank Agarwal said monsoons halted trenching in several project areas, while Chairman and Managing Director Sanjay Kumar Sarraf said incomplete final milestones can prevent billing even where most site work has been completed.
Management also linked the first-half pattern to the timing of government approvals and fund clearances. Sarraf said government funding approvals can remain in process during Q1, while the rainy season becomes a major Q2 constraint for EPC projects, delaying milestones that would otherwise support certification and revenue recognition.
What is delaying project execution and billing?
Annu Projects said right-of-way permissions, local clearances, land availability, site handovers, coordination with government agencies, measurement and certification delays can affect execution, billing and margins. Agarwal said these conditions are relevant to both the pace of project delivery and the ability to maintain the H1 FY27 EBITDA margin of 19.64%.
The principal disclosed approval dependency is BharatNet Phase III in Kerala. As of September 30, 2026, approvals had been received for about Rs 260 crore of annual maintenance contract, or AMC, work, and execution had started on part of that scope; right-of-way approvals for the balance EPC construction work remained pending with the Department of Telecommunications.
Management said the Kerala package represented about Rs 741 crore of the Rs 1,018.39 crore order book. Roughly Rs 260 crore is AMC work spread across about 10 years, with around one to one-and-a-half years already completed, while the balance construction work can start only after the required right-of-way permissions are received.
How did Annu Projects perform in H1 FY27?
Annu Projects reported H1 FY27 revenue from operations of Rs 35.65 crore, up from Rs 6.51 crore in H1 FY26. EBITDA excluding other income was Rs 7 crore, and profit before tax turned to Rs 3.35 crore from a loss before tax of about Rs 10 crore in the corresponding half year.
Profit after tax was Rs 2.29 crore in H1 FY27, with a profit-after-tax margin of 6.4% and earnings per share of 45 paise. Management said the margin reflected the seasonal weighting of EPC execution toward the second half and said it expected profitability to improve as project activity picked up in H2.
In Q2 FY27, revenue from operations was Rs 15.74 crore and total income was Rs 16.54 crore, including other income of Rs 80 lakh. Q2 profit after tax was Rs 1.01 crore, compared with total income of Rs 3.70 crore and a loss before tax of Rs 3.48 crore in the corresponding quarter a year earlier.
Agarwal said management expected margins to be sustained around the H1 level, subject to approvals and operational factors. He did not offer FY27 revenue guidance, saying only that the company was confident of maintaining the growth momentum established over the previous three to four years.
Got a follow-up? Ask IRIS
Which projects and funding plans support H2 activity?
Annu Projects expects telecom to be the main contributor to FY27 execution because telecom accounted for 81.23% of the order book as of September 30, 2026. Sewerage represented 14.65%, railway signalling 2.49% and gas pipelines 1.63%, leaving the group’s near-term activity concentrated in telecom despite its four operating verticals.
The company disclosed a Rs 12.81 crore North East Frontier Railway contract to develop a 143-kilometre optical-fibre-cable backbone. It also signed a memorandum of understanding with GEIE to supply materials for a Rs 44.3 crore JVVNL rooftop-solar project covering 8,000 systems in Dausa, Rajasthan; management said its current role is primarily material supply.
As of September 30, Annu Projects had 30 ongoing projects with aggregate contract value of Rs 1,987 crore, compared with 23 projects as of June 30. Management said AMC assignments may extend for six to 10 years, whereas EPC projects typically have two-to-three-year execution periods, meaning the stated order book cannot be treated as one-year revenue.
The company received about Rs 175.06 crore from its initial public offering, including Rs 20.5 crore earmarked for issue expenses, Rs 115 crore for working capital and Rs 15.4 crore for machinery. By September 30, it had used about Rs 70.3 crore, including Rs 54.4 crore for working capital, and said planned machinery purchases include horizontal directional drilling machines for existing work and expansion into additional states.
Working-capital metrics improved during the period, according to management. Trade receivables declined to Rs 142 crore from Rs 156 crore in March, unbilled revenue decreased to Rs 59 crore from Rs 76 crore, and receivable days fell to 192 from 237; management also said it had collected about Rs 73 crore from the prior year through H1.
Conclusion
Annu Projects’ H2 expectation is based on the seasonal pattern of its EPC business and the potential release of delayed project milestones, rather than on a formal annual revenue forecast. H1 FY27 revenue increased to Rs 35.65 crore from Rs 6.51 crore a year earlier, while the Rs 1,018.39 crore order book provides a base for execution, although a substantial Kerala component has long-duration AMC characteristics or awaits approvals.
The next developments to watch are right-of-way approvals for BharatNet Kerala, Q3 and Q4 project execution and billing, and progress toward management’s expectation of an order book of around Rs 2,000 crore by the March-end under normal circumstances. Management also plans to use remaining IPO proceeds for working capital and machinery and said it did not currently anticipate additional funding requirements.