Annu Projects' ₹741 crore Kerala EPC awaits ROW approval
Key highlights
- BharatNet Phase III Kerala represented ₹741 crore of Annu Projects’ ₹1,018.39 crore order book at September 30, 2026.
- ₹260 crore of the Kerala package is AMC work expected to continue for roughly eight more years.
- Telecom accounted for 81.23% of Annu Projects’ order book at September 30, 2026.
- H1 FY27 revenue from operations was ₹35.65 crore, compared with ₹6.51 crore in H1 FY26.
powered by IRIS

Annu Projects Limited said on November 17, 2026 that ₹741 crore of its ₹1,018.39 crore order book at September 30, 2026 was BharatNet Phase III Kerala work, whose engineering, procurement and construction activity awaits right-of-way approvals. The package includes ₹260 crore of annual maintenance contract work spread over several years.
Know Annu Projects inside out
Results, valuation, peers and who's buying, in one view.
Why is Annu Projects' Kerala EPC work awaiting approvals?
Annu Projects’ Kerala EPC work is awaiting right-of-way, or ROW, permissions, which management said are required before construction on the balance portion can start. The company had received approvals for about ₹260 crore of annual maintenance contract, or AMC, work, and had begun execution on part of that scope as of September 30, 2026.
Management said it was in regular discussion with the Department of Telecommunications, or DoT, and hoped to receive the pending permissions shortly. It did not provide a date for approval or a completion schedule for the EPC portion, meaning the pace of construction depends on ROW clearances rather than the ₹741 crore contract value alone.
The chairman initially referred to the Kerala package as approximately ₹800 crore during the call, while the chief financial officer specified that BharatNet Kerala represented ₹741 crore of the ₹1,018.39 crore order book. The ₹741 crore figure accounts for about 73% of the reported order book across 30 ongoing projects at September 30, 2026.
How long will Annu Projects' Kerala order take to execute?
Annu Projects said the ₹260 crore Kerala AMC component is a long-duration contract, while the balance EPC work can begin only after ROW approvals. Management said about one to one-and-a-half years of the Kerala AMC work had already been completed, with the remaining activity expected to extend over roughly the next eight years.
The wider order book also combines AMC contracts with shorter-cycle construction work. Management said AMC assignments generally run for six to 10 years, whereas EPC projects are ordinarily delivered in two to three years. This difference means the ₹1,018.39 crore order book should not be viewed as a measure of revenue available within one financial year.
Management also cited approximately ₹150 crore of sewerage-related AMC work that would be completed over five to seven years. It said AMC work generates regular revenue of about ₹50 crore, while the remaining order book is expected to convert through project execution and milestone billing.
What does the order mix mean for Annu Projects' revenue?
Annu Projects said telecom represented 81.23% of its order book at September 30, 2026, making it the main source of potential execution and revenue. Sewerage represented 14.65%, railway signalling 2.49% and gas pipelines 1.63%, leaving the approval-dependent Kerala telecom package central to the group’s near-term project mix.
Revenue from operations reached ₹35.65 crore in H1 FY27, compared with ₹6.51 crore in H1 FY26, while profit after tax was ₹2.29 crore after a loss before tax of about ₹10 crore in the prior-year half. Management said the timing of approvals had affected the execution and revenue pace in FY27, and said the Kerala contract value should not be read as annual revenue potential.
Q2 FY27 revenue from operations was ₹15.74 crore and total income was ₹16.54 crore. Management attributed the sequential reduction from the roughly ₹20 crore Q1 revenue cited by an analyst to monsoon disruption, including stoppages in trenching work, and said EPC activity is usually weighted towards the second half.
Got a follow-up? Ask IRIS
Which factors could delay Annu Projects' project execution?
Annu Projects identified ROW permissions, local clearances, land availability, site handovers, government-agency coordination, and measurement and certification delays as factors that can affect execution and margins. These processes can defer physical progress or milestone billing even after a project is included in the ₹1,018.39 crore order book.
Management said its priorities for H2 FY27 included timely project delivery, improved milestone billing and receivable collection, and cost discipline. It expects business momentum to improve in Q3 and to be particularly strong in Q4 FY27 as projects progress and required approvals are received, but it gave no numerical FY27 revenue guidance.
The company had used about ₹54.4 crore of its ₹175.06 crore initial public offering proceeds for working capital by September 30, 2026. Of the total proceeds, ₹115 crore was planned for working capital, ₹15.4 crore for machinery and ₹20.5 crore for issue expenses; management said it did not anticipate an additional funding requirement at that point.
Can Annu Projects add orders while Kerala approvals remain pending?
Annu Projects’ management expects an order book of more than ₹2,000 crore by the March-end under normal circumstances, but this was an expectation rather than a reported award. The company said it had bid for about ₹3,000 crore of tenders, received clearance for about 9.3%, and expected letters of intent worth ₹125 crore during November 2026.
The company said it was the lowest bidder, or L1, on some sewerage, gas and railway orders, but had not disclosed them because letters of acceptance had not been received. Those projects were therefore not included in the ₹1,018.39 crore reported order book as of September 30, 2026.
Newer disclosed work is smaller than the Kerala package. Annu Projects secured a ₹12.81 crore North East Frontier Railway contract for a 143-kilometre optical-fibre cable backbone and signed a memorandum of understanding with GEIE for ₹44.3 crore of material supply under JVVNL rooftop solar projects covering 8,000 systems in Dausa, Rajasthan.
Conclusion
Annu Projects’ ₹1,018.39 crore order book provides a substantial project pipeline, but the timing of its conversion is uneven. The ₹741 crore BharatNet Kerala package combines ₹260 crore of multi-year AMC work with EPC activity that cannot fully begin until ROW permissions are granted, while telecom accounts for 81.23% of the total order book.
The next disclosures to watch are the DoT’s ROW approvals for the Kerala project, execution progress in Q3 and Q4 FY27, and the conversion of L1 positions into letters of acceptance. Management is targeting an order book of more than ₹2,000 crore by the March-end while maintaining that it will bid selectively within its internal margin thresholds.