CESC awards 153.7 MW Madhya Pradesh wind project package
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- Purvah Green Power awarded Venwind Refex Power a 153.7 MW Madhya Pradesh wind-project package on November 25, 2026.
- CESC disclosed an approximate 24-month execution period for the 153.7 MW project.
- The scope includes WTGs, tubular towers, land, BoP, installation, commissioning, STPT and PCVT.
- CESC said the 153.7 MW order is not a related-party transaction.
powered by IRIS

CESC Limited said its subsidiary Purvah Green Power Private Limited awarded Venwind Refex Power Limited a package to supply and execute a 153.7 megawatt, or MW, wind project in Madhya Pradesh, with the filing stating an approximate execution period of 24 months for the November 25, 2026 award.
Know CESC inside out
Results, valuation, peers and who's buying, in one view.
What wind-project order has CESC awarded?
CESC said Purvah Green Power issued a Letter of Award on November 25, 2026 to Venwind Refex Power for the supply of wind turbine generators and tubular towers, as well as execution of a 153.7 MW wind project in Madhya Pradesh. The disclosure was made by CESC under Regulation 30 of the Securities and Exchange Board of India, or SEBI, Listing Regulations.
The reported order size is 153.7 MW, and the filing describes it as covering both the supply of wind turbine generators, or WTGs, and execution of the project. CESC did not disclose a rupee value for the Letter of Award in its November 25, 2026 announcement, so the commercial scale stated in the filing is capacity rather than contract consideration.
Purvah Green Power is identified in the filing as a subsidiary of CESC, while Venwind Refex Power is identified as a subsidiary of Refex Industries Limited. The disclosure therefore sets out the companies’ stated roles clearly: Purvah Green Power is the entity issuing the award, and Venwind Refex Power is the domestic entity receiving it.
What does Venwind Refex Power have to deliver for CESC?
Venwind Refex Power is to supply WTGs and tubular towers and undertake end-to-end execution for the 153.7 MW Madhya Pradesh project. CESC’s filing specifically includes testing and pre-commissioning of the WTGs, commissioning of the WTGs, a Short Term Performance Test, or STPT, and a Power Curve Verification Test, or PCVT.
The package also includes land, balance of plant, or BoP, and installation works for the 153.7 MW project. BoP is the term used in the disclosure for project components outside the named WTGs and tubular towers; CESC did not break out individual quantities, sites, technical specifications or separate values for the land, BoP and installation elements.
The stated scope combines equipment supply with execution and testing rather than describing an equipment-only order. In particular, the November 25, 2026 disclosure lists the WTG supply, tubular towers, testing, commissioning, STPT, PCVT, land, BoP and installation in one award, indicating that these activities are included within the disclosed 153.7 MW package.
When is CESC's Madhya Pradesh wind project expected to be completed?
CESC disclosed an associated time period of about 24 months for the 153.7 MW order awarded on November 25, 2026. The filing uses “~ In 24 months”, which signals an approximate timeframe rather than a specific commissioning date or a sequence of dated construction milestones.
No quarterly schedule was provided for turbine delivery, tower supply, land work, installation, testing or commissioning within the stated 24-month period. As a result, the filing establishes the overall targeted duration for the 153.7 MW project but does not disclose when STPT or PCVT will occur, or when any individual portion of the project will be completed.
The completion timeframe should also be read alongside the breadth of the disclosed scope. The roughly 24-month period applies to a package that includes equipment supply and project execution, including land, BoP and installation works, rather than solely the delivery of WTGs for the Madhya Pradesh project.
Got a follow-up? Ask IRIS
How does this CESC order compare with the contract information disclosed?
The filing distinguishes between the project’s physical size and its commercial consideration: it reports a size of 153.7 MW but does not report a contract price. This means the announcement allows comparison of the order by installed-capacity measure, while a revenue, margin or cash-flow comparison cannot be made from the November 25, 2026 disclosure.
Within the disclosed package, the project has one stated capacity measure, 153.7 MW, and one overall time measure, about 24 months. CESC does not allocate MW capacity between separate phases, turbine supply and other execution work, nor does it provide separate completion periods for the WTG, tubular-tower, land, BoP or installation components.
The disclosed change is therefore the issuance of a Letter of Award by Purvah Green Power on November 25, 2026 for a defined 153.7 MW project package. The announcement does not provide an earlier capacity figure, a previous contract value, operating data or a baseline project schedule, so no before-and-after financial or operational comparison is supported by the filing.
Is CESC's wind-project award a related-party transaction?
CESC said neither its promoter, promoter group nor group companies has an interest in Venwind Refex Power, and it stated that the order is not a related-party transaction. The company specifically said the transaction does not fall within the definition of a related-party transaction under Regulation 2(1)(zc) of the SEBI Listing Regulations.
The recipient is described as a domestic entity and as a subsidiary of Refex Industries Limited. CESC’s November 25, 2026 disclosure does not identify any promoter or group-company interest in Venwind Refex Power, and accordingly does not provide an arm’s-length assessment because it says the transaction is not a related-party transaction.
The governance disclosure is separate from the project-execution disclosure. The 153.7 MW capacity, about 24-month period and end-to-end scope describe the contract package, while the related-party statement addresses the relationship between CESC’s promoter or group interests and the entity receiving the award.
Conclusion
CESC has disclosed that Purvah Green Power awarded Venwind Refex Power a 153.7 MW Madhya Pradesh wind-project package covering WTGs, tubular towers, land, BoP, installation, testing and commissioning. The filing provides a broad project scale and delivery scope, while leaving the order’s rupee consideration, technical configuration and component-level milestones undisclosed.
The next disclosed timeframe is execution in about 24 months, rather than a fixed commissioning date. Readers can watch for progress towards that stated period, including any future disclosure of delivery, testing, commissioning or commercial terms, which were not provided in this November 25, 2026 announcement.