Diamond Power Infrastructure’s ₹3,735 Crore Book Led by Conductors
Key highlights
- Diamond Power reported a ₹3,735 crore order book as of September 30, with conductors accounting for ₹1,718 crore or 46%.
- The order book includes a ₹974 crore AL59 conductor order for an 800 kV HVDC line.
- Q2 FY2026-2027 revenue was ₹1,050.07 crore and reported profit was ₹107.88 crore.
- Diamond Power disclosed a ₹1,349.11 crore Adani Energy Solutions order for 24,080 AL-59 high-performance conductors.
powered by IRIS

Diamond Power Infrastructure Limited reported a ₹3,735 crore order book as of September 30, led by ₹1,718 crore of conductor orders, while its Q2 FY2026-2027 revenue reached ₹1,050.07 crore and profit was ₹107.88 crore. The order mix highlights the company’s exposure to transmission and renewable-energy evacuation projects.
Know Diamond Power Infrastructure inside out
Results, valuation, peers and who's buying, in one view.
What is driving Diamond Power’s ₹3,735 crore order book?
Diamond Power’s ₹3,735 crore order book is primarily driven by conductors, which accounted for ₹1,718 crore, or 46%, of the total backlog. This category includes a ₹974 crore order for AL59 high-performance conductors for an 800 kV high-voltage direct-current, or HVDC, line.
Medium-voltage cables formed the second-largest category, contributing ₹1,328 crore, or 36%, of the book. The remaining balance comprised low-tension and data-centre cable orders. The disclosed order mix reflects demand for transmission equipment, underground distribution networks and renewable-energy evacuation infrastructure.
The company had earlier disclosed an order book of ₹3,688 crore as of August 11, 2026, including ₹1,000 crore of fresh wins since April. The September 30 figure indicates that the company continued to report a substantial backlog during the period.
Which orders expanded Diamond Power’s cable backlog?
Diamond Power secured several cable orders linked to electricity distribution and transmission projects. It received orders worth ₹116.49 crore, including GST, from Polite Powertech Limited for approximately 655 km of 11 kV XLPE power cables for underground distribution projects in Gujarat.
Of this ₹116.49 crore order, ₹79.83 crore was subject to receipt of a Letter of Award from the end utility. Polite Powertech was identified as an EPC contractor for Paschim Gujarat Vij Company Ltd and Uttar Gujarat Vij Company Ltd, and the stated completion timeline was within the next 12 months.
The company also disclosed a ₹76.06 crore order, including GST and on a variable-price basis, from a domestic EPC contractor. The work involves approximately 293 km of 66 kV extra-high-voltage underground power cables for a Gujarat transmission project. A separate ₹52.86 crore order was received from Aurionpro Solutions Limited.
Other disclosed wins included a ₹61.04 crore order from Purvanchal Vidyut Vitran Nigam Limited, a Uttar Pradesh government undertaking, for 33 kV HT XLPE cables. The company described the supply quantity as 250 km in a separate disclosure, where the order value was stated as ₹61.03 crore, inclusive of GST.
How did Diamond Power perform in Q2 FY2026-2027?
Diamond Power reported revenue of ₹1,050.07 crore and profit of ₹107.88 crore for Q2 FY2026-2027. These figures provide the reported quarterly financial context for an order book that was several times the stated quarterly revenue.
The company’s disclosed backlog spans conductors, medium-voltage cables, extra-high-voltage cables, low-tension cables and data-centre cables. Demand was specifically identified in 11-66 kV MV and EHV cables, AL59 conductors for 800 kV HVDC lines, and renewable-energy evacuation projects.
Diamond Power has stated that it fully implemented its resolution plan and exited the National Company Law Tribunal framework. That development is relevant because the current order disclosures show the company supplying projects across Gujarat, Uttar Pradesh, Mumbai and the broader transmission market.
Got a follow-up? Ask IRIS
Why are AL59 conductors important to Diamond Power?
AL59 conductors are important because the ₹974 crore 800 kV HVDC order is the largest identified conductor project in Diamond Power’s disclosed backlog. Management described it as the company’s largest FY2026-2027 order and said it would support prequalification credentials for tariff-based competitive-bidding, or TBCB, projects.
The company also reported securing a ₹1,349.11 crore order from Adani Energy Solutions Ltd for the supply of 24,080 AL-59 high-performance conductors. The supplied information does not specify whether this order is the same as, or separate from, the ₹974 crore AL59 HVDC order included in the September 30 order-book discussion.
Management said the company supplied more than 40,000 km of conductors to TBCB developers and Power Grid over the last year. It also referred to long-term backup arrangements with TBCB suppliers, under which their project wins can generate supply opportunities for Diamond Power.
How does the order mix affect Diamond Power’s operations?
Diamond Power’s order mix requires execution across distinct product categories and project timelines, from 11 kV underground distribution cables to 800 kV HVDC conductors. The disclosed Gujarat cable order from Polite Powertech is expected to be completed within 12 months, while other orders are linked to transmission and utility projects.
For investors, the key disclosed indicators are the ₹3,735 crore backlog, the 46% conductor contribution, and the large identified AL59 order. These data points show that conductors remain the largest part of the order book, while MV and EHV cable projects provide a significant second source of demand.
The company’s reported customers and counterparties include Adani Energy Solutions, Adani Electricity Mumbai, Gujarat Energy Transmission Company, Purvanchal Vidyut Vitran Nigam, Polite Powertech and Aurionpro Solutions. The order disclosures point to activity across private EPC contractors, state utilities and transmission-related customers.
Conclusion
Diamond Power’s reported ₹3,735 crore order book is led by ₹1,718 crore of conductor orders, with the ₹974 crore AL59 requirement for an 800 kV HVDC line forming a major identified project. Its ₹1,328 crore MV cable backlog and multiple utility-linked cable orders add diversification within the transmission and distribution equipment business.
The next areas to watch are execution of the Gujarat underground cable projects within their stated timelines, progress on orders subject to Letters of Award, and further order inflows in 66 kV EHV cables and AL59 conductors. Management has also identified TBCB-related prequalification as an expected benefit of the HVDC conductor project.