Elevate pipeline: Rs 646.5 crore cost, Rs 350 crore pending
Key highlights
- Elevate's development pipeline had an estimated project cost of about Rs 646.5 crore as of September 30, 2026.
- Pending capital expenditure across the pipeline was about Rs 350 crore.
- IIT Madras accounts for 1,878 of Elevate's 2,126 listed student-accommodation beds.
- The K-12 pipeline spans 3,83,000 square feet, including about 2,77,000 square feet at St. Andrews Suchitra.
powered by IRIS

ELEVATE reported an education development pipeline with an estimated cost of about Rs 646.5 crore and pending capital expenditure of about Rs 350 crore as of September 30, 2026, spanning 2,126 student-accommodation beds and 3,83,000 square feet of K-12 campus projects. IIT Madras accounts for 1,878 beds, while two Suchitra school developments cover about 2,77,000 square feet.
Know Elevate Campuses inside out
Results, valuation, peers and who's buying, in one view.
What does Elevate's development pipeline include?
Elevate's disclosed pipeline comprises two higher education institution, or HEI, accommodation projects and four K-12 campus projects. The accommodation projects provide for 2,126 beds at IIT Madras in Tamil Nadu and UPES in Uttarakhand, while the school projects cover 3,83,000 square feet across St. Andrews and Billabong High International School locations.
The portfolio has an estimated total project cost of about Rs 646.5 crore and pending capital expenditure of about Rs 350 crore, according to data as of September 30, 2026. Elevate does not disclose project-level costs, completion dates, funding mix or the allocation of the pending capital expenditure between student accommodation and K-12 campuses.
The two HEI projects differ materially in capacity. IIT Madras has 1,878 planned beds and UPES has 248, meaning IIT Madras represents about 88% of the listed 2,126-bed accommodation pipeline. The presentation separately identifies development potential for about 750 additional beds on existing UPES land, which is not included in the reported pipeline total.
How is Elevate's pipeline split between student housing and schools?
Elevate measures its two business verticals differently: the HEI accommodation pipeline is measured in beds, while the K-12 pipeline is measured in built-up area. The 2,126-bed accommodation programme spans two institutions, compared with four K-12 developments totalling 3,83,000 square feet as of September 30, 2026.
IIT Madras is the larger accommodation project at 1,878 beds, against 248 beds at UPES. The disclosed UPES potential of about 750 further beds on existing land is a development opportunity rather than part of the currently listed 2,126 beds, separating the reported project pipeline from potential future expansion.
The K-12 programme includes about 60,000 square feet at St. Andrews Keesara, about 1,82,000 square feet for St. Andrews Suchitra High School Block F, about 95,000 square feet for Suchitra future development, and about 46,000 square feet at Billabong High International School. These four projects add to the stated 3,83,000-square-foot K-12 total.
Suchitra's two developments total about 2,77,000 square feet, or roughly 72% of the K-12 pipeline by disclosed area. Keesara and Billabong together account for about 1,06,000 square feet, while Elevate labels the 95,000-square-foot Suchitra scheme as “Future Development” without providing a separate construction timetable or capital requirement.
Got a follow-up? Ask IRIS
What is the status of Elevate's IIT Madras project?
Elevate said it had completed pre-construction activities at IIT Madras, paving the way for construction to commence. The 1,878-bed project is a greenfield development under the public-private partnership, or PPP, mode and is the largest individual accommodation asset in the 2,126-bed pipeline.
Elevate also said the Ministry of Finance approved the release of viability gap funding, or VGF, for the IIT Madras project. The presentation does not state the VGF amount, the release date, or how the funding approval affects the portfolio-wide pending capital expenditure of about Rs 350 crore.
IIT Madras is the only listed pipeline asset with a construction-stage update in the supplied presentation. UPES is listed with 248 beds, while the four school-campus projects are listed by areas ranging from about 46,000 square feet to about 1,82,000 square feet, without equivalent progress descriptions.
The IIT Madras update therefore combines a defined 1,878-bed capacity with two disclosed milestones: completed pre-construction work and VGF release approval. Subsequent construction progress and VGF release details would show how the largest component of Elevate's student-accommodation pipeline is advancing.
How does the JGU proposal compare with Elevate's development pipeline?
Elevate presents the proposed 2,450-bed addition at O.P. Jindal Global University, or JGU, separately from its six-project development-pipeline table. The JGU proposal would take total beds after the transaction to about 10,500 under a 50-year contract tenure, while the September 30, 2026 pipeline table lists 2,126 development beds.
The JGU purchase consideration is Rs 1,350 crore, payable over nine years in 10 annual instalments, with about 40% payable in the first five instalments. That consideration exceeds the about Rs 646.5 crore estimated cost of the development pipeline, but the presentation identifies JGU as a post-Q2FY27 transaction update rather than a component of the pipeline cost figure.
JGU is a mandatorily residential, 100-acre campus in Sonipat, Haryana, established in 2009, according to the presentation. Elevate reports a stabilised yield on cost of about 9.3% on a net present value basis, alongside 6% same-store growth and take-or-pay guarantees from JGU.
The updates show two distinct expansion mechanisms. IIT Madras is a 1,878-bed greenfield PPP project with VGF approval, whereas JGU is a proposed 2,450-bed expansion with instalment-based purchase consideration and a 50-year contract tenure.
Conclusion
Elevate's reported education development programme combines 2,126 HEI accommodation beds and 3,83,000 square feet of K-12 construction at an estimated cost of about Rs 646.5 crore. IIT Madras supplies most of the listed accommodation capacity at 1,878 beds, while Suchitra's Block F and future development together represent about 2,77,000 square feet of the school pipeline.
The next disclosed matters to watch are the start and progress of IIT Madras construction following completed pre-construction work, and the release of approved VGF. Elevate also has about Rs 350 crore of pending capital expenditure, while the separate JGU proposal requires Rs 1,350 crore of consideration over nine years.