GAMCO expects Kolkata warehousing revenue starting 2028
Key highlights
- GAMCO expects Kolkata warehousing revenue to begin in calendar 2028.
- GAMCO's Dankuni, Delhi Road land has potential for 40 lakh square feet of warehousing development.
- GAMCO estimates about Rs 600 crore of capital expenditure and targets rental yields of 8% to 10%.
- GAMCO reported borrowings of Rs 327 crore and a debt-to-equity ratio of 1.6 times at September 30, 2026.
powered by IRIS

GAMCO expects Kolkata warehousing revenue to enter its books in calendar 2028 from a 40 lakh-square-foot logistics pipeline in Dankuni on Delhi Road, for which management estimates capital expenditure of about Rs 600 crore. Construction has started, and management is targeting rental yields of 8% to 10% from the development.
Know Gamco inside out
Results, valuation, peers and who's buying, in one view.
When will GAMCO's Kolkata warehouses start generating revenue?
GAMCO expects its Kolkata warehousing assets to begin contributing revenue in calendar 2028. Rajeev Goenka said on the call that construction had started and that revenues would begin hitting the books from 2028, while also saying the projects could start producing revenue within a year to a year and a half.
Management attributed the timetable to land and pre-construction approvals, describing them as the major requirements for the projects. It also said it was applying for approvals, without disclosing a project-level approval-completion schedule. GAMCO did not provide a leasing date, occupancy target, tenant name or warehouse revenue forecast for the 40 lakh-square-foot pipeline.
What is GAMCO building in Kolkata and why?
GAMCO is developing Grade A warehousing capacity in Kolkata because management said there was technically zero supply of such warehouses in the city. Goenka said 100 to 125 acres coming into play could provide immediate supply of 25 to 30 lakh square feet and that GAMCO was positioned to sign a couple of leases.
The 40 lakh-square-foot Kolkata pipeline is larger than the 6.25 lakh square feet leased by Amazon at the group-developed Nanak Logistics park in Lucknow. That park spans 63 acres, and Amazon occupies its leased space across 20 acres. GAMCO cited Nanak Logistics as evidence of the group’s logistics experience, but described it as a group asset rather than reporting it as a GAMCO operating asset.
How does GAMCO plan to expand beyond Kolkata?
GAMCO plans to expand warehousing into Tier 2 markets where management sees limited Grade A supply and less presence from large corporate funds and multinational institutions. Goenka named Guwahati, Patna and Jaipur, alongside Kolkata and Lucknow, as possible locations for logistics parks of 50 to 100 acres.
Management said the intended customers include existing clients that have expressed interest in expanding warehouse requirements in these locations. This approach differs from buying a completed Grade A warehouse in Mumbai, Delhi, Bengaluru or Chennai. Goenka said completed Tier 1 assets could offer returns on investment of 7% to 9%, whereas GAMCO’s Tier 2 development approach seeks returns on capital of 11% to 12%; those ranges were management’s assessment, not forecasts for any specific project.
Got a follow-up? Ask IRIS
What capital and balance-sheet capacity support the warehouse plan?
GAMCO estimates capital expenditure of about Rs 600 crore for the Dankuni, Delhi Road warehousing development and targets rental yields of 8% to 10%. Management also said it had tied up with one of the world’s largest fund houses to expand warehousing, but did not name the fund, disclose committed capital or specify ownership, borrowing or profit-sharing terms.
At September 30, 2026, GAMCO reported borrowings of Rs 327 crore, net worth of Rs 207 crore and a debt-to-equity ratio of about 1.6 times, compared with 1.7 times in March 2026. Net worth rose 24% from Rs 167 crore at March 2026, while total assets reached Rs 557 crore. Management said expansion could be funded through internal accruals, market borrowings and selective sales of real-estate or equity assets, while retaining 25% of the overall portfolio in liquid equity treasury.
GAMCO also said it had recycled capital through the sale of Visco Advisory, a warehousing asset sold to a global institutional fund for Rs 15.8 crore. Management said the sale generated a return of 158 times its investment over three years. The call did not say whether proceeds from that transaction have been allocated to the Kolkata project or quantify the portion of the Rs 600 crore requirement to be funded from asset sales.
When could GAMCO's other projects add revenue?
GAMCO has disclosed different planned revenue dates for residential, warehousing and hospitality assets, with warehousing expected in calendar 2028. Management said revenue from Uma Properties, its Alipore residential project, could start around March or April 2028, while it said the Port Blair hotel could begin contributing revenue by 2030.
The hospitality timetable contained more than one management indication. Goenka said construction at the Blissara Resorts project would start within a month and referred to revenue by 2030, while an earlier response indicated operations could begin in two to two-and-a-half years. GAMCO did not reconcile those timeframes. The project involves an 11-acre site in Port Blair planned for a 140-key upper-upscale hotel.
In the first half of financial year 2027, or H1 FY27, GAMCO reported consolidated revenue from operations of Rs 254 crore, up 79% year on year, and earnings before interest, tax, depreciation and amortisation of Rs 53 crore, a 21% margin. Second-quarter revenue was Rs 141 crore, versus Rs 114 crore in the June quarter and Rs 87 crore a year earlier. GAMCO did not report warehouse-specific revenue, profit or cash flow, so its current financial performance cannot be attributed to the Kolkata pipeline.
Conclusion
GAMCO’s stated calendar 2028 revenue target puts its Kolkata warehousing initiative ahead of its disclosed Port Blair hotel timetable and broadly alongside the expected start of revenue from the Alipore residential project. The warehouse plan combines 40 lakh square feet of development potential, an estimated Rs 600 crore capital requirement and management’s intended entry into under-supplied Tier 2 logistics markets.
The next points to watch are progress on approvals and construction, lease signings for the stated 25 to 30 lakh square feet of immediate Kolkata supply, and the funding structure for the Rs 600 crore project. Management’s plan to use internal accruals, selective asset monetisation and borrowings will also be relevant as borrowings stood at Rs 327 crore at September 30, 2026.