Key highlights
- GreenLeaf Envirotech expects Sayan Phase 1 to generate about Rs 80 lakh of monthly revenue at full capacity.
- Management targets about a 40% EBITDA margin and a five-year payback on the Rs 35 crore Phase 1 project.
- Sayan Phase 1 was 50% complete overall in September 2026, and commissioning moved from March 2027 to April 2027.
- GreenLeaf Envirotech said 60 members had committed around 75% of Phase 1 capacity, or about 3,000 of 4,000 machines.
powered by IRIS

GreenLeaf Envirotech Limited expects its 10 million litres a day (MLD) Sayan common effluent treatment plant (CETP) Phase 1 to deliver about a 40% earnings before interest, tax, depreciation and amortisation (EBITDA) margin and a five-year payback on Rs 35 crore of capital, with commissioning now planned for April 2027 rather than March 2027.
Know Greenleaf Envirotech inside out
Results, valuation, peers and who's buying, in one view.
What returns does GreenLeaf Envirotech expect from Sayan Phase 1?
GreenLeaf Envirotech expects the 10 MLD Phase 1 plant to generate about Rs 80 lakh of monthly revenue at 100% capacity, with an EBITDA margin of about 40%. Management said the Rs 35 crore project should have a payback period of around five years and a project internal rate of return (IRR) of around 18% to 20%.
Management identified power, chemicals and manpower as the main operating costs, estimated at Rs 45 lakh to Rs 48 lakh a month. Against the stated Rs 80 lakh monthly revenue at full capacity, those costs imply that the plant economics depend on both operating-cost control and the planned utilisation level. The company did not disclose a tariff, depreciation charge or interest cost for the facility on the call.
GreenLeaf Envirotech said 60 members had committed around 75% of Phase 1 capacity, which management described as about 3,000 machines compared with about 4,000 machines at 100% capacity. It expected to book the remaining capacity over the four to five months then remaining before the planned commissioning. The 40% margin estimate was maintained at the capacity levels discussed, but management did not give separate margin guidance for 75% utilisation.
The plant is part of GreenLeaf Envirotech's plan to increase recurring revenue over the next three to four years. Laboratory and consulting activities then contributed around 5% of revenue, while operation and maintenance contributed another 5%; management expects these services and environmental infrastructure, including the CETP, to reach around 25% of total revenue.
How is GreenLeaf Envirotech funding the Rs 35 crore project?
GreenLeaf Envirotech had invested about Rs 13 crore in Sayan Phase 1 by September 2026 and said Rs 22 crore remained to be invested before commissioning. Management's funding plan for the remaining amount comprised Rs 11.5 crore from a bank, Rs 5.5 crore from its existing business or equity, and around Rs 5 crore of member deposits committed but yet to be collected.
Member cash receipts were below the total deposits previously indicated by management. GreenLeaf Envirotech said it had received about Rs 3.5 crore from members, while the balance remained due for collection; management had earlier indicated approximately Rs 10 crore of membership deposits. The call did not reconcile the Rs 5 crore still to be collected within the stated remaining funding mix with the wider amount implied by deposits of Rs 10 crore less Rs 3.5 crore received.
The Sayan funding requirement sits alongside a Rs 122 crore order book reported as of September 30, 2026. Management planned to execute around 50% of that order book in H2 FY27, with the remainder scheduled for FY28 and FY29. It said smaller projects generally take around six months, larger projects around 24 months, and the average order-to-execution period is 12 to 18 months.
GreenLeaf Envirotech also said it had around 45 project managers and engineers able to execute approximately eight to 10 large projects in parallel. That capacity statement covers the wider project portfolio, while the Sayan project has a distinct Rs 22 crore remaining construction and funding requirement before its April 2027 target.
Got a follow-up? Ask IRIS
Why did GreenLeaf Envirotech move Sayan commissioning to April 2027?
GreenLeaf Envirotech moved the Phase 1 commissioning target by one month, from March 2027 indicated in its June call to April 2027, because of monsoon conditions and the equipment-delivery schedule. Management said the project was 50% complete on an overall physical-progress basis as of September 2026.
The remaining work included equipment supply and installation, as well as links for the collection and supply network. Management also cited consent to operate from the Gujarat Pollution Control Board as a remaining requirement, although it said it saw no regulatory obstacle at the time of the November 20, 2026 call.
The 50% overall-progress figure is not directly comparable with the 70% civil-work completion reported in June. GreenLeaf Envirotech said the June measure covered only civil work, whereas the September measure included civil work along with electromechanical equipment supply and installation. The lower overall percentage therefore reflects a broader project scope rather than a stated reduction in civil-work completion.
Across its broader project portfolio, management said around 20% of projects can be delayed by government approvals, land allocation or funding-related issues, while 80% have a clear path. These are portfolio-level observations rather than a revised forecast for Sayan, for which management maintained the April 2027 commissioning plan.
When could GreenLeaf Envirotech begin Sayan Phase 2?
GreenLeaf Envirotech said it would start planning Sayan Phase 2 when Phase 1 reaches around 90% utilisation, and it may begin construction three to four months into FY28. The wider Sayan plan is for 20 MLD in two 10 MLD phases, so Phase 1 member commitments and operating utilisation are the stated conditions for expansion.
Phase 2 would require additional capital beyond the Rs 35 crore Phase 1 project, according to management. GreenLeaf Envirotech said potential funding could include bank loans, contributions from existing and future member units, funds from current businesses and warrant-conversion proceeds. It expects around Rs 11.55 crore from warrants already in process and said it had no new equity plan beyond those warrants.
The expansion condition differs from the nearer-term Phase 1 position, where management said 75% capacity had been committed by 60 members. GreenLeaf Envirotech did not disclose a Phase 2 project cost, commissioning date, tariff, revenue estimate or EBITDA margin. The disclosed 40% margin, 18% to 20% IRR and five-year payback therefore apply to Phase 1 only.
Conclusion
GreenLeaf Envirotech has set out a defined Phase 1 economic case: Rs 80 lakh of monthly revenue at full capacity, Rs 45 lakh to Rs 48 lakh of monthly operating costs, an EBITDA margin of about 40% and a five-year payback on Rs 35 crore. The one-month move to April 2027 resulted from monsoon conditions and equipment delivery scheduling, while overall physical progress stood at 50% in September 2026.
The next disclosed milestones are equipment installation, collection and supply-network links, consent to operate, and collection of member deposits before the April 2027 commissioning plan. Management's stated trigger for Phase 2 planning is around 90% utilisation of the initial 10 MLD plant, with possible construction three to four months into FY28 and funding expected from debt, member units, business funds and Rs 11.55 crore of warrant proceeds.