Greenleaf 10 MLD CETP is 50% built, due April 2027
Key highlights
- Greenleaf reported Phase 1 of its Sayan textile CETP was 50% complete in September 2026.
- Memberships had committed 75% of the 10 MLD Phase 1 capacity in September 2026.
- Phase 1 has a disclosed project cost of Rs 35 crore and an April 2027 commissioning target.
- The Sayan facility is planned at 20 MLD across two 10 MLD phases.
powered by IRIS

Greenleaf Envirotech Ltd.’s first owned textile common effluent treatment plant, or CETP, had its 10 million litres per day, or MLD, Phase 1 50% complete and 75% of capacity committed as of September 2026. Greenleaf targets commissioning of the Rs 35 crore Phase 1 in April 2027 at Syadala, Surat.
Know Greenleaf Envirotech inside out
Results, valuation, peers and who's buying, in one view.
What is Greenleaf’s Sayan Textile CETP project?
Greenleaf’s Sayan Textile CETP is a planned 20 MLD wastewater-treatment asset for textile processing units at Syadala, Surat, split into two 10 MLD phases. The September 2026 update identifies the project as Greenleaf’s first owned infrastructure asset, rather than a customer-owned wastewater project delivered under its engineering and construction activities.
The asset is held through Greenleaf Eco Infra Pvt Ltd, a 100% owned subsidiary that Greenleaf describes as its infrastructure asset-holding and development vehicle. The corporate structure lists the 20 MLD Sayan Textile CETP as the subsidiary’s key asset, while Greenleaf’s other services include environmental consulting, laboratory testing, wastewater solutions and operations and maintenance, or O&M.
Greenleaf’s wastewater portfolio also includes effluent treatment plants, sewage treatment plants, and zero liquid discharge systems. The Sayan facility is specifically designed for textile processing units, whereas the company’s project examples include a 32 MLD sewage treatment plant, or STP, at Latur in Maharashtra and a 15 kilolitres per day effluent treatment plant at Gandhidham in Gujarat.
How far has Greenleaf built the first CETP phase?
Greenleaf reported Phase 1 construction at 50% complete as of September 2026, meaning the initial 10 MLD stage was halfway built on the presentation’s stated measure. It also reported membership commitments for 75% of Phase 1 capacity, while disclosing no construction or subscription status for the second 10 MLD phase.
The Rs 35 crore project cost applies only to the 10 MLD Phase 1. Greenleaf did not disclose the cost, construction date, commissioning target or membership level for Phase 2, and it did not provide the number of members, treatment tariffs, contract terms, funding mix or annual revenue associated with the committed Phase 1 capacity.
April 2027 is a commissioning target, not an operating milestone. Between the September 2026 update and the planned April 2027 commissioning, Greenleaf must complete the remaining 50% of Phase 1 construction and commission the plant; the presentation provides no intermediate timeline or stated commissioning conditions.
How does the CETP alter Greenleaf’s business model?
Greenleaf says its environmental-infrastructure model can generate recurring revenue through treatment charges, memberships and operational services. This differs from its turnkey project model, which covers design, engineering, procurement, construction, installation, commissioning and handover of wastewater treatment systems for customers.
The 100% ownership of Greenleaf Eco Infra Pvt Ltd keeps the 10 MLD Phase 1 asset within the group after commissioning. Greenleaf presents this ownership structure alongside its established consulting, laboratory, wastewater and O&M businesses, but it does not quantify expected CETP revenue, operating costs, margin or cash flow after April 2027.
The 75% membership commitment indicates pre-commissioning demand for the first 10 MLD stage, but it does not establish recognised revenue in the information disclosed. Greenleaf names treatment charges, memberships and operating services as revenue mechanisms, without publishing tariff levels, utilisation assumptions, customer identities or payment schedules.
Got a follow-up? Ask IRIS
What project experience has Greenleaf disclosed?
Greenleaf cites the 32 MLD STP at Latur, Maharashtra, as its largest engineering, procurement and construction, or EPC, project milestone in 2024. That project is 12 MLD larger than the planned 20 MLD Sayan CETP and more than three times the capacity of Sayan’s 10 MLD Phase 1, although Latur is a sewage treatment project rather than a textile CETP.
Other disclosed projects include a 16 MLD STP at Solapur, Maharashtra; 4.1 MLD and 2.9 MLD STPs at Vijaypur; and a 5 MLD STP at Sirohi, Rajasthan, from L&T Construction. The smaller 15 kilolitres per day industrial effluent plant at Gandhidham shows a different application and scale from the Sayan textile-processing facility.
Greenleaf was incorporated in 2010, has its headquarters in Surat and reports serving 12 states. Its laboratory has held National Accreditation Board for Testing and Calibration Laboratories, or NABL, accreditation under ISO/IEC 17025:2017 continuously since 2017, but these credentials do not provide construction or operating data for the Rs 35 crore CETP phase.
What financial context has Greenleaf provided for Phase 1?
For H1 FY27, Greenleaf reported revenue of Rs 28.62 crore, EBITDA of Rs 4.74 crore and profit after tax of Rs 3.04 crore. The Rs 35 crore Phase 1 project cost is Rs 6.38 crore higher than reported revenue for that six-month period, although the presentation does not disclose how the project will be financed.
Greenleaf also reported year-on-year revenue growth of 35.8% and EBITDA growth of 13.8% for H1 FY27. Revenue growth exceeded EBITDA growth by 22 percentage points on the company’s stated measures, while the source does not separate revenue, profit, capital expenditure or financing between the operating businesses and Greenleaf Eco Infra Pvt Ltd.
The presentation defines EBITDA as profit before tax plus finance costs plus depreciation, including other income. No CETP forecast for revenue, EBITDA, payback, debt servicing or profit after tax is disclosed, so the supplied information does not support a calculation of Phase 1’s financial return after the April 2027 target date.
Conclusion
Greenleaf’s September 2026 update shows measurable progress on its first owned infrastructure asset: the Rs 35 crore, 10 MLD Phase 1 was 50% built and 75% subscribed. The project adds an owned treatment facility intended to earn treatment charges, membership income and operational-service revenue alongside Greenleaf’s EPC, testing, consulting and O&M activities.
The next disclosed milestone is Phase 1 commissioning in April 2027. Investors can watch whether Greenleaf completes the remaining construction on schedule, turns committed capacity into operating activity, and discloses the tariff structure, financing, Phase 2 timetable and financial contribution of the 20 MLD facility.