GRSE sees post-FY27 revenue trough before FY29 NGC ramp
Key highlights
- GRSE said FY26 and FY27 are its peak revenue years before a natural trough.
- The Rs 32,308 crore NGC project is expected to contribute substantially from FY29.
- GRSE expects about 7.5% to 8% of NGC project cost to be recognised in FY28.
- GRSE reported Rs 2,900 crore of remaining NGOPV order book as on September 30.
powered by IRIS

Garden Reach Shipbuilders & Engineers Limited (GRSE) expects a natural revenue trough after FY27 because current peak-execution programmes will close before its Rs 32,308 crore Next-Generation Corvette (NGC) order contributes substantially in FY29. Management identified FY26 and FY27 as peak revenue years and said NGC revenue should begin modestly in FY28.
Know Garden Reach Shipbuilders & Engineers inside out
Results, valuation, peers and who's buying, in one view.
When does GRSE expect its revenue trough?
GRSE expects revenue to trough after its FY26 and FY27 peak years and before NGC makes a substantial contribution in FY29. Management described the transition as a natural consequence of the execution schedules for current programmes, while noting that revenue had risen at a compound annual growth rate (CAGR) of about 20% to 25% in recent years.
The earlier growth period reflected peak execution of the P-17 Alpha and Anti-Submarine Shallow Water Craft programmes. GRSE said P-17 Alpha would be completed in the current financial year, while the Anti-Submarine Shallow Water Craft programme would spill into the first quarter of FY28. The Next Generation Offshore Patrol Vessel (NGOPV) programme will continue until FY29, but management did not indicate that it would wholly replace the revenue contribution of the winding-down projects.
Why will NGC not immediately replace completed programmes?
NGC will begin generating revenue in FY28, but GRSE expects the initial contribution to be moderate at about 7.5% to 8% of the project cost. Management said this phase will principally cover design and procurement work, including information required from major original equipment manufacturers (OEMs), before ship construction advances.
GRSE said revenue recognition in warship building differs from industries with shorter production cycles. The largest revenue recognition typically occurs when physical construction is between 40% and 65% complete, after hull fabrication and during equipment installation, outfitting, integration and trials. The first NGC vessel is contractually scheduled for delivery in the latter half of calendar 2032, with the fifth vessel expected in 2035 or 2036.
Which projects can support GRSE before FY29?
GRSE expects NGOPV to support the transition because its revenue recognition is due to peak in the next financial year and its completion is scheduled for FY29. Management also identified the Ocean Research Vessel, Acoustic Research Ship and Multi-Purpose Vessel programme for a German client as projects that are maturing and expected to become more active in the next financial year.
The remaining order book disclosed as on September 30 shows the scale of that project mix. GRSE reported Rs 2,900 crore for NGOPV, Rs 1,565 crore for Anti-Submarine Shallow Water Craft, Rs 1,253 crore for the Multi-Purpose Vessel project and Rs 984 crore for Platform Supply Vessels. These balances provide work through the transition, although each is smaller than the Rs 32,308 crore NGC order.
Got a follow-up? Ask IRIS
What work remains after GRSE completes a vessel programme?
GRSE said a vessel delivery does not end all activity under a project because base and depot spares can represent up to about 15% of the project cost. Management said about 10% to 12% of a project cost may remain for execution for roughly one year after the main vessel programme is completed, while some 5% of spares may be delivered earlier.
For P-17 Alpha, which GRSE expects to complete in the current financial year, base and depot spares outstanding were about Rs 1,700 crore. Management cited Rs 465 crore of such spares for Anti-Submarine Shallow Water Craft and Rs 427 crore for NGOPV. These residual orders extend work beyond vessel delivery, but management still expects a trough before NGC reaches a larger construction phase.
Which new orders could change GRSE's revenue path after FY27?
GRSE has identified several defence opportunities that could add future work, although none of these opportunities was presented as an awarded order. Four bids that had already closed, including interceptor boats, water-jet fast attack craft and offshore patrol vessels, represented about Rs 25,000 crore of industry opportunities. Management said it conservatively expected GRSE to secure about one-fourth of that group, with results expected in the coming months.
The P-17 Bravo programme was the largest near-term opportunity discussed by management. GRSE expects the lowest-bidder, or L1, declaration during the current financial year and, on its conservative timeline, contract conclusion by the fourth quarter of FY28. Management said an L1 outcome could mean an order worth more than Rs 40,000 crore for GRSE, while an L2 outcome would entail a smaller allocation.
GRSE also cited live opportunities in the Landing Platform Dock project, with an approval value of about Rs 33,000 crore, and the mine countermeasure vessel project, with an approval value of about Rs 44,000 crore. Management said seven or eight defence projects, including closed and live requests for proposals, represented about Rs 1,72,000 crore in opportunities for Indian shipyards, subject to bidding outcomes and contract awards.
Conclusion
GRSE's stated outlook combines a large Rs 32,308 crore NGC order with a timing gap in its revenue profile. FY26 and FY27 are expected to be the high point for the current execution cycle, as P-17 Alpha and Anti-Submarine Shallow Water Craft approach completion. NGOPV, research vessels, export work and post-delivery spares can support activity, but management expects a natural trough before NGC becomes substantial in FY29.
The next milestones are bid results for approximately Rs 25,000 crore of closed tenders in the coming months and the expected P-17 Bravo L1 declaration during the current financial year. Management's stated conservative timetable places a P-17 Bravo contract conclusion by the fourth quarter of FY28, while NGC is expected to recognise about 7.5% to 8% of project cost in FY28 before its FY29 ramp-up.