HEC Infra Projects Limited wins Rs 136.29 crore Hindalco order
Key highlights
- HEC Infra Projects disclosed a Rs 136.29 crore Hindalco work order on 20 November 2026.
- The domestic order covers supply, erection and commissioning of a 400 kV transmission line.
- HEC Infra Projects stated an execution period of 17 months for the Hindalco contract.
- The company said the Rs 136.29 crore order is not a related-party transaction.
powered by IRIS

HEC Infra Projects has received a Rs 136.29 crore domestic work order from Hindalco Industries Limited to supply, erect and commission a 400 kV transmission line, with execution specified at 17 months, according to its 20 November 2026 disclosure to the National Stock Exchange of India.
Know HEC Infra Projects inside out
Results, valuation, peers and who's buying, in one view.
What contract did HEC Infra Projects receive from Hindalco?
HEC Infra Projects received a Rs 136.29 crore work order from Hindalco for a 400 kV transmission-line project. The company disclosed the award on 20 November 2026 under Regulation 30 of the Securities and Exchange Board of India, or SEBI, Listing Obligations and Disclosure Requirements Regulations, 2015. The announcement identifies Hindalco as the entity awarding the order and describes it as a domestic contract.
The Rs 136.29 crore amount is the broad consideration, or size, of the order reported in the annexure to the filing. The disclosure does not split the consideration between supply, erection and commissioning, and it does not provide payment milestones, advances, retention amounts or a variation mechanism. It therefore establishes the reported order value and scope, rather than a revenue-recognition or cash-collection schedule.
The annexure separately classifies both the awarder and the contract as domestic. Compared with an international award, the 20 November 2026 filing provides no overseas execution location, foreign-currency amount or international order component. Unlike a financial-results disclosure, it also gives no earlier-period order value or segment-level contract data, preventing a comparison with prior orders or business segments.
What work will HEC Infra Projects perform under the order?
HEC Infra Projects is contracted to supply, erect and commission a 400 kV transmission line for Hindalco. This description appears in both the filing's significant terms and conditions field and its nature-of-order field. The repeated disclosure confirms that the stated assignment covers all three activities under one Rs 136.29 crore work order.
The filing gives the electrical rating as 400 kV but does not state the line length, route, site, tower count, conductor specification or geographical location. It also does not identify associated substations or other packages. The disclosed scope is therefore limited to supply, erection and commissioning of the specified 400 kV transmission line.
The 20 November 2026 intimation calls the award a work order rather than a framework agreement or memorandum of understanding. It reports one Rs 136.29 crore consideration for the full assignment, with no separate amount for supply compared with erection or commissioning. The filing consequently does not allow a value comparison between the project's three named activities.
Got a follow-up? Ask IRIS
When is HEC Infra Projects expected to complete the Hindalco work?
HEC Infra Projects has a stated execution period of 17 months for the Rs 136.29 crore Hindalco order. The period appears in the annexure field asking when the order or contract is to be executed. The 20 November 2026 filing provides no separate commencement date, milestone timetable or calendar completion date.
The 17-month period is the only project timetable disclosed for the 400 kV assignment. The announcement does not say whether the duration runs from the work-order date, site handover, a notice to proceed or another contractual trigger. It also provides no quarterly delivery targets, construction phases or commissioning deadline apart from the overall 17 months.
The filing distinguishes between Rs 136.29 crore as the stated broad consideration and 17 months as the stated execution duration. It does not allocate the consideration across the 17-month period or indicate a financial-year contribution. Cost estimates, margins, completion penalties and cash-flow timing are also not disclosed in the 20 November 2026 announcement.
Is the Hindalco contract a related-party transaction?
HEC Infra Projects stated that none of its promoters or promoter group has an interest in Hindalco, which awarded the Rs 136.29 crore order. In the annexure, the response on promoter, promoter-group and group-company interest is marked “Not applicable.” The company made that confirmation in the 20 November 2026 disclosure.
HEC Infra Projects also stated that the 400 kV order does not fall within the purview of a related-party transaction. The annexure marks the related-party-transaction disclosure as “Not applicable,” rather than providing an arm's-length assessment. This is the company's stated classification of the Hindalco award for the purpose of its SEBI disclosure.
Management said the 400 kV assignment could enhance the company's track record and credentials and that it plans to bid for similar projects with private and government departments in other states. That is a disclosed future bidding plan, not a further order in addition to the Rs 136.29 crore Hindalco work order. The filing gives no number, timing, state, customer or prospective value for those potential bids.
Conclusion
The 20 November 2026 filing records a domestic Rs 136.29 crore work order for HEC Infra Projects covering supply, erection and commissioning of a 400 kV transmission line for Hindalco. It also specifies a 17-month execution period and records the company's confirmation that the award is not a related-party transaction and involves no promoter or promoter-group interest in the awarding entity.
The next disclosed matter to watch is execution over the 17-month period, as the filing provides no dated milestones or component-wise value allocation. Management's plan to bid for similar private- and government-department projects in other states is the other forward-looking item, although the disclosure gives no tender pipeline, award timetable or prospective contract value.