Airpro plans 1.25 lakh Jaipur capacity across five lines
MAX Plan at ₹4,999/yr
Find your next multibaggerBe a Pro Investor
Research stocks and track your picks on the go. Download the app.
Key highlights
- Airpro plans five Jaipur assembly lines with approximately 1.25 lakh units of annual capacity.
- Airpro’s Mumbai assembly line had annual capacity of 24,000 units and 100% utilisation in Fiscal 2026.
- Airpro proposes Rs 2 crore of net proceeds for machinery and Rs 4.97 crore for Jaipur construction.
- Airpro estimates Fiscal 2027 working-capital requirements of Rs 34.72 crore.
powered by IRIS

Airpro Technology India Limited plans five assembly lines at a Jaipur factory with approximately 1.25 lakh units of annual capacity, more than five times its single Mumbai line’s 24,000-unit annual capacity in Fiscal 2026; Rs 2 crore of net proceeds is allocated to machinery.
How much will Airpro’s Jaipur capacity increase?
Airpro expects its proposed Jaipur facility to have five assembly lines with aggregate capacity of approximately 1.25 lakh units a year after capital expenditure. That is 1.01 lakh units above the 24,000-unit annual capacity of the existing Mumbai line in Fiscal 2026, taking planned capacity to about 5.2 times the current annual level.
Airpro currently operates one assembly-and-testing line at a 1,400-square-foot facility in Goregaon East, Mumbai, where it primarily assembles and tests access-point devices. Chartered engineer Vikas V. Patankar certified the proposed Jaipur capacity on August 22, 2026, while the existing-capacity data was certified on November 16, 2026.
Airpro’s proposal concerns assembly, integration, testing and quality checks, rather than a disclosed plan to fabricate components. Under completely knocked down, or CKD, assembly, separate parts such as printed circuit boards, chipsets, antennas and casings are assembled and tested locally; under semi knocked down, or SKD, assembly, major modules arrive partly assembled for final assembly, software installation, testing and packaging.
Why is Airpro adding five Jaipur assembly lines?
Airpro is adding five Jaipur assembly lines after its Mumbai component-assembly line operated at 100% utilisation in Fiscal 2025, Fiscal 2026 and the period ended September 30, 2026. Output was 24,000 units against 24,000 units of annual capacity in each of Fiscal 2025 and Fiscal 2026, and 12,000 units against 12,000 units for April to September 2026.
The utilisation record changed from Fiscal 2024, when the Mumbai line assembled 18,500 units against annual capacity of 24,000 units, or 77% utilisation. The capacity figures assume one eight-hour shift a day and 25 working days a month, meaning the Jaipur target depends on completing the building, installing machinery and securing components, labour and orders for five lines.
Airpro sells wireless access points, wireless local area network controllers, gateways, Ethernet switches, outdoor wireless bridging products, 4G and 5G customer-premises equipment, and fibre-access equipment. The prospectus does not state how much of the proposed 1.25 lakh-unit capacity will be allocated to each category, so the mix of products made at Jaipur remains unspecified.
What will Airpro spend on Jaipur machinery and construction?
Airpro estimates machinery expenditure of Rs 2.04 crore, including Rs 2 crore from net offer proceeds and Rs 3.79 lakh from internal accruals or borrowings. The equipment plan comprises five assembly lines costing Rs 1.68 crore, 100 electrostatic-discharge-safe worktables costing Rs 18.93 lakh, and Rs 12.50 lakh of conveyor-line installation fees.
Airpro’s June 25, 2026 machinery quotation also covers 100 bench-top ion fans, 100 wrist-strap line monitors and worktable installation. The company says the equipment will be new and company-owned; Goods and Services Tax on procurement is excluded from the Rs 2.04 crore estimate and is to be funded from internal accruals.
Airpro estimates Jaipur building expenditure of Rs 4.99 crore, of which Rs 4.97 crore is proposed from net offer proceeds and Rs 1.58 lakh from internal accruals or borrowings. The estimate covers site development, civil structure, storage and operational support at Plot No. F-23, Shri Ram Janki Industrial Area, Kunjbiharipura, Jaipur, including Rs 45.34 lakh for sanitary and electrical work.
The company received a Rs 3.97 crore site-development and civil-work quotation from Ritekch Vikas Vijay dated May 24, 2026. Any construction price escalation above the quotation, along with applicable taxes and interest, is to be borne from internal accruals rather than offer proceeds, increasing the project’s reliance on funds outside the stated IPO allocation.
Got a follow-up? Ask IRIS
How will Airpro finance the Jaipur factory and working capital?
Airpro proposes to use Rs 7.57 crore of net offer proceeds for Jaipur machinery, land and construction: Rs 2 crore for machinery, Rs 60 lakh for land and Rs 4.97 crore for construction. These allocations represent about 30.4% of the stated Rs 24.91 crore net proceeds, with the balance directed to working capital and general corporate purposes.
The Jaipur plot is covered by a lease agreement dated April 23, 2026 with Rajasthan State Industrial Development and Investment Corporation Limited. The land cost is Rs 1.11 crore, and Airpro says it had deposited Rs 30.37 lakh as of the prospectus date; of the Rs 80.99 lakh then remaining, Rs 60 lakh is proposed from net proceeds and the balance from internal accruals or borrowings.
Airpro also plans Rs 13 crore from net proceeds for working capital, with Rs 8 crore scheduled for Fiscal 2027 and Rs 5 crore for Fiscal 2028. Its estimated working-capital requirement is Rs 34.72 crore at March 31, 2027, compared with Rs 20.83 crore at September 30, 2026, reflecting projected inventories of Rs 21.50 crore and trade receivables of Rs 17.53 crore.
Airpro states that estimates other than machinery costs are based on management estimates and have not been appraised by a bank or financial institution. If net proceeds fall short or costs rise, Airpro may use internal accruals, seek debt financing or reallocate proceeds in accordance with applicable law.
When could Airpro’s Jaipur factory be ready?
Airpro says Jaipur factory construction could be completed by April 30, 2027 if its equity-share listing takes place on October 15, 2026. The company gives an overall construction period of about six to eight months, subject to timely availability of materials, labour and other required resources.
The disclosed schedule includes ground-floor work in January 2027, first-floor activities during February and March 2027, and painting and plaster-of-Paris work through April 2027. Airpro says it would apply for Shops and Establishment registration after building construction; it also says no approval is currently required because it is in the white category and acquired the land from Rajasthan State Industrial Development and Investment Corporation Limited.
The stated April 30, 2027 date is a construction target, not a disclosed commercial-production date. Airpro says actual utilisation of the proposed facility can be assessed only after machinery installation, initial trial runs and the commencement of regular production.
Conclusion
Airpro’s Jaipur project would increase planned annual assembly capacity from 24,000 units at one Mumbai line to approximately 1.25 lakh units across five lines. The expansion follows 100% assembly utilisation in Fiscal 2025, Fiscal 2026 and the period ended September 30, 2026, but the additional capacity remains contingent on construction, equipment installation and operating ramp-up.
The next disclosed milestone is the targeted April 30, 2027 completion of the Jaipur building, conditional on the stated listing assumption and resource availability. Progress on machinery installation, trial runs, production commencement, construction costs and the Rs 34.72 crore Fiscal 2027 working-capital plan will determine how quickly Airpro can use the proposed capacity.