- Jash Engineering retained its Rs 875 crore FY27 revenue target on November 5, 2026.
- Jash Engineering reported a Rs 955 crore consolidated order book, including Rs 625 crore for projects outside India.
- Jash Engineering reported H1 FY27 consolidated revenue of Rs 351 crore, up 20% year on year.
- Jash Engineering said export transit delays could affect deliveries needed to meet FY27 guidance.
powered by IRIS

Jash Engineering Limited, referred to as Jash Engineering, retained its Rs 875 crore FY27 revenue target on November 5, 2026, supported by a Rs 955 crore consolidated order book, but management said longer transit times for exports from India could affect deliveries required to achieve the target.
Know Jash Engineering inside out
Results, valuation, peers and who's buying, in one view.
Can Jash Engineering meet its Rs 875 crore FY27 revenue target?
Jash Engineering said it remains confident of reaching Rs 875 crore of FY27 revenue if transit-related issues affecting exports from India improve. Management retained the guidance announced at the beginning of the year after reporting consolidated revenue of Rs 351 crore for H1 FY27, up 20% year on year. Reaching the target would require Rs 524 crore of revenue in the second half.
The disclosed uncertainty concerns delivery timing rather than an announced cancellation or reduction in the order book. Management identified transit time for products exported from India to international markets as a key challenge and said the situation had become difficult. The call did not quantify delayed shipments, name affected customers or provide an expected resolution date.
The first-half result provides the basis for management's outlook, although the required second-half revenue is higher than H1 revenue. Consolidated revenue was Rs 195 crore in Q2 FY27, up 22% year on year, while earnings before interest, tax, depreciation and amortisation, or EBITDA, rose 23% to Rs 27.3 crore. Profit after tax, or PAT, increased 30% to Rs 14.3 crore in Q2 FY27.
What is in Jash Engineering's Rs 955 crore order book?
Jash Engineering's Rs 955 crore consolidated order book is weighted toward projects outside India, which account for Rs 625 crore, compared with about Rs 330 crore for domestic projects. The company said the consolidated amount is calculated after deducting inter-company orders. International projects are therefore the larger component of the reported backlog, making export transit conditions relevant to delivery execution.
Management also cited prospective order additions. It said orders worth about Rs 46 crore had already been negotiated and were expected to be received during the month of the call. A further Rs 129 crore of orders was under negotiation and was expected to be finalised during the quarter. These are expected inflows rather than part of the reported Rs 955 crore consolidated order book.
The subsidiary-level order-book amounts exceed the consolidated figure in aggregate because the Rs 955 crore total excludes inter-company orders. Jash Engineering reported Rs 561 crore for Jash Engineering, Rs 391 crore for Rodney Hunt, Rs 27 crore for Mahr, Rs 31 crore for Waterfront and Rs 32 crore for Jash Process Equipment. Management did not provide a schedule for converting these orders into FY27 revenue.
Got a follow-up? Ask IRIS
Which businesses support Jash Engineering's FY27 outlook?
Jash Engineering said its FY27 revenue outlook comprises Rs 530 crore for Jash Engineering, Rs 330 crore for Rodney Hunt, Rs 15 crore for Mahr, Rs 60 crore for Waterfront and Rs 40 crore for Jash Process Equipment. Jash Engineering and Rodney Hunt together account for Rs 860 crore of the stated business-level figures, placing most of the planned revenue delivery in those two operations.
The five business targets total Rs 975 crore, which is Rs 100 crore above the separately reiterated consolidated FY27 revenue target of Rs 875 crore. Management said the breakup remained unchanged but did not explain the difference between the component targets and consolidated guidance. The transcript therefore leaves the treatment of consolidation or inter-company revenue in those targets unresolved.
First-half performance varied across the businesses. Jash Engineering reported revenue of Rs 227 crore, compared with Rs 208 crore a year earlier, a 9% increase, while its PAT rose 18%. Rodney Hunt recorded 17% revenue growth but slightly negative PAT, while Waterfront's revenue rose 8% to Rs 23 crore and its PAT remained positive.
Jash Process Equipment reported revenue of Rs 21 crore, down from Rs 25 crore a year earlier, and slightly negative PAT. Management linked the decline to a low opening order book after order-acquisition setbacks in the prior year. It said it expected some major orders in the second half and was integrating costing processes and manufacturing selected products at Jash Engineering's Indore premises.
What are management's margin and capacity plans?
Management said Jash Engineering has historically operated at an EBITDA margin of about 18% to 20%, with 18% described as a normal level in recent years. It said tariffs and war-related effects had affected margins in 2022 and the previous year, while its longer-term target is an EBITDA margin of about 21% to 23% as international businesses scale.
The plan depends partly on volume targets for overseas operations. Management cited a target of GBP 10 million to GBP 12 million for Waterfront in the United Kingdom and USD 50 million for the US business over the next one to two years. It said revenue growth should produce operating leverage because fixed costs are not expected to rise at the same pace.
Jash Engineering is also considering another US plant as local manufacturing requirements increase and labour availability remains a challenge at its existing location. Management said the India-US mix had shifted from about 75:25 or 70:30 previously to closer to 50:50. It illustrated the change with an order book of about 40 million, comprising roughly 22 million from India and 18 million from the US.
Conclusion
Jash Engineering's maintained Rs 875 crore FY27 target is supported by a Rs 955 crore consolidated order book and H1 FY27 revenue growth of 20% to Rs 351 crore. However, the company needs Rs 524 crore in second-half revenue, and management has identified export transit delays as a delivery-timing risk for a backlog that includes Rs 625 crore of projects outside India.
The next indicators are whether export transit conditions improve, whether the about Rs 46 crore of negotiated orders and Rs 129 crore under negotiation are converted into orders, and whether management clarifies the gap between Rs 875 crore of consolidated guidance and Rs 975 crore of business-level targets. Management also expects second-half orders to improve Jash Process Equipment's order book after its revenue declined from Rs 25 crore to Rs 21 crore.